1.10 Project Scheduling in Software Engineering.pptx

168 views 66 slides Aug 29, 2024
Slide 1
Slide 1 of 66
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66

About This Presentation

Project Scheduling in Software Engineering


Slide Content

Project Scheduling Unit-I

Work Breakdown Structure Work Breakdown Structure (WBS) involves  breaking down a project into smaller, more manageable components , allowing for better understanding and control of the project scope

A Product Breakdown Structure (PBS ) is  a hierarchical structure of things that the project will make or outcomes that it will deliver . It can be thought of as the project “shopping list.” It decomposes a "Main Project Product" into its constituent parts in the form of a hierarchical structure. A Product Breakdown Structure (PBS

Critical Path Method (CPM) is a method used in project planning, generally for project scheduling for the on-time completion of the project. It helps in the determination of the earliest time by which the whole project can be completed. There are two main concepts in this method namely critical task and critical path. Critical Path Method (CPM) It is a sequence of critical tasks/activities and is the largest path in the project network. It gives us the minimum time which is required to complete the entire project . The activities in the critical path are known as critical activities and if these activities are delayed then the completion of the entire project is also delayed.

Benefits of using the critical path method in project management: Show the project schedule visually. Highlight important tasks with CPM. Use CPM to find and handle risks. CPM helps the project team communicate better.

How to find the critical path in a project : Step 1: Identify all tasks required to complete the project Step 2: Determine the sequence of tasks Step 3: Estimate the duration of each task Step 4: Draw a network diagram Step 5: Identify the critical path Step 6: Calculate the float Step 7: Monitor the critical path Rules for Designing the Activity-on-Node network diagram: A project network should have only one start node A project network should have only one end node A node has a duration Links normally have no duration “Precedents” are the immediate preceding activities Time moves from left to right in the project network A network should not contain loops A network should not contain dangles

Activity Duration (in weeks) Precedents A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E,F H 2 C,D Activity label  is the name of the activity represented by that node. Earliest Start  is the date or time at which the activity can be started at the earliest. Earliest Finish  is the date or time at which the activity can be completed at the earliest. Latest Start  is the date or time at which the activity can be started at the latest. The latest Finish  is the date or time at which the activity can be finished at the latest. Float  is equal to the difference between the earliest start and latest start or earliest finish and latest finish.

Backward Pass in Critical path in project management:

Forward Pass in Critical path in project management:

Backward Pass in Critical path in project management:

Identifying Critical Path:   Activity float is the difference between an activity’s Earliest start and its latest start date or the difference between the activity’s Earliest finish and its latest finish date. it indicates how much the activity can be delayed without delaying the completion of the entire project . If the float of an activity is zero, then the activity is critical and must be added to the critical path of the project network. In this example, activities F and G have zero float and hence, are critical activities.
Tags