#174 Logistic Plan for site including silt trap design

khirrahman47 12 views 3 slides Jun 05, 2024
Slide 1
Slide 1 of 3
Slide 1
1
Slide 2
2
Slide 3
3

About This Presentation

Logistic plan sample


Slide Content

SITE LOGISTIC LAYOUT – 174 UNITS ADERYN SETIA ALAM SARI Meeting room Site Office C.O.W Office Rest area LEGEND Office Rest Area Toilet Carpenter Yard Barbender Yard Sub-con Store Soil Stock Pile Area Temporary Storage Area Earth Drain Culvert Check Dam Septic Tank Silt Trap Discharge to existing silt pond Revision No. : 0 Date : 15/05/2023 60m 15m 60m 15m 30m 10m 30m 30m A1 A2 B1 & B2 A3 B3

Silt Trap Specification 3m 6m Silt Trap (Depth 1.5m) Sand Bags 1m X 1m X 1.5m 4inch pipe X 2nos Discharge to existing silt pond Earth drain from Aderyn 174#

Septic Tank Specification