1st week report on indode


Slide Content

1st Week Of MAY Weekly Report Date: APP 26-MAY 03 / 2024 G.C INDODE Maintenance center Mechanical workshop

CONTENTS INTRODUCTION COMPLETED WORKS STUMBLING BLOCKS PLAN FOR NEXT WEEK

INTRODUCTION Mechanical Workshop is responsible for the maintenance of machine, machineries and equipment's such as railcars, tamping machines, stabilizer machine, ballast collector machine, generators, pumps, Hydraulic track lining machine, cranes, Internal combustion Track wrench and Vehicles . Besides, it builds and maintains different structures by welding.

INTRODUCTION Based On New organizational Structure Mechanical Maintenance Workshop Has 3 Teams Machinery Maintenance Mechanical Maintenance Large Machine Operation 1 2 3

STAFF SIZE S/N Staff position Number of staffs Remark 1 Mechanical workshop manager 1 2 Team leaders 3 1 vacant 3 Operator, Tamping Machine 6 4 vacant 4 Operator, Stabilizer Machine 1 1 vacant 5 Operator, Ballast distributor 1 1 vacant 6 Technician, Electrical 1 7 Welder 4 1 vacant 8 Electrical Mechanical Fitter 4

STAFF SIZE continued … S/N Staff position Number of staffs Remark 9 Assistant Technician, Mechanical 4 10 Technician, Vehicle Maintenance 2 11 Technician, Generator Maintenance 2 1 vacant 12 Technician, Pump Maintenance 2 2 vacant 13 Technician, Gantry Crane Maintenance 2 2 vacant 14 Technician, Mechanical 4 2 vacant Total no of staffs 37 15 vacant

Completed works S/N Equipment, Vehicles or machinery's name User unit Maintenance highlight Quantity of equipment/vehicle/ machinery maintained Spare s and materials used 1 ETS rail car indode Engine support maintenance 1 Modefic rubbers 2 Civil ND4 tamping machine indode Overall maintenance and service 10 5 motor assembled, 6 spark plug, 6 carburetor 3 Civil railcar indode Air compressor maintenance 1 2 gasket makers, welding Mechanical maintenance workshop Weekly Report in MAY. 2024

Completed works S/N Equipment, Vehicles or machinery's name Equipment, Vehicles or machinery's name Use unit Maintenance highlight No of equipment/machinery maintained Spare and material used 4 YD22 tamping machine indode Maintenance and engine service 4 Engine oil, 5 ETS railcar mieso Maintenance of clutch, engine support 1 Pressure plate, Mechanical maintenance workshop Weekly Report in MAY.2024

Completed works S/N Equipment, Vehicles or machinery's name Equipment, Vehicles or machinery's name Use unit Maintenance highlight No of equipment/machinery maintained Spare and material used 6 prado indode Changed engine oil, wheel inspected 1 5L ENGINE OIL, oil filter, fuel filter 7 CIVIL railcar matahara Gearbox leakage maintenance 1 - 8 Civil railcar adama Compressor overhaul 1 Gasket maker Mechanical maintenance workshop Weekly Report in MAY.2024

Completed works S/N Equipment, Vehicles or machinery's name Equipment, Vehicles or machinery's name Use unit Maintenance highlight No of equipment/machinery maintained Spare and material used 9 Half crane (damp truck) indode maintenance 1 15L engine oil, 1 oil filter 10 rail crane adama Starting failure 1 2 battery Mechanical maintenance workshop Weekly Report in MAY.2024

Planned vs completed Mechanical maintenance workshop Weekly Report in MAY.2024 S.N Equipment/ machinery/ vehicle Requested Completed PERCENTAGE 1 TRACK JACK YQB 4 - 0% (spare parts issue) 2 prado 1 1 100% 3 YD 22 tamping machine 4 1 100% 4 Rail crane 1 1 100% 5 ND 4 TAMPING MACHINE 10 10 100% 6 Half crane Truck 1 2 100% 7 railcar 4 4 100%

Pictures during maintenance work

Mechanical maintenance workshop. Work Plan For The Next Week 1. Emergency maintenance of vehicles, generators and other machines will be done according to the priority given in consideration. 2. Maintenance of one starter motor , adama railcar and, mieso railcar, shifting of mechanical spares from the container to store.

Mechanical maintenance workshop. stumbling blocks 1. Delay of supply of spare parts is a serious issue. Most of the time the delay is significantly too much. 2. Staff issue skill gaps staffs not recruited in some critical positions

Thanks _____The End_____ Mechanical Maintenance Workshop