240810 Weekly Earthwork progress bulan juni

ronifauzi2 7 views 6 slides Sep 07, 2024
Slide 1
Slide 1 of 6
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6

About This Presentation

Progress pekerjaan tanah


Slide Content

1
10
th
August 2024 (Week 2)
Pani Project Execution Report Clearing Priority
Earth works

2
Heap Leach –Clearing Priority Plan
N
HEAP LEACH STAGE
1
CELL 1
CELL 2
ADR
PLS
ILS
SWP
ECD
OPP
OFFICE
COMPLEX
HEAP LEACH NORTHERN
ROAD (PART 1 & 2)
MINE HAUL ROAD
1
DAM4
MAGAZINE
DAM3
TEMP. DIVERSION
CHANNELPriority  Area Category Start Finish
1 OPP Earthwork Dec-23 Nov-24
1 MHR Earthwork Dec-23 Dec-24
1 SWP ECD Starter Embankment Earthwork Aug-24 Nov-24
2 HLP Stage 1 Temp. Diversion ChannelEarthwork Aug-24 Nov-24
2 HLP Stage 1 Earthwork Aug-24 Jul-25
2 Office Complex Pad Preparation Earthwork Aug-24 Nov-24
3 ADR Earthwork Sep-24 Feb-25
4 PLS ILS Pond Earthwork Oct-24 Nov-25
5 SWP - DAM 2 Earthwork Nov-24 Mar-25
5 Magazine Earthwork Nov-24 Jun-25
5 HLP North Road Part 1 Earthwork Nov-24 Feb-25
6 HLP North Road Part 2 Earthwork Feb-25 Sep-25
6 DAM 4 - RWD Earthwork Feb-25 Apr-25
6 SAR - Pioneer to HLP Pad Earthwork Feb-25 Jun-25
6 SAR - to ADR Earthwork Feb-25 May-25
7 ECD - DAM 1 Earthwork Mar-25 Jun-25
8 DAM 3 - Sediment Control Earthwork Apr-25 Jul-25
HEAP LEACH STAGE 1 CONSTRUCTION
1
1
1
2
2
2
3
4
5
5
5
6
6
6
SAR (PIONEER –HLP)
6
SAR ADR
7
8
Starter DAM is
now priority
Starter DAM is
now priority
Reference;
Pani Construction Schedule_
July 24.pdf
Upper Diversion
Channel
Priority
Priority

3
Heap Leach –Clearing Priority Plan
N
11 Ha
1.Clearing area HPHD release start at 19Jul24 (Area PAD-MIA-Stock Top Soil) –Up to W3 Aug 24
2.Clearing starter DAM & ADR –Up to W2 Sep 24
MHR
OPP
HEAP LEACH
ADR
MAGAZINE
HPHD
12 Ha
10 Ha

4
Heap Leach –ProgresClearing W2 August 24
N
1.Progresclearing stock top soil & accesMIA-ADR
2.Progresclearing stock top soil HPL & Acces
MHR
OPP
HEAP LEACH
ADR
MAGAZINE
HPHD
Clearing Stock
Top Soil HPL Acces9 Ha
ClearingStockTopSoil MIA,
AccesMIA –ADR 5 Ha
2
1

5
Heap Leach –ProgresClearing W2 August 24
N
1.Progresclearing stock top soil & accesMIA-ADR
2.Progresclearing stock top soil HPL & Acces
3.Continue plan accesand pad miato ADR 12 Ha
4.ContinueplanaccesHPLtoDAM1 10 Ha
ClearingStockTopSoil MIA,
AccesMIA –ADR 5 Ha
1
Clearing Stock
Top Soil HPL Acces9 Ha
2
3
3
4
4
PLANACCES ADR-ILS/PLS PAD
PLAN ACCES HPL to DAM 1

6
2024