General information No Project Description Client Consultant Contrat amount Agreement date Duration (Days) status remark 1 Seven Irrigation (Hida, badule , farangifage,weama,entiaso and dewe bora ) WIEB AFDSWE 156,116,561,59 Apr 20 210 59.6% Initial design problem, payment dalliance, price inflation and Shortage of construction inputs, late approval, junta attach 2 4-irrigation ( Ayrolaf 1 & 2, Gurmudale & Abikala2) MOP AFDSWE 67,739,785.90 Jan 20 360 50% Delay of site handover due to flood. Design problem, stopped by junta & price inflation 3 Belbel WSP WIEB AFDSWE 32,169,631.86 Dec 19 300 72.50% Payment dalliance, co. material shortage & price 4 Farasdage WSP WIEB AFDSWE 42,038,896.30 Apr 19 300 66.30% Borehole failure, payment dalliance, final dalliance of approval of electromechanical 5 Belbel irrigation WIEB AFDSWE 44,918,017.07 Nov 19 380 5% The canal alignment designed as cross cemetery, flood damage and finally junta attach