Basic design of PV system for the pv installation.pptx

furqanasghar7 68 views 70 slides Mar 09, 2025
Slide 1
Slide 1 of 70
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66
Slide 67
67
Slide 68
68
Slide 69
69
Slide 70
70

About This Presentation

pv


Slide Content

Basics of PV System Design your own PV system Dr. Furqan Asghar

How Solar Power System Works ?

Types of PV Systems 3 Grid-tied Standalone Hybrid

Mounting Structure 4

Types of Mounting Systems (According to orientation type) Fixed 5 Tracking Adjustable

Mounting Structure Fixed Roof Mounted Ground Mounted Shade Structure BIPV Car Port Single Axis Tracking & Adjustable Double Axis 6

Roof Mounted 7

Ground Mounted 8

Self- Ballasted Arrays 9

Direct- Mounted Arrays 10

Pole- Mounted Arrays 11

Shade Structure 12

Building Integrated Photovoltaics (BIPV) 13

Car Ports 14

Single Axis Tracking 15

Double Axis Tracking 16

Key factors in Mechanical Design and Module Layout 17

Module physical characteristics 18

Thermal characteristics of modules and effects of mounting system 19

Weather sealing of building penetrations and attachments. 20

Materials and hardware compatibilities with the application environment 21

Materials and hardware compatibilities with the application environment 22

23 Aesthetics and appearance

24 Aesthetics and appearance

Aesthetics and appearance 25

Optimizing Array Performance 26

Optimum Tilt & Azimuth 27

Good Ventilation 28

yellow area: almost no shading blue area: shaded in the mornings (left) or evenings (right) red area: temporary shading

Combiner box (if necessary) 30

31

32

33

Design of On- G rid System 34

Design Steps of On- grid PV System 35 Energy Consumption Site Planning Mounting Structure Components selection Shading Analysis Module Layout Solar panel selection String Configuration Energy Yield BOQ Economical Evaluation

Site Planning 36 Suitable roof for mounting? Solar access for the site? Shading objects (location and dimensions) Orientation and tilt of the roof Suggested location of the inverter Location of AC switchboards Coordinates of the project Pictures for the location Available area Horizon shading Connection voltage CB data Elec. Room pictures

Suitable roof for mounting? 37

Solar access for the site? 38

Orientation and tilt of the roof 39

Location of AC switchboards 40

Coordinates of the project 41

Connection voltage Single Phase or 3-Phase? 42

Mounting Structure Fixed? Tracking? 43 Steel? Aluminum?

Select the manufacturers for: Solar panels Mounting structure DC & AC cables Protection devices 44 Components selection

Shading Analysis h ΞΈ D 45 D = 2h

Shading Analysis D’ = h / tan(Ι‘) 46 D’ = Maximum shadow length h = height of obstruction Ξ± = solar altitude angle

47 Module Layout

String Configuration 48

String Configuration 49

String Configuration 50

Economical Evaluation 51 Simple Payback Period Levelized Cost of Energy (LCOE)

Simple Payback Period Simple Payback Period = CAPEX Yearly Savings 52

CAPEX 53 PV Modules Inverter Mounting Structure DC & AC Cables Installation Permissions

Levelized Cost of Energy (LCOE) LCOE = CAPEX + OPEX Total Energy Yield 54

Design Steps of a Solar PV System for Your Home (Standalone) A solar PV system design can be done in five steps: Step 1: Calculate the energy consumption of appliances Step 2: Calculation of inverter sizing Step 3: Calculation of battery bank Step 4: Calculation of number of PV panels Step 5: Solar charge controller sizing Cost calculation of the solar PV system

Step 1: Calculate energy consumption of appliances We want to know how much electricity is consumed by an appliance in a day? Energy= Power Γ— Duration of use (hours) LED bulb electricity (or energy )consumption per day 10 W Γ— 10 Hr every day= 100 Whr every day LED bulb electricity (or energy )consumption per month 10 W Γ— 10 Hr /day Γ— 30 days=3000 Whr/month Calculate the electricity consumption of all appliances per day and per month?

List of appliances electricity consumption S.No. Name of Appliance Power Rating (W) Per day usage (hr) Per day Electricity used (Whr) Multiply the total appliances watt-hours per day times 1.3 (the energy lost in the system), also known as the fill factor to get the total Watt-hours per day which must be generated by the panel

Step2: Inverter Sizing An inverter is used in the system where AC power output is needed. The input power rating of the inverter should never be lower than the total watt appliances. The inverter size should be 25-30% bigger than the total watts of appliances. For standalone systems, the inverter must be large enough to handle the total amount of watts you will be using at one time. For grid-connected systems , the input rating of the i nverter should be same as PV array rating to allow for safe and efficient operation. The inverter must have the same nominal voltage as your battery.

Step 3: Battery Sizing The battery type recommended for using in solar PV system is deep cycle battery . Deep cycle battery is specifically designed to be discharged to a low energy level and rapid recharged or cycle charged and discharged day after day for years. The battery should be large enough to store sufficient the appliances at night and cloudy days . energy to operate

To find out the size of battery, calculate as follows: Calculate total watt-hours per day used by appliances. Divide the total watt-hours per day used by 0.85 for battery loss (Battery Factor). Divide the answer obtained in step 3.2 by (0.6-0.7) for depth of discharge. Divide the answer obtained in step 3.3 by the nominal battery voltage. Multiply the answer obtained in step 3.4 with days of autonomy to get the required battery sizing. Days of autonomy: the number of days that you need the system to operate when there is no power produced by the panels Step 3: Battery Sizing

π΅π‘Žπ‘‘π‘‘π‘’π‘Ÿπ‘¦ πΆπ‘Žπ‘π‘Žπ‘π‘–π‘‘π‘¦ π΄β„Ž = π‘‡π‘œπ‘‘π‘Žπ‘™ π‘€π‘Žπ‘‘π‘‘ βˆ’ β„Žπ‘œπ‘’π‘Ÿπ‘  π‘π‘’π‘Ÿ π‘‘π‘Žπ‘¦ 𝑒𝑠𝑒𝑑 𝑏𝑦 π‘Žπ‘π‘π‘™π‘–π‘Žπ‘›π‘π‘’π‘  Γ— π·π‘Žπ‘¦π‘  π‘œπ‘“ π΄π‘’π‘‘π‘œπ‘›π‘œπ‘šπ‘¦ 0.85 Γ— 0.6 Γ— π‘›π‘œπ‘šπ‘–π‘›π‘Žπ‘™ π‘π‘Žπ‘‘π‘‘π‘’π‘Ÿπ‘¦ π‘£π‘œπ‘™π‘‘π‘Žπ‘”π‘’ Step 3: Battery Sizing

Example Total appliances use = (18 W Γ— 4 hours)+(60 W Γ— 2 hours)+(75 W Γ— 12 hours) The nominal voltage of the battery = 12 V. Days of Autonomy = 3 Days π΅π‘Žπ‘‘π‘‘π‘’π‘Ÿπ‘¦ πΆπ‘Žπ‘π‘Žπ‘π‘–π‘‘π‘¦ π΄β„Ž = (18 W Γ— 4 hours)+(60 W Γ— 2 hours)+(75 W Γ— 12 hours) 0.85Γ—0.6Γ—12 Γ— 3 Total Ampere-hours required=535.29 Ah T he refore, t h e batter y s h oul d b e rated : 1 2 V , 6 A h for 3 D a y Autonomy Step 3: Battery Sizing

Step 4: Solar PV Sizing = Solar radiation unit=kWh/m 2 /day At given location=5.5 kWh/m 2 /day Divide it by 1000 W/m 2 (under STC) Hours of solar radiation=5.5 hours per day Power of solar panel Total energy by solar panel per day Hours of solar radiation per day

Ste p 5: S ola r C harg e Co n troller Its function is to regulate the voltage and current from the solar arrays to the battery to prevent overcharging and also over-discharging. The solar charge controller is typically rated against Ampere and Voltage capacities. Select the solar charge controller to match the PV array and batteries. Make sure that solar charge controller has enough capacity to handle the current from PV array.

Design Example on off-grid solar PV system sizing

Load Considered for our Example Name of Appliance Number of Appliances Power Rating (W) Per day usage (hr) Per day Electricity used (Whr) Air Conditioner 1 2500 8 20,000 Lamps 5 60 12 3,600 Refrigerator 1 200 24 4,800 TV 1 200 2 400 Total Power 3,200 W Or 3.2 kW Total energy consumed 28,800 Wh Or 28.8 kWh

Inve r ter Sizing Inverter size should be greater by 25 to 30% of load Therefore, minimum inverter sizing= 1.25 Γ— 3.2= 4 kW Considered efficiency  =97% The inverter minimum input=96V As efficiency  = π‘œπ‘’π‘‘π‘π‘’π‘‘ π‘π‘œπ‘€π‘’π‘Ÿ 𝑖𝑛𝑝𝑒𝑑 π‘π‘œπ‘€π‘’π‘Ÿ π‘œπ‘Ÿ π‘œπ‘’π‘‘π‘π‘’π‘‘ π‘’π‘›π‘’π‘Ÿπ‘”π‘¦ 𝑖𝑛𝑝𝑒𝑑 π‘’π‘›π‘’π‘Ÿπ‘”π‘¦  . 97 𝑖𝑛𝑝𝑒𝑑 π‘’π‘›π‘’π‘Ÿπ‘”π‘¦ = π‘œπ‘’π‘‘π‘π‘’π‘‘ π‘’π‘›π‘’π‘Ÿπ‘”π‘¦ = 28.8 = πŸ‘πŸŽ π’Œπ‘Ύπ’‰

Bat t er y Si z ing Consider the efficiency of the battery with charge controller combined= 85% So input energy to charger and battery = 30kWh/0.85 = πŸ‘πŸ“. πŸπŸ— π’Œπ‘Ύπ’‰ We need to consider days of autonomy where sun is not available Assume 1 day of autonomy π΅π‘Žπ‘‘π‘‘π‘’π‘Ÿπ‘¦ πΆπ‘Žπ‘π‘Žπ‘π‘–π‘‘π‘¦ π΄β„Ž = π‘‡π‘œπ‘‘π‘Žπ‘™ π‘€π‘Žπ‘‘π‘‘ β„Žπ‘œπ‘’π‘Ÿπ‘  π‘π‘’π‘Ÿ π‘‘π‘Žπ‘¦ 𝑒𝑠𝑒𝑑 𝑏𝑦 π‘Žπ‘π‘π‘™π‘–π‘Žπ‘›π‘π‘’π‘ Γ—π·π‘Žπ‘¦π‘  π‘œπ‘“ π΄π‘’π‘‘π‘œπ‘›π‘œπ‘šπ‘¦ 0.85Γ—0.6Γ—π‘›π‘œπ‘šπ‘–π‘›π‘Žπ‘™ π‘π‘Žπ‘‘π‘‘π‘’π‘Ÿπ‘¦ π‘£π‘œπ‘™π‘‘π‘Žπ‘”π‘’ DoD of battery=60%, each battery 200 Ah So Ah required= 3.67 kAh 12 Number of series batteries= 96 = πŸ– 8Γ—200 Number of parallel strings= 3670 = 2.29 = 𝟐

P V Modu l e Sizing At given location=5 kWh/m 2 /day Divide it by 1000 W/m 2 (under STC) Hours of solar radiation=5 hours per day Power of solar panel= Total energy by solar panel per day Hours of solar radiation per day =35.29kWh/5=7kW PV panel available in the market: P m =580 W, V oc =45V, I sc = 13 A 580 Therefore number of PV panels = πŸ•πŸŽπŸŽπŸŽ = 12 panels

Solar C h arg e Controller Si z ing Total Solar Power = 12* 580W = 6.96kW With specifications of 96 V and 40 A First group: 2 series and 6 parallel which gives 12 panels Total current=6 Γ— 8.3=78 A Total voltage=2 Γ— 45=90 V Keeping in view the system current, we need two charge controllers to handle the system properly.
Tags