Review of Ongoing Projects under Execution under Bridge Programme PW(R&B) Department South Kashmir
Abstract of Bridges under Various Sectors S.NO Sector No of Bridges No of Bridges Completed 1 Bridge Sector 11 3 2 CRIF 2 2 NABARD 4 2 3 JTFRP 3 1 Total 20 5
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 Bridge Sector
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 S.NO Name of the Bridge R&B Division Sector Whether Transfered from JKPCC Whether Transfered from Languishing Programme Date of Start Estt. Cost AA Cost Allotted Cost Cum. Expdt. upto 03/2023 Cumm. Expdtt. ending 03/2024 Balance Cost as on 01.04.2024 Funds Recieved 2024-25 (if any) Expenditure 2024-25 (as on 17.05.2024) Additional Funds Required 2024-25 (Above approved Allocation) Total Work Done (WD) value as on date Percentage of Completion as on 17.05.2024 Likely date of completion Detailed Physical Progress 1 2 3 4 5 6 7 8 9 10 11 15 16 18 19 20 21 22 23 25 1 Suspension Foot bridge over River Jehlum at Padshahi Bagh Bijbehara Padshahi Bagh Bijbehara , Anantnag (2x14 + 1x105) =133 Mtr Anantnag Bridge NO Yes NA 318.00 318.00 318.00 84.00 84.00 234.00 172.00 145.00 34.00 318.00 100% Completed 2 Construction of overhead Foot bridge at Harnag Anantnag (1x42 Mtr) Anantnag Bridge No No 2022-23 297.84 297.84 185.50 86.54 111.54 73.96 0.00 0.00 25.00 140.00 75% Aug- 2024 Super Structure Launched, stiar work in progress 3 Balance work of 4x30 mtr span steel girder Bridge at Kandiwara on Khalhar to Kandiwara road Vailoo Bridge No No 2023-24 0.00 390.59 390.59 0.00 0.00 390.59 116.69 71.10 208.00 370.00 95% 06-2024 95% COMPLETED 4 Construction of Seer Numbal Bridge including approaches on either side (2 25 +1x 30+2x20) =120 Mtr Pahalgam Bridge No Yes 2010-11 950.05 950.05 808.23 380.97 499.76 308.47 20.00 0.00 100.00 500.00 55% 12-2024 55% 5 Construction of 1x10 Mtr span bridge on Nillow Awhatoo Road. Kulgam Bridge No No 2017-18 77.50 77.50 73.89 65.61 69.67 4.22 2.25 0.00 0.00 73.66 100% Bridge completed Bridge completed 6 Construction of 1x30 Mtr span intermediate lane compositebridge on Udipora Mishpora Road (2nd bridge) Kulgam Bridge No No 2022-23 276.13 276.13 231.93 2.02 2.02 229.91 24.20 23.00 98.00 25.00 15% 03-2025 Work is in progress (15% )
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 S.NO Name of the Bridge R&B Division Sector Whether Transfered from JKPCC Whether Transfered from Languishing Programme Date of Start Estt . Cost AA Cost Allotted Cost Cum. Expdt . upto 03/2023 Cumm . Expdtt . ending 03/2024 Balance Cost as on 01.04.2024 Funds Recieved 2024-25 (if any) Expenditure 2024-25 (as on 17.05.2024) Additional Funds Required 2024-25 (Above approved Allocation) Total Work Done (WD) value as on date Percentage of Completion as on 17.05.2024 Likely date of completion Detailed Physical Progress 1 2 3 4 5 6 7 8 9 10 11 15 16 18 19 20 21 22 23 25 7 Construction of 3x30 mtr span plate Girder Bridge Over Nallah Bushi Dragdan Dudkuchan Sanyardi Road at Dudkuchan DH Pora D.H Pora Bridge Sector No NO 05-09-2023 872.30 872.30 627.93 3.10 3.10 624.83 139.42 98.84 488.51 160.00 27% 2026-27 Rafts of both abuts and both piers completed. 03 lifts of A1 & A2, &05 Lifts of P1 & 04 lifts of P2 completed. work in progress. 8 Construction of 1x30 mtr span RCC Slab at Adijan on Pambay Adijan Damhal road. (Balance work). D.H Pora Bridge Sector NO NO 12-02-2024 200.00 200.00 143.59 0.00 0.00 143.59 34.17 34.17 109.42 47.00 31% FY 2024-25 one truss girder launched .Fabrication of another girder in progress and will be launched within 10 days. Crate work completed. Development of one-sided approach road also in progress 9 Construction of Sub- Structutre of 4x25 Mtr + 1x30 Mtr bridge including deck slab at Shankerpora . Qazigund Bridge Sector No No 2017-18 693.00 693.00 693.00 643.46 687.64 5.36 0.00 0.00 0.00 693.00 100% Bridge Completed and opened for traffic. Bridge completed and opened for traffic. 10 Construction of 129 Mtr span double lane trussed girder bridge over River Jehlum at Dogripora. Awantipora Bridge Sector Yes Yes 2007-2008 1384.69 1384.69 1204.72 805.87 885.46 319.26 0.00 0.00 500.00 885.46 60% 2024-25 60% 11 Construction of 109 Mtr span double lane plate girder bridge over River Jehlum at Reshipora Awantipora Bridge Sector Yes Yes 2008-2009 893.56 893.56 447.89 447.89 447.89 0.00 0.60 0.60 200.00 448.49 40% 2025-26 40% Total Bridge Sector 5963.07 6353.66 5125.27 2519.46 2791.08 2334.19 509.33 372.71 1762.93 3660.61 6.98
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 CRIF Bridges
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 S.NO Name of the Bridge R&B Division Sector Whether Transfered from JKPCC Whether Transfered from Languishing Programme Date of Start Estt . Cost AA Cost Allotted Cost Cum. Expdt . upto 03/2023 Cumm . Expdtt . ending 03/2024 Balance Cost as on 01.04.2024 Funds Recieved 2024-25 (if any) Expenditure 2024-25 (as on 17.05.2024) Additional Funds Required 2024-25 (Above approved Allocation) Total Work Done (WD) value as on date Percentage of Completion as on 17.05.2024 Likely date of completion Detailed Physical Progress 1 2 3 4 5 6 7 8 9 10 11 15 16 18 19 20 21 22 23 25 1 Constrtion of bridge at river Jehlum at Gadhanjipora , Bijbehara (2 x 20+1 x 60) =100 Mtr Anantnag CRIF Yes NO 2023-24 889.07 889.07 707.84 0.00 0.00 707.84 40.00 40.00 0.00 80.00 35% 2025-26 Two pile caps laid out of three pile caps 2 Additional 30 m span RCC bridge over river Jehlum at Khanabal Anantnag CRIF NO NO 2018-19 1746.00 1746.00 1053.88 104.70 104.70 949.18 0.00 0.00 0.00 104.70 16% .... .... Total CRIF 2635.07 2635.07 1761.72 104.70 104.70 1657.02 40.00 40.00 0.00 184.70 0.51
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 NABARD Bridges
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 S.NO Name of the Bridge R&B Division Sector Whether Transfered from JKPCC Whether Transfered from Languishing Programme Date of Start Estt . Cost AA Cost Allotted Cost Cum. Expdt . upto 03/2023 Cumm. Expdtt. ending 03/2024 Balance Cost as on 01.04.2024 Funds Recieved 2024-25 (if any) Expenditure 2024-25 (as on 17.05.2024) Additional Funds Required 2024-25 (Above approved Allocation) Total Work Done (WD) value as on date Percentage of Completion as on 17.05.2024 Likely date of completion Detailed Physical Progress 1 2 3 4 5 6 7 8 9 10 11 15 16 18 19 20 21 22 23 25 1 Construction of 2x40 mtr Span Steel Girder Bridge on Bundzoo Chatripora road Pulwama NABARD RIDF XXVII NO NO Feb-2022 901.97 901.97 715.42 1.00 180.11 535.31 13.64 13.64 349.36 193.75 25% 2024-25 shaft completed for two abutments and one pier. One side approach 75% complete. Pedestal and cap to be laid 2 Construction of 1x40 mtr span Steel Girder Bridge Between Mir Bagh and Dogam Pulwama NABARD RIDF XXV NO NO Jan-2021 386.56 386.56 368.00 332.86 343.42 24.58 1.70 1.70 10.00 345.12 99% 2024-25 bridge completed and opened for traffice, however river training works pending 3 Construction of 1x40 Mtrs Span Steel Girder Bridge on Kakapora Padgampora Road over Romshi Nallah at Lelhar Under NABARD Pulwama NABARD RIDF XXIX NO NO 2023-24 499.63 499.63 395.36 0.00 0.00 395.36 0.00 0.00 150.00 2.00 2% 2025-26 site clearance in progress by way of disambling of old damaged plate girder bridge and DPR/ design for the new bridge under Third party vetting 4 Construction of 1x30 Mtr addational span steel girder bridge in Km 2nd of Nowbugh Urill Thatoo road at Kraloo Kulgam Nabard No No 2020-21 416.32 416.32 300.00 208.83 263.27 36.73 4.94 4.94 10.00 268.21 98% Main Bridge completed Appraoched to be macadamized Bridge completed Total NABARD 2204.48 2204.48 1778.78 542.69 786.80 991.98 20.28 20.28 519.36 809.08
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 JTFRP Bridges
Detailed Physical/Financial Status of of Major Bridges as on 18.05.2024 S.NO Name of the Bridge R&B Division Sector Whether Transfered from JKPCC Whether Transfered from Languishing Programme Date of Start Estt . Cost AA Cost Allotted Cost Cum. Expdt . upto 03/2023 Cumm . Expdtt . ending 03/2024 Balance Cost as on 01.04.2024 Funds Recieved 2024-25 (if any) Expenditure 2024-25 (as on 17.05.2024) Additional Funds Required 2024-25 (Above approved Allocation) Total Work Done (WD) value as on date Percentage of Completion as on 17.05.2024 Likely date of completion Detailed Physical Progress 1 2 3 4 5 6 7 8 9 10 11 15 16 18 19 20 21 22 23 25 1 Construction of 6x50 Mtr span Double Lane Trussed Trenz Sheikhpora Bridge under JPFTRP Zainapora JTFRP YES NO Nov-2017 3941.21 3941.21 3603.85 1119.48 1119.48 2484.37 0.00 0.00 755.00 1874.48 60% 12-2024 60% completed. Fabrication of structural steel and approaches are under progress. Also erection of structural steel has been started. 2 Construction of 1X45 Mtr span trussed bridge over nallah Rambiara at Watchi (Kumar Mohalla) including construction of approach road and nallah training works (EPC Mode) Under JPFTRP Zainapora JTFRP No No Dec-2019 311.00 311.00 311.00 199.10 301.10 9.90 9.90 0.00 0.00 311.00 100% 3-2024 100% Compled 3 Construction of 150 Mtrs Long Rohmu Bridge Pulwama JTFRP YES No Nov-2017 2597.88 2597.88 2335.94 939.3 (includes Corporation overhead deduction = 180.77) 939.30 1396.64 271.00 271.00 1387.58 2130.30 85% 2024-25 01 - Slab laid on two No. spans. 02 - Third span girder also launched, cross girders are in progress. 03- Approach walls completed 04- Crate protection work upstream and downstream in progress Total (JTFRP) 6850.09 6850.09 6250.79 2257.88 2359.88 3890.91 280.90 271.00 2142.58 4315.78