Objective of the Presentation
Current Industry Scenario
Present “ What is meant by Design Coordination”
along with the dependent issues and proposed
action plan
Current Status
Immediate Action Plan
3
Current Industry Scenario
Turnkey Projects
Complex
Multi Disciplinary
Tenders based on EPC / PPP mode – Lump Sum
Price
Lowest Bidder
There is scarcity of resources
Skill Set Required
Multi Disciplinary Skills –
Thorough understanding of the functions of all the components of the
project.
Close coordination among the various systems / stakeholders
Benchmarking
Value Engineering
Specialist Domain Knowledge
Contract Management including planning and monitoring the
deliverables
With Client
With Consultants
Interpersonal Skills and Communication Skills
4
Design Coordination
5
Design of Enabling
Works
Design of Permanent
Structures
Contractual
Requirements
Construction
Methodology
Design
Coordination
Design Coordinator has to have an eye
on economy and ease of construction
Design Coordination – Stake Holders
6
Client
Design
Consultant
Project Team
at Site
Proof
Consultant
Supplier
CPMG
Other
Consultants
GFC
Drawings
Designer for
Enabling works
Functionalities with Different Stake Holders
Project Team at Site
Providing GFC Drawings in time
Agree for timelines based on the construction program
(Action Item A)
Providing Clarifications
7
Functionalities with Different Stake Holders
Design Consultant
Providing Inputs
GAD
Design Basis Note
Construction Methodology
Receipt of the Designs
Agree for timelines keeping in view the Action Item 1.
(Action Item 2)
Review of the Design
For completeness – Agreed Checklist
(Action Item 3)
For Compliance – Agreed Checklist
(Action Item 3)
For contractual requirements like BOQ
Seeking Clarifications
8
Functionalities with Different Stake Holders
Design Consultant
Obtaining the Clarifications sought by the Client and
Project Team at Site
Obtaining Parameters for monitoring during execution
Erection Manual (Action Item 4)
Obtaining Parameters for Suppliers of Bearings and
Expansion Joints
Interaction during execution
Submission of As Built Drawings
Project Completion Report – Designs Chapter
9
Functionalities with Different Stake Holders
Client
Submission of Designs and Drawings
Advise the design submission program
(Action Item 5)
Approvals for designs and drawings
Agree for timelines for approvals (Action Item 6)
Clarifications while getting approvals
10
Functionalities with Different Stake Holders
CPMG
Agree for the methodology of construction.
Provide Inputs from Design Consultant for construction
monitoring
Providing necessary clarifications
Proof Consultant
Normally there is no interaction.
Keep a watch on the correspondence between the Design
Consultant and Proof Consultant
11
Functionalities with Different Stake Holders
Designer for Enabling Works
Providing the methodology of construction.
Providing necessary clarifications.
Suppliers
Providing the technical specifications.
Providing necessary clarifications.
Other Consultants
Providing necessary inputs.
Providing necessary clarifications.
Review and Monitoring the deliverables
12
General Arrangement Drawing
1313
Arch Portion 785m Viaduct Portion 530m
14
Breakup of Work for Monitoring
Permanent Work
Arch Portion – S10 to S70
Viaduct Portion – S70 to S180
Ancillary Works
Temporary Works
Arch Portion – S10 to S70
Viaduct Portion – S70 to S180
15
Breakup of Work – Permanent - Arch Portion
Arch Portion – S10 to S70
Foundations – S10 to S70
Abutment – S10
Piers – S20, S30, S40, S40A, Spandrel Columns S41 to
S49, S50, S50A, S60, S70
Arch
Bearings and Expansion Joints
Deck Structure
16
Breakup of Work – Permanent - Viaduct
Viaduct Portion – S70 to S180
Foundations – S70 to S180
Abutment – S180
Piers – S70 to S170
Bearings and Expansion Joints
Deck Structure
17
Breakup of Work – Permanent - Ancillary
Slope Stability for S10-S40
Slope Stability for S50-S70
Slope Stability for S120 – S130
Slope Stability for S170 – S180
Cable Crane
Mechanically operating cages for steel piers
18
Breakup of Work – Temporary - Arch Portion
Arch Portion – S10 to S70
Will be decided after finalizing the methodology of
erection of Arch.
Basic Components
Stays
Foundations for Stays
Anchorages
Launching Arrangements at S10
Launching Arrangements between S70 and S90
Derrick
19
Breakup of Work – Temporary - Viaduct
Viaduct Portion S70 to S180
Launching Arrangements at S180
Launching Arrangements between S80 and S90
Temporary Pier between S170 and S180
Temporary Pier between S120 and S130 (To be decided)
Launching Nose
Side Guidance Arrangements
20
Status
All the designs of the permanent Structures were
submitted once.
Based on the earlier designs, the foundations and piers
from S90 to S180 have been constructed.
The Design Basis Note for viaduct portion has been
revised.
The Design Basis Note for arch portion is under revision.
The arch span was revised from 460m to 467m. Founding
levels of arch and piers at S20, S30, S60 are under review.
Methodology of erection of deck in viaduct portion and
arch portion is under review.
21
Broad Scope of Work
Viaduct Portion
Firm up methodology of launching.
Check of the design of deck and pier and foundations at
S80 and S70 in terms of final DBN.
Recheck of the design of already constructed
components and assess the extent of overstress.
Arch Portion
Firm up methodology of erection of arch.
Take up fresh designs.
22
Immediate Action Items
Firm up commercial offer for design checks of viaduct.
Agree with the Project Team for timelines based on the
construction program for issuing GFC Drawings.
Firm up methodology of launching of the deck
Agree with the Design Consultant for the dates for design
submissions.
Agree for timelines for approval with the client.
Firm up founding levels for foundations from S10 to S80
Follow up with the Client for finalizing the DBN for Arch
Portion