Chenab PPT-Design Coordination-Srinivas.ppt

SaritaJoshi5 13 views 24 slides Aug 09, 2024
Slide 1
Slide 1 of 24
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24

About This Presentation

Chenab bridge construction coordination


Slide Content

2 0 0 7
2 0 0 7
Chenab Bridge – Design
Coordination
Presentation
By
Srinivas Mantrala

2
Objective of the Presentation
Current Industry Scenario
Present “ What is meant by Design Coordination”
along with the dependent issues and proposed
action plan
Current Status
Immediate Action Plan

3
Current Industry Scenario
Turnkey Projects
Complex
Multi Disciplinary
Tenders based on EPC / PPP mode – Lump Sum
Price
Lowest Bidder
There is scarcity of resources

Skill Set Required
Multi Disciplinary Skills –
Thorough understanding of the functions of all the components of the
project.
Close coordination among the various systems / stakeholders
Benchmarking
Value Engineering
Specialist Domain Knowledge
Contract Management including planning and monitoring the
deliverables
With Client
With Consultants
Interpersonal Skills and Communication Skills
4

Design Coordination
5
Design of Enabling
Works
Design of Permanent
Structures
Contractual
Requirements
Construction
Methodology
Design
Coordination
Design Coordinator has to have an eye
on economy and ease of construction

Design Coordination – Stake Holders
6
Client
Design
Consultant
Project Team
at Site
Proof
Consultant
Supplier
CPMG
Other
Consultants
GFC
Drawings
Designer for
Enabling works

Functionalities with Different Stake Holders
Project Team at Site
Providing GFC Drawings in time
Agree for timelines based on the construction program
(Action Item A)
Providing Clarifications
7

Functionalities with Different Stake Holders
Design Consultant
Providing Inputs
GAD

Design Basis Note

Construction Methodology
Receipt of the Designs
Agree for timelines keeping in view the Action Item 1.
(Action Item 2)
Review of the Design
For completeness – Agreed Checklist
(Action Item 3)
For Compliance – Agreed Checklist
(Action Item 3)
For contractual requirements like BOQ
Seeking Clarifications
8

Functionalities with Different Stake Holders
Design Consultant
Obtaining the Clarifications sought by the Client and
Project Team at Site
Obtaining Parameters for monitoring during execution
Erection Manual (Action Item 4)
Obtaining Parameters for Suppliers of Bearings and
Expansion Joints
Interaction during execution
Submission of As Built Drawings
Project Completion Report – Designs Chapter
9

Functionalities with Different Stake Holders
Client
Submission of Designs and Drawings
Advise the design submission program
(Action Item 5)
Approvals for designs and drawings
Agree for timelines for approvals (Action Item 6)
Clarifications while getting approvals
10

Functionalities with Different Stake Holders
CPMG
Agree for the methodology of construction.
Provide Inputs from Design Consultant for construction
monitoring
Providing necessary clarifications
Proof Consultant
Normally there is no interaction.
Keep a watch on the correspondence between the Design
Consultant and Proof Consultant
11

Functionalities with Different Stake Holders
Designer for Enabling Works
Providing the methodology of construction.
Providing necessary clarifications.
Suppliers
Providing the technical specifications.
Providing necessary clarifications.
Other Consultants
Providing necessary inputs.
Providing necessary clarifications.
Review and Monitoring the deliverables
12

General Arrangement Drawing
1313
Arch Portion 785m Viaduct Portion 530m

14
Breakup of Work for Monitoring
Permanent Work
Arch Portion – S10 to S70
Viaduct Portion – S70 to S180
Ancillary Works
Temporary Works
Arch Portion – S10 to S70
Viaduct Portion – S70 to S180

15
Breakup of Work – Permanent - Arch Portion
Arch Portion – S10 to S70
Foundations – S10 to S70
Abutment – S10
Piers – S20, S30, S40, S40A, Spandrel Columns S41 to
S49, S50, S50A, S60, S70
Arch
Bearings and Expansion Joints
Deck Structure

16
Breakup of Work – Permanent - Viaduct
Viaduct Portion – S70 to S180
Foundations – S70 to S180
Abutment – S180
Piers – S70 to S170
Bearings and Expansion Joints
Deck Structure

17
Breakup of Work – Permanent - Ancillary
Slope Stability for S10-S40
Slope Stability for S50-S70
Slope Stability for S120 – S130
Slope Stability for S170 – S180
Cable Crane
Mechanically operating cages for steel piers

18
Breakup of Work – Temporary - Arch Portion
Arch Portion – S10 to S70
Will be decided after finalizing the methodology of
erection of Arch.
Basic Components
Stays
Foundations for Stays
Anchorages
Launching Arrangements at S10
Launching Arrangements between S70 and S90
Derrick

19
Breakup of Work – Temporary - Viaduct
Viaduct Portion S70 to S180
Launching Arrangements at S180
Launching Arrangements between S80 and S90
Temporary Pier between S170 and S180
Temporary Pier between S120 and S130 (To be decided)
Launching Nose
Side Guidance Arrangements

20
Status
All the designs of the permanent Structures were
submitted once.
Based on the earlier designs, the foundations and piers
from S90 to S180 have been constructed.
The Design Basis Note for viaduct portion has been
revised.
The Design Basis Note for arch portion is under revision.
The arch span was revised from 460m to 467m. Founding
levels of arch and piers at S20, S30, S60 are under review.
Methodology of erection of deck in viaduct portion and
arch portion is under review.

21
Broad Scope of Work
 Viaduct Portion
Firm up methodology of launching.
Check of the design of deck and pier and foundations at
S80 and S70 in terms of final DBN.
Recheck of the design of already constructed
components and assess the extent of overstress.
Arch Portion
Firm up methodology of erection of arch.
Take up fresh designs.

22
Immediate Action Items
Firm up commercial offer for design checks of viaduct.
Agree with the Project Team for timelines based on the
construction program for issuing GFC Drawings.
Firm up methodology of launching of the deck
Agree with the Design Consultant for the dates for design
submissions.
Agree for timelines for approval with the client.
Firm up founding levels for foundations from S10 to S80
Follow up with the Client for finalizing the DBN for Arch
Portion

23
Thanks

Middle Third Rule
24
e
x < L/6
e
y
< B/6