7/8
The template contains the dashboard. The dashboard updates itself when the actual dates
and earned costs are entered for the activity. The dashboard contains a graph for planned
vs actual for the complete project. Another graph is the plan till status date vs the actual
till date for structural works and finishing works.
A doughnut chart shows the schedule performance index. A line chart shows the
cumulative total delay of the project.
Worksheet 6: Dashboard
Note- If the dashboard doesn’t update on putting actual values, go to the “Dashboard
Backup” worksheet, click on the pivot table, select the ‘Analyse’ tab and click ‘Refresh All’.
Final Words for Construction Project Schedule Template
The excel construction project schedule template works on the basics of scheduling. The
activities name, duration, relationships and lead/lag can be modified as per the
requirements of the site. Other than scheduling, the purpose of the template is to make
people more curious about the schedules and their effectiveness.
Further, you can also get a customised excel template, dashboards, tracking sheets for
your project at a nominal charge. You can contact me via mail at
[email protected] or my LinkedIn profile (link available on the Contact Us
page).