Reducing the Time of a Project
(crashing)
Activit
y
Normal
Time (wk)
Normal
Cost ($)
Crash
Time
Crash
Cost ($)
Max. weeks
of
reduction
Reduce
cost per
week
A 4 8,000 3 11,000 1 3,000
B 6 30,000 5 35,000 1 5,000
C 3 6,000 3 6,000 0 0
D 6 24,000 4 28,000 2 2,000
E 14 60,000 12 72,000 2 6,000
F 5 5,000 4 6,500 1 1500
G 2 6,000 2 6,000 0 0
H 2 4,000 2 4,000 0 0
I 3 4,000 2 5,000 1 1,000
J 4 4,000 2 6,400 2 1,200
K 2 5,000 2 5,000 0 0