classes P2- Class VII (Q-value 0.0031, RMR 16)
Geological condition
(photos in Annex. I)
P1: Dominantly laminated shale with subordinate thin beds of
sandstone. Three prominent joint sets (38/098, 65/152, 73/305).
Slightly damp ground.
P2: Thinly laminated shale, highly weathered. Three prominent joint
sets (43/050, 65/205, 72/103). Damp ground.
Primary support in following sequence
Forepoling 32 mm/4 m/200 mm c/c spacing/SN
Excavation method Mechanical breaking (Heading-Benching-Invert)/Drilling blasting
Excavated area 69.64 sq. mt.
Pull length P1: 2.25-3 m
P2: 1 m
Rockbolt NA
Ribs ISMB 250X125 @ 0.75 m spacing, 3 set in one pull
Lagging MS plate 6 mm (or slabs 730X200X50
Backfilling M20
Primary lining
thickness
450 mm
Remarks 1. Support is Rigid and Conventional
2. Cycle time 20-22 hrs avg.
3. Lesser activities in each cycle:
(a) Face excavation for heading,(With Blasting operation)
(b) Scaling and mucking,
(c) Face sealing,
(d) Surveying and placement of steel support,
(e) Erection of ISMB, (f) Backfilling,
(g) Anchor drilling and fixing with SN type, no SDA rockbolt, hence,
time savings for grouting and torqueing etc, however, for such worst
rock class, where, hole collapse situation, design permitted for SN
Rock Bolt anchoring of RIB with Plate.
(f) Out of alternate 3 RIB spacing @0.75 mtr for one RIB spacing
3.14mm MS plate is at Tunnel Side of RIB (Inner) and for 3 RIB space
plates are welded with RIB outer side, thus less concrete back filling,
Remaining 3 round space backfilling will be done along with final
lining, thus less time for round length.
Tunnel T4P1, 1168m long. Method of Tunnelling is conventional. Support class VII is applied.
Side slope in front of portal are damaged. During site visit backfilling concrete for benching was
in progress. Tunnel face in dry condition hence no water seepage observed in executed tunnel,
no drainage holes was drilled. Tunnel excavation carried out by mechanical/Drill and blast
method in Heading/Benching and Invert. Excavated benching face, some blasting drilled holes
sockets observed. Tunnel face muck is being used for maintenance of tunnel road. SN type
forepolling is in use. Heading pull length is fixed for 2.25m. Three set of Ribs 150 X 250mm
ISMB were installed in one pull at spacing of 0.75m. Maximum achieved monthly progress 40m.
Ribs spacing can be increased 1m to 1.25m. Out of alternate 3 RIB spacing @0.75 m for one
RIB spacing 3.14mm MS plate shuttering is at Tunnel Side of RIB Inner flange and for 3 RIB
space plates are welded with RIB outer flange, thus less concrete back filling, Remaining 3
round space backfilling will be done along with final lining, thus less time for round length.
Ventilation and housekeeping is ok. Tunnel road is well maintained. Main tunnel execution
completed without TRNs. TRNs still pending in executed 679m length. Methane gas is
encountered in tunnel; additional ventilation fan is located inside tunnel to dilute encountered