Diversion headworks

327 views 40 slides Sep 15, 2020
Slide 1
Slide 1 of 40
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40

About This Presentation

the material of this PPt according to the RTU syllabus


Slide Content

Assi Prof . Brijlata sharma JECRC, Jaipur

DIVERSION HEAD WORKS The works which are constructed at the head of the canal , in order to divert the river water towards the canal , so as to ensure regulated continuous supply of silt free water with certain minimum head into that canal is called as diversion head works. These are constructed on a river where adequate flow of river water is available throughout the year. If the storage on upstream of diversion head works is significant, it is called storage weir If it is constructed on downstream of dam for purpose of diverting water from upstream side of dam into canal, it is called pick up weir.

. LOCATION OF DIVERSION HEAD WORK:- It should be near the command area. The site which gives economical arrangement is usually selected. SITE SELECTION :- Good foundation should be available. The site should be such that weir can be aligned at right angle to the diversion of water in the river. The site should be such that there should be sufficient space for location of head regulator and other component of the diversion headwork. The overall cost should be less. Proper approach way should be nearby site. On the upstream side where water is retained, should not include costly land. While construction of weir or barrages river should be available near the site. The material and labours should be available nearby site. The river should be perennial. The river should have non erodible as well as non submersible banks. 11)The site should be narrow and well defined.

COMPONENT PARTS OF A DIVERRSION HEADWORK 1. Weir or barrage 2. Undersluices 3. Divide wall 4. Fish ladder 5. Canal head regulator 6. pocket or approach channel 7. Silt excluders/ Silt prevention devices 8. River training works (Marginal bunds and guide banks)

Weir & Barrage :- Weir: It is an impervious . barrier constructed across a river to raise its water level on its upstream side and divert the water into the canal taking off from its upstream side . Weir afflux chances are more in floods. Barrage: If storage of water is done by gates and very small portion or nil portion of water is stored by raised crest then the barrier is called as barrage. Barrage is a gate controlled weir. The heading up of water is effected by the gates alone. Barrage afflux chances are reduced by gates.

. T Y PES OF WEIR:- 1) gravity weir 2) non gravity weir 1) gravity weir Depending on material and design features, gravity weirs are subdivided into following types- (i)Vertical drop weir. (ii) Sloping weir a. Rock fill weirs. b. Concrete weirs Weirs are also classified as follows : (1) According to use and function. (a) Storage weir. (b) Pick up weir. (c) Diversion weir. (d)Waste weir. (2) According to control of surface flow. (3) According to the design of floors. (4) According to constructional material a) Masonry weir b) Rockfill weir c) Concrete weir

Gravity weir:- when the weight of weir balances uplift pressure caused by the head of water seep . ing below weir it is called as gravity weir. Non gravity weir:- in non gravity weir the uplift pressure is largely resisted by weight of concrete slab with the weight of divide piers. i ) Vertical Drop Weir:

This type of weir consists of horizontal floor and masonry crest with vertical or nearby vertical downstream face and the shutters are provided at the crest. Most of the . storage is done by raised crest and some storage by shutters provided over the crest . ii ) Rock Fill Weir It is also called as dry stone slope weir. It is suitable for fine sandy foundation. stone are mainly used for construction of such type of weir and hence requires large quantities of stone

iii ) Concrete Weir : These are suitable for permeable . foundations. In such weirs sheet piles are provided on both upstream and downstream floors in order to destroy the energy of water

. According to use and function a ) Storage Weir : It is high weir constructed for storing water. It is also called as diversion weir. In such weirs shutters may or may not be provided. b ) Pick Up Weir : These are constructed when command area is far away from reservoir either due to rolling topography or because the land is not cultivable and if there is broken or rolling topography on one or both banks of parent river in which construction of canal may be costly.

A solid weir usually with crest gates constructed in concrete or stone masonry located at some distance downstream of dam forming a large reservoir to raise the water . level up to FSL of canal is known as pickup weir . Situations : It is proposed in the following situations- i) In case of broken or rolling topography on one or both banks of the parent river where canal construction is costly. ii)In case of command area is too far away from the reservoir may be due to rolling topography. iii) In case of land nearby the reservoir is not cultivable. iv) The command area not near the reservoir. v) Canal has to run idle. Vi) Geographically difficult terrain so that the canal alignment is very costly or impossible.

c ) Diversion Weir: A weir which is constructed for di . verting the river water into the canal is called as diversion weir. Generally it is constructed at 900 to the flow of river. D) Waste weir:- it is constructed in continuation of dam . It is also known as escape channel or a spillway. It allows flood water to escape and thus ensure safety of the dam.

UNDER SLUICE Under sluice are opening provid ed in the body of weir at low level. These are located at same side from which canal is taking off. The crest of under sluice is kept lower than crest of weir due to which water is attracted towards it and thus ensure easy diversion into canal.

FUNCTIONS OF UNDERSLUICE:- 1) it control entry of silt i . nto canal. 2) it lowers the HFL. 3) it helps in passing low river flood without lifting shutters. 4) it helps to pass silt on downstream side of weir. whenever silt is remover the gates of head regulator are closed and of sluice are opened through these sluice the silt which is deposited is removed and it goes on downstream side when all silt is removed silt gates are closed and regulator gates are opened.

DIVIDE WALL:- is wall constructed bet . ween under sluices and the weir at right angle to the axis of the weir to divide the river channel. Function of divide wall:- 1) it separates the under sluices from weir. 2) it also helps in reducing velocity of flow near the head regulator due to which silt is deposited and clear water passes in to canal. 3) it prevents vortices means flow in circular motion.

FISH LADDER It is passage provided adjacent to divide wall for the movement of fish from upstream to downstream and vice versa. It allows free access to fish so that they can travel from colder water to hot water It has been observed that fish moves from old water to warm water and in monsoon they again move towards upstream or downstream of the work. These are provided with various fashion like sluice type in which the baffle wall is in zig zag way over flow type in which V notches are provided in staggered arrangement etc.

Silt excluder :- The device which are constructed at the head of main canal which prevents entry of silt particles into canal are called as silt exclusion devices. Silt ejectors:- The structure which is constructed across the canal to eject silt accumulated in canal section is called silt ejector. Silt ejector consist of tunnel which is connected parallel to the flow of the canal and then turns 90 degree to eject silt. The length of tunnel provided may be different. These are provided with sufficient slope. So that silt should not be deposited in its bed.

GUIDE BANK:- Guide banks are provided on either side of diversion head work. In alluvial soil to prevent river from out flankin . g the work. The main object of guide banks are:- 1) it prevent oblique approach to the head regulator . 2) it protect regulator from river attack. 3) it increases maximum discharge at all point. 4) it prevent out flanking of structure. 5) it create reasonable water way for a weir. 6) To separate flow from the scouring weir which is at lower level than proper weir. 7) To separate the silting packet from scouring sluices 8) To prevent formation of cross currents to avoid domain effects 9) To cut off the main portion of the river and provide a comparatively quite packet in front of the canal head regulator resulting in deposition of silt in the pocket and enter clear water in canal

Marginal embankment:- Marginal embankment are provided on either bank of river upstream of diversion head work to protect the land and property which is likely to be submerged during flood. It helps in :- 1) reduce the intensity of flood. 2) it prevents bed level of the river by silting. 3) it protect land and property which is likely to be submerged. SCOURING SLUICE:- It helps in scour out the deposited bed silt.

HEAD REGULATOR:- 1) It regulates the supply . of water entering in canal. 2) It controls the entry of silt into canal 3) It prevents the river flood entering the canal Stilling Pond: In still can be taken outing pond water made stil where deposition of silt takes place due to sedimentation and from which silt can be taken out. 1) To reduce velocity of water. 2) To settle down the silt and allow clear water to the canal.
Tags