Elemental Cost Analysis

26,318 views 125 slides Nov 13, 2016
Slide 1
Slide 1 of 125
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66
Slide 67
67
Slide 68
68
Slide 69
69
Slide 70
70
Slide 71
71
Slide 72
72
Slide 73
73
Slide 74
74
Slide 75
75
Slide 76
76
Slide 77
77
Slide 78
78
Slide 79
79
Slide 80
80
Slide 81
81
Slide 82
82
Slide 83
83
Slide 84
84
Slide 85
85
Slide 86
86
Slide 87
87
Slide 88
88
Slide 89
89
Slide 90
90
Slide 91
91
Slide 92
92
Slide 93
93
Slide 94
94
Slide 95
95
Slide 96
96
Slide 97
97
Slide 98
98
Slide 99
99
Slide 100
100
Slide 101
101
Slide 102
102
Slide 103
103
Slide 104
104
Slide 105
105
Slide 106
106
Slide 107
107
Slide 108
108
Slide 109
109
Slide 110
110
Slide 111
111
Slide 112
112
Slide 113
113
Slide 114
114
Slide 115
115
Slide 116
116
Slide 117
117
Slide 118
118
Slide 119
119
Slide 120
120
Slide 121
121
Slide 122
122
Slide 123
123
Slide 124
124
Slide 125
125

About This Presentation

g


Slide Content

Elemental Cost Analysis
Group 1

Group member
Pang KhaiShuen0318423 (leader)
Chong Hui Xin 0319363
Lee Jian Ru 0318132
Liu Wei Qian 0322969
Lu SiauVay0318567
MokPo Yi 0318207
Ng Seng He 0323037
Pan LekVun0323164
Sherlyn AngTseYun 0317977
Tan KiahChun 0324414
Yap JiaEn0319550
Yeo DorEen0316224

1 Block 20 Storey apartment (375 unit)
and public facilities (Level 5)

Project Details
Address: Above Lot 70285, PJU 10, 47810 PetalingJaya,
Selangor DahrulEhsan
Overall Size : 101.6m x 56.8m
Building Purposes : Residential
Type of Project : Private
Gross Floor Area : 45569m2

Key Plan

Location Plan

Site Plan

Form 1

Gross Floor Area

5
th
Floor
Gross Floor Area = 257.01m2

5A
th
Floor
Gross Floor Area = 2982.89m2

6
th
Floor
Gross Floor Area = 2180.90m2

Gross Floor Area = 2222.94m2 x 2Nos
= 4445.88m2
7
th
to 8
th
Floor

9
th
to 22
nd
Floor
Gross Floor Area = 2188.98m2 x 14 Nos
= 30645.72m2

23
rd
Floor
Gross Floor Area = 2253.89m2

24
th
Floor
Gross Floor Area = 2177.98m2

Roof Top
Gross Floor Area = 624.82m2

Total Gross Floor Area
Floor GFA (m2)
5
th
257.01
5A
th
2982.89
6
th
2180.90
7
th
–8
th
4445.88
9
th
–22
nd
30645.72
23
rd
2253.89
24
th
2177.98
Roof Top 624.82
TOTAL 45569.09

Usable Area –5Ath Floor

Usable Area –6
th
Floor

Usable Area-7
th
to 8
th
Floor

Usable Area –9
th
to 22
nd
Floor

Usable Area –23
rd
Floor

Usable Area –24
th
Floor
Total Usable Area = 31652m2

Circulation Area –5
th
Floor

Circulation Area –5Ath Floor

Circulation Area –6
th
Floor

Circulation Area –7
th
to 8
th
Floor

Circulation Area –9
th
to 22
nd
Floor

Circulatory Area –23
rd
Floor

Circulation Area –24
th
Floor

Circulation Area –Roof Top
Total Circulation Area = 4708m2

Ancillary Area –5
th
Floor

Ancillary Area –5Ath Floor

Ancillary Area –6
th
Floor

Ancillary Area –7
th
to 8
th
Floor

Ancillary Area –9
th
to 22
nd
Floor

Ancillary Area –23
rd
Floor

Ancillary Area –24
th
Floor

Ancillary Area –Roof Top
Total Ancillary Area = 963m2

Total Net Floor Area
Element Net Floor Area (m2)
Usable 31652
Circulation 4708
Ancillary 963
InternalDivision 8246
TOTAL 45569

Floor Space NOT Enclosed
Total unenclosed space = 168m2

Roof Area
Total Roof Area = 2,735.26m2

Functional Unit: 30,982 m2
�??????�??????��????????????????????????????????????
������??????���??????�????????????
=
17733.28
45569.09
= 0.389

Design/Shapes
Percentage of Gross Floor Area
a)Below GrdFlr. : -%
b)Single Storey Construction : -%
c)Two-Storey Construction : -%
d)3-Storey Construction : -%
e)20 Storey Construction : 100 %

Brief Cost Information
Contract Sums (RM): 59,103,612.65 Functional UnitCosts
excluding External
Works:
RM1883.23/m2
Provisional Sum (RM) :1,042,000.00
Prime Cost Sum (RM) :17,074,000.00
Preliminaries (RM) :3,665,896.39 being 6.61% of remainder
Contingencies (RM) :3,000,000.00 being 5.72% of Contract Sum
ContractSum less
Contingencies (RM) :
56,103,612.65

Form 2

Discount & Rationalisation
Factor Calculation
•CONTRACT SUM –Prime Cost Sums (Excluding Profit)
–Provisional Sums = 38,718,765.45
•Rationalised Cost Difference = 731,152.8
•100 –A/B = 0.9811163194

Total Cost of Element (RM)= 10,790,862.90
After Discount & Rationalisation(RM) = 10,587,091.69
Cost per m2 GFA (RM) = 232.33
Element Unit Quantity =45,569.00
Element Unit Rate (RM) =232.33
Element Ratio per m2 GFA =1.00
Reinforced Concrete (kg) = 10,959.00
Reinforcement (kg) = 1,235,963.96
Formwork (m2) = 120,579.00
Frame

Frame
•Frame Reinforcement Concrete and Sawn Formwork
RM4,082,977.20 RM1,786,265.00

•Frame Steel Rod and Fabric
Reinforcement
RM2,853,135.00RM70,112.00

•Frame Steel Rod and Fabric Reinforcement
RM562,383.00
RM1,416,206.20

Upper Floor
•Total Cost of Element (RM)= 4,702,008.45
•After Discount & Rationalisation(RM) = 4,613,217.22
•Cost per m2 GFA (RM) =101.24
•Element Unit Quantity =45,569.00
•Element Unit Rate (RM) =101.24
•Element Ratio per m2 GFA =1.00
•Reinforced Concrete (m3) = 6043.00
•Reinforcement (kg) = 414,567.22
•Formwork (m2) = 43,022.00

•Steel rod reinforcement
•Fabric reinforcement
Upper Floor

•UPPER FLOOR SAWN FORWORK

•UPPER FLOOR REINFORCED
CONCRETE

Roof
•Total Cost of Element (RM)= 2,009,838.75
•After Discount & Rationalisation(RM) = 1,880,811.61
•Cost per m2 GFA (RM) = 41.27
•Element Unit Quantity = 3,977.40
•Element Unit Rate (RM) = 472.87
•Element Ratio per m2 GFA = 0.09
•Reinforced Concrete (m3) = 293
•Reinforcement (kg) = 35,393
•Formwork (m2) =2403

Suspended Gutter Beam &
Plinth (Reinforced Concrete)

Formwork to sides and soffit of
Suspended Gutter Beam

Formwork to sides of plinth

Gutter Beam Reinforcement

Gutter Beam Mild Steel
Reinforcement
Plinth High Tensile Reinforcement

Formwork to Suspended Roof
Slab and Gutter Slab
BRC for Suspended Roof Slab
and Gutter Slab

SpecialisedButterfly Roof

Rainwater Downpipes

Step 1: Roof Sum –Roof structure Prime
Cost
Step 2: Add butterfly roof profit and
attendance
Step 3: Multiply 0.981116319
Step 4: Add roof structure and butterfly
roof prime cost
ROOF SUM:
Roof + RWDP + Frame & Slabs
[1,141,629.00+121,554.00+285,566.25
= 1,548,749.25]

ROOF SUM –Roof Structure PC:
[1,548,749.25 –762,000 = 786,49.25]
+ Butterfly Roof Profit and Attendance
[+ 10,110 = 796, 859.25]
Multiply 0.981116319
[x 0.981116319 = 781,811.62]
+ Roof Structure PC + Butterfly Roof PC
[+ 762,000 + 337,000 = 1,880,811.62]

Stairs
•Total Cost of Element (RM)= 452,140.30
•After Discount & Rationalisation(RM) = 447,378.96
•Cost per m2 GFA (RM) = 9.82
•Element UnitQuantity = N/A
•Element Unit Rate (RM) =N/A
•Element Ratio per m2 GFA =N/A
•Reinforced Concrete (m3) = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

Total cost of element (after Discount &
Rationalisation)
= (Stairs Sum + Handrailing)x
0.981116319 + Metal Ramp PC
= RM252,140.30 x 0.981116319 +
RM200,000
= RM447,378.96

External Wall
•Total Cost of Element (RM)= 499,582.05
•After Discount & Rationalisation(RM) = 490,148.10
•Cost per m2 GFA (RM) = 10.76
•Element UnitQuantity = 7352.00
•Element Unit Rate (RM) =66.67
•Element Ratio per m2 GFA =0.16
•Reinforced Concrete (m3) = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

External Wall

Windows and External Doors
•Total Cost of Element (RM)= 3,309,598.07
•After Discount & Rationalisation(RM) = 3,247,100.68
•Cost per m2 GFA (RM) = 71.26
•Element Unit Quantity = 12,148.82
•Element Unit Rate (RM) = 267.28
•Element Ratio per m2 GFA = 0.27
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

•Windows

•Doors

External door total cost
of element (door, frame
, painting & lintol
only)
= RM1,547,856.27

External door total cost
of element
(ironmongery only) =
RM86,137.50

Internal Walls & Partitions
•Total Cost of Element (RM)= 1,269,291.65
•After Discount & Rationalisation (RM) = 1,245,322.75
•Cost per m2 GFA (RM) = 27.33
•Element Unit Quantity = 25,091
•Element Unit Rate (RM) = 49.63
•Element Ratio per m2 GFA = 0.55
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

Internal Doors
•Total Cost of Element (RM)= 633,522.08
•After Discount & Rationalisation (RM) = 621,558.85
•Cost per m2 GFA (RM) = 13.64
•Element Unit Quantity (m2)= 7,368.48.00
•Element Unit Rate (RM) = 84.35
•Element Ratio per m2 GFA = 0.16
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

Internal door’s
door frame
Timber panel door

Internal door’s
Ironmongery
Internal
door’s lintol
Internal door’s
Painting

Internal Wall Finishes
•Total Cost of Element (RM)= 3,418,577.10
•After Discount & Rationalisation (RM) = 3,354,021.78
•Cost per m2 GFA (RM) = 73.60
•Element Unit Quantity = 266,785.00
•Element Unit Rate (RM) = 12.57
•Element Ratio per m2 GFA = 5.85
•Reinforced Concrete (m3) = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

Internal Wall Finishes

Internal Floor Finishes
•Total Cost of Element (RM)= 4,213,683.95
•After Discount & Rationalisation(RM) = 4,134,114.09
•Cost per m2 GFA (RM) = 90.72
•Element Unit Quantity = 40,638.00
•Element Unit Rate (RM) = 101.73
•Element Ratio per m2 GFA = 0.89
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

Internal Floor Finishes

Internal Ceiling Finishes
•Total Cost of Element (RM)= 947,834.90
•After Discount & Rationalisation (RM) = 929,936.29
•Cost per m2 GFA (RM) = 20.41
•Element Unit Quantity = 49,439.00
•Element Unit Rate (RM) = 18.81
•Element Ratio per m2 GFA = 1.08
•Reinforced Concrete (m3) =N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A

Internal Ceiling Finishes

External Finishes
•Total Cost of Element (RM)= 2,148,623.50
•After Discount & Rationalisation(RM) = 2,108,049.58
•Cost per m2 GFA (RM) = 46.26
•Element Unit Quantity = NA
•Element Unit Rate (RM) = NA
•Element Ratio per m2 GFA = NA
•Reinforced Concrete (m3) = NA
•Reinforcement (kg) =NA
•Formwork (m2) = NA

Breakdown
•External Finishes Sum:
•1,442,461.90
•Add Decorative Curvature Railing:
•687,508.80
•Add Handrailing:
•18652.80

External Finishes

External Finishes

External Finishes

Fittings and Furnishes
•Total Cost of Element (RM)= 220,500.00
•After Discount & Rationalisation(RM) = 220,471.67
•Cost per m2 GFA (RM) = 4.84
•Element Unit Quantity = NA
•Element Unit Rate (RM) = NA
•Element Ratio per m2 GFA = NA
•Reinforced Concrete (m3) = NA
•Reinforcement (kg) =NA
•Formwork (m2) = NA

Sanitary Appliances
•Total Cost of Element (RM)= 1,324,218.75
•After Discount & Rationalisation (RM) = 1,299,212.63
•Cost per m2 GFA (RM) = 28.51
•Element Unit Quantity =3695.00
•Element Unit Rate (RM) = 287.12
•Element Ratio per m2 GFA = 0.10
•Reinforced Concrete = NA
•Reinforcement (kg) = NA
•Formwork (m2) = NA

Prime cost and provisional list

Plumbing Installation
•Total Cost of Element (RM)= 3,290,000.00
•After Discount & Rationalisation(RM) = 3,290,000.00
•Cost per m2 GFA (RM) = 72.20
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Air-conditioning & Ventilation
System
•Total Cost of Element (RM)= 700,000.00
•After Discount & Rationalisation(RM) = 700,000.00
•Cost per m2 GFA (RM) = 15.36
•Element Unit Quantity =N/A (Tm3)
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Electrical Installation
•Total Cost of Element (RM)= 9,060,000.00
•After Discount & Rationalisation(RM) = 9,060,000.00
•Cost per m2 GFA (RM) = 198.82
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Fire Protection Installation
•Total Cost of Element (RM)= 875,000.00
•After Discount & Rationalisation(RM) = 875,000.00
•Cost per m2 GFA (RM) = 19.20
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Lift and Conveyor Installation
•Total Cost of Element (RM)= 1,500,000.00
•After Discount & Rationalisation(RM) = 1,500,000.00
•Cost per m2 GFA (RM) = 32.92
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Special Installation
•Total Cost of Element (RM)= 340,000.00
•After Discount & Rationalisation (RM) = 340,000.00
•Cost per m2 GFA (RM) = 24.12
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Builder’s Profit and Attendance
on Services
•Total Cost of Element (RM)= 462,750.00
•After Discount & Rationalisation (RM) = 454,011.58
•Cost per m2 GFA (RM) = 9.96
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Builder’s Work in Connection
with Services
•Total Cost of Element (RM)= 283,000.00
•After Discount & Rationalisation(RM) = 283,000.00
•Cost per m2 GFA (RM) = 6.21
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Site Work
•Total Cost of Element (RM) = 711,258.10
•After Discount & Rationalisation(RM) = 707,268.77
•Cost perm2 GFA (RM) = 15.52
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Recreational Facility
•Total Cost of Element (RM) = 50,000.00
•After Discount & Rationalisation(RM) = 50,000.00
•Cost perm2 GFA (RM) = 1.10
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A

Preliminary
•Total Cost of Element (RM) = 3,736,454.40
•After Discount & Rationalisation(RM) = 3,665,896.39
•Cost perm2 GFA (RM) = 80.45

Total (less contingencies)
Group of element Total cost
Superstructure 23,132,629.88
Finishes 10,526,121.74
Fittings and furnishings 220,471.67
Services 17,801,224.20
External work 757,268.77
Preliminaries 3,665,896.39
TOTAL: 56,103,612.65

Thank You
Tags