Group member
Pang KhaiShuen0318423 (leader)
Chong Hui Xin 0319363
Lee Jian Ru 0318132
Liu Wei Qian 0322969
Lu SiauVay0318567
MokPo Yi 0318207
Ng Seng He 0323037
Pan LekVun0323164
Sherlyn AngTseYun 0317977
Tan KiahChun 0324414
Yap JiaEn0319550
Yeo DorEen0316224
1 Block 20 Storey apartment (375 unit)
and public facilities (Level 5)
Project Details
Address: Above Lot 70285, PJU 10, 47810 PetalingJaya,
Selangor DahrulEhsan
Overall Size : 101.6m x 56.8m
Building Purposes : Residential
Type of Project : Private
Gross Floor Area : 45569m2
Key Plan
Location Plan
Site Plan
Form 1
Gross Floor Area
5
th
Floor
Gross Floor Area = 257.01m2
5A
th
Floor
Gross Floor Area = 2982.89m2
6
th
Floor
Gross Floor Area = 2180.90m2
Gross Floor Area = 2222.94m2 x 2Nos
= 4445.88m2
7
th
to 8
th
Floor
9
th
to 22
nd
Floor
Gross Floor Area = 2188.98m2 x 14 Nos
= 30645.72m2
23
rd
Floor
Gross Floor Area = 2253.89m2
24
th
Floor
Gross Floor Area = 2177.98m2
Roof Top
Gross Floor Area = 624.82m2
Total Gross Floor Area
Floor GFA (m2)
5
th
257.01
5A
th
2982.89
6
th
2180.90
7
th
–8
th
4445.88
9
th
–22
nd
30645.72
23
rd
2253.89
24
th
2177.98
Roof Top 624.82
TOTAL 45569.09
Usable Area –5Ath Floor
Usable Area –6
th
Floor
Usable Area-7
th
to 8
th
Floor
Usable Area –9
th
to 22
nd
Floor
Usable Area –23
rd
Floor
Usable Area –24
th
Floor
Total Usable Area = 31652m2
Circulation Area –5
th
Floor
Circulation Area –5Ath Floor
Circulation Area –6
th
Floor
Circulation Area –7
th
to 8
th
Floor
Circulation Area –9
th
to 22
nd
Floor
Circulatory Area –23
rd
Floor
Circulation Area –24
th
Floor
Circulation Area –Roof Top
Total Circulation Area = 4708m2
Ancillary Area –5
th
Floor
Ancillary Area –5Ath Floor
Ancillary Area –6
th
Floor
Ancillary Area –7
th
to 8
th
Floor
Ancillary Area –9
th
to 22
nd
Floor
Ancillary Area –23
rd
Floor
Ancillary Area –24
th
Floor
Ancillary Area –Roof Top
Total Ancillary Area = 963m2
Total Net Floor Area
Element Net Floor Area (m2)
Usable 31652
Circulation 4708
Ancillary 963
InternalDivision 8246
TOTAL 45569
Floor Space NOT Enclosed
Total unenclosed space = 168m2
Design/Shapes
Percentage of Gross Floor Area
a)Below GrdFlr. : -%
b)Single Storey Construction : -%
c)Two-Storey Construction : -%
d)3-Storey Construction : -%
e)20 Storey Construction : 100 %
Brief Cost Information
Contract Sums (RM): 59,103,612.65 Functional UnitCosts
excluding External
Works:
RM1883.23/m2
Provisional Sum (RM) :1,042,000.00
Prime Cost Sum (RM) :17,074,000.00
Preliminaries (RM) :3,665,896.39 being 6.61% of remainder
Contingencies (RM) :3,000,000.00 being 5.72% of Contract Sum
ContractSum less
Contingencies (RM) :
56,103,612.65
Total Cost of Element (RM)= 10,790,862.90
After Discount & Rationalisation(RM) = 10,587,091.69
Cost per m2 GFA (RM) = 232.33
Element Unit Quantity =45,569.00
Element Unit Rate (RM) =232.33
Element Ratio per m2 GFA =1.00
Reinforced Concrete (kg) = 10,959.00
Reinforcement (kg) = 1,235,963.96
Formwork (m2) = 120,579.00
Frame
Frame
•Frame Reinforcement Concrete and Sawn Formwork
RM4,082,977.20 RM1,786,265.00
•Frame Steel Rod and Fabric
Reinforcement
RM2,853,135.00RM70,112.00
•Frame Steel Rod and Fabric Reinforcement
RM562,383.00
RM1,416,206.20
Upper Floor
•Total Cost of Element (RM)= 4,702,008.45
•After Discount & Rationalisation(RM) = 4,613,217.22
•Cost per m2 GFA (RM) =101.24
•Element Unit Quantity =45,569.00
•Element Unit Rate (RM) =101.24
•Element Ratio per m2 GFA =1.00
•Reinforced Concrete (m3) = 6043.00
•Reinforcement (kg) = 414,567.22
•Formwork (m2) = 43,022.00
•Steel rod reinforcement
•Fabric reinforcement
Upper Floor
•UPPER FLOOR SAWN FORWORK
•UPPER FLOOR REINFORCED
CONCRETE
Roof
•Total Cost of Element (RM)= 2,009,838.75
•After Discount & Rationalisation(RM) = 1,880,811.61
•Cost per m2 GFA (RM) = 41.27
•Element Unit Quantity = 3,977.40
•Element Unit Rate (RM) = 472.87
•Element Ratio per m2 GFA = 0.09
•Reinforced Concrete (m3) = 293
•Reinforcement (kg) = 35,393
•Formwork (m2) =2403
Formwork to sides and soffit of
Suspended Gutter Beam
Formwork to sides of plinth
Gutter Beam Reinforcement
Gutter Beam Mild Steel
Reinforcement
Plinth High Tensile Reinforcement
Formwork to Suspended Roof
Slab and Gutter Slab
BRC for Suspended Roof Slab
and Gutter Slab
SpecialisedButterfly Roof
Rainwater Downpipes
Step 1: Roof Sum –Roof structure Prime
Cost
Step 2: Add butterfly roof profit and
attendance
Step 3: Multiply 0.981116319
Step 4: Add roof structure and butterfly
roof prime cost
ROOF SUM:
Roof + RWDP + Frame & Slabs
[1,141,629.00+121,554.00+285,566.25
= 1,548,749.25]
ROOF SUM –Roof Structure PC:
[1,548,749.25 –762,000 = 786,49.25]
+ Butterfly Roof Profit and Attendance
[+ 10,110 = 796, 859.25]
Multiply 0.981116319
[x 0.981116319 = 781,811.62]
+ Roof Structure PC + Butterfly Roof PC
[+ 762,000 + 337,000 = 1,880,811.62]
Stairs
•Total Cost of Element (RM)= 452,140.30
•After Discount & Rationalisation(RM) = 447,378.96
•Cost per m2 GFA (RM) = 9.82
•Element UnitQuantity = N/A
•Element Unit Rate (RM) =N/A
•Element Ratio per m2 GFA =N/A
•Reinforced Concrete (m3) = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
Total cost of element (after Discount &
Rationalisation)
= (Stairs Sum + Handrailing)x
0.981116319 + Metal Ramp PC
= RM252,140.30 x 0.981116319 +
RM200,000
= RM447,378.96
External Wall
•Total Cost of Element (RM)= 499,582.05
•After Discount & Rationalisation(RM) = 490,148.10
•Cost per m2 GFA (RM) = 10.76
•Element UnitQuantity = 7352.00
•Element Unit Rate (RM) =66.67
•Element Ratio per m2 GFA =0.16
•Reinforced Concrete (m3) = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
External Wall
Windows and External Doors
•Total Cost of Element (RM)= 3,309,598.07
•After Discount & Rationalisation(RM) = 3,247,100.68
•Cost per m2 GFA (RM) = 71.26
•Element Unit Quantity = 12,148.82
•Element Unit Rate (RM) = 267.28
•Element Ratio per m2 GFA = 0.27
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
•Windows
•Doors
External door total cost
of element (door, frame
, painting & lintol
only)
= RM1,547,856.27
External door total cost
of element
(ironmongery only) =
RM86,137.50
Internal Walls & Partitions
•Total Cost of Element (RM)= 1,269,291.65
•After Discount & Rationalisation (RM) = 1,245,322.75
•Cost per m2 GFA (RM) = 27.33
•Element Unit Quantity = 25,091
•Element Unit Rate (RM) = 49.63
•Element Ratio per m2 GFA = 0.55
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
Internal Doors
•Total Cost of Element (RM)= 633,522.08
•After Discount & Rationalisation (RM) = 621,558.85
•Cost per m2 GFA (RM) = 13.64
•Element Unit Quantity (m2)= 7,368.48.00
•Element Unit Rate (RM) = 84.35
•Element Ratio per m2 GFA = 0.16
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
Internal Wall Finishes
•Total Cost of Element (RM)= 3,418,577.10
•After Discount & Rationalisation (RM) = 3,354,021.78
•Cost per m2 GFA (RM) = 73.60
•Element Unit Quantity = 266,785.00
•Element Unit Rate (RM) = 12.57
•Element Ratio per m2 GFA = 5.85
•Reinforced Concrete (m3) = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
Internal Wall Finishes
Internal Floor Finishes
•Total Cost of Element (RM)= 4,213,683.95
•After Discount & Rationalisation(RM) = 4,134,114.09
•Cost per m2 GFA (RM) = 90.72
•Element Unit Quantity = 40,638.00
•Element Unit Rate (RM) = 101.73
•Element Ratio per m2 GFA = 0.89
•Reinforced Concrete = N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
Internal Floor Finishes
Internal Ceiling Finishes
•Total Cost of Element (RM)= 947,834.90
•After Discount & Rationalisation (RM) = 929,936.29
•Cost per m2 GFA (RM) = 20.41
•Element Unit Quantity = 49,439.00
•Element Unit Rate (RM) = 18.81
•Element Ratio per m2 GFA = 1.08
•Reinforced Concrete (m3) =N/A
•Reinforcement (kg) = N/A
•Formwork (m2) = N/A
Internal Ceiling Finishes
External Finishes
•Total Cost of Element (RM)= 2,148,623.50
•After Discount & Rationalisation(RM) = 2,108,049.58
•Cost per m2 GFA (RM) = 46.26
•Element Unit Quantity = NA
•Element Unit Rate (RM) = NA
•Element Ratio per m2 GFA = NA
•Reinforced Concrete (m3) = NA
•Reinforcement (kg) =NA
•Formwork (m2) = NA
Fittings and Furnishes
•Total Cost of Element (RM)= 220,500.00
•After Discount & Rationalisation(RM) = 220,471.67
•Cost per m2 GFA (RM) = 4.84
•Element Unit Quantity = NA
•Element Unit Rate (RM) = NA
•Element Ratio per m2 GFA = NA
•Reinforced Concrete (m3) = NA
•Reinforcement (kg) =NA
•Formwork (m2) = NA
Sanitary Appliances
•Total Cost of Element (RM)= 1,324,218.75
•After Discount & Rationalisation (RM) = 1,299,212.63
•Cost per m2 GFA (RM) = 28.51
•Element Unit Quantity =3695.00
•Element Unit Rate (RM) = 287.12
•Element Ratio per m2 GFA = 0.10
•Reinforced Concrete = NA
•Reinforcement (kg) = NA
•Formwork (m2) = NA
Prime cost and provisional list
Plumbing Installation
•Total Cost of Element (RM)= 3,290,000.00
•After Discount & Rationalisation(RM) = 3,290,000.00
•Cost per m2 GFA (RM) = 72.20
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Air-conditioning & Ventilation
System
•Total Cost of Element (RM)= 700,000.00
•After Discount & Rationalisation(RM) = 700,000.00
•Cost per m2 GFA (RM) = 15.36
•Element Unit Quantity =N/A (Tm3)
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Electrical Installation
•Total Cost of Element (RM)= 9,060,000.00
•After Discount & Rationalisation(RM) = 9,060,000.00
•Cost per m2 GFA (RM) = 198.82
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Fire Protection Installation
•Total Cost of Element (RM)= 875,000.00
•After Discount & Rationalisation(RM) = 875,000.00
•Cost per m2 GFA (RM) = 19.20
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Lift and Conveyor Installation
•Total Cost of Element (RM)= 1,500,000.00
•After Discount & Rationalisation(RM) = 1,500,000.00
•Cost per m2 GFA (RM) = 32.92
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Special Installation
•Total Cost of Element (RM)= 340,000.00
•After Discount & Rationalisation (RM) = 340,000.00
•Cost per m2 GFA (RM) = 24.12
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Builder’s Profit and Attendance
on Services
•Total Cost of Element (RM)= 462,750.00
•After Discount & Rationalisation (RM) = 454,011.58
•Cost per m2 GFA (RM) = 9.96
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Builder’s Work in Connection
with Services
•Total Cost of Element (RM)= 283,000.00
•After Discount & Rationalisation(RM) = 283,000.00
•Cost per m2 GFA (RM) = 6.21
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Site Work
•Total Cost of Element (RM) = 711,258.10
•After Discount & Rationalisation(RM) = 707,268.77
•Cost perm2 GFA (RM) = 15.52
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Recreational Facility
•Total Cost of Element (RM) = 50,000.00
•After Discount & Rationalisation(RM) = 50,000.00
•Cost perm2 GFA (RM) = 1.10
•Element Unit Quantity =N/A
•Element Unit Rate (RM) = N/A
•Element Ratio per m2 GFA = N/A
•Reinforced Concrete =N/A
•Reinforcement (kg) =N/A
•Formwork (m2) =N/A
Preliminary
•Total Cost of Element (RM) = 3,736,454.40
•After Discount & Rationalisation(RM) = 3,665,896.39
•Cost perm2 GFA (RM) = 80.45
Total (less contingencies)
Group of element Total cost
Superstructure 23,132,629.88
Finishes 10,526,121.74
Fittings and furnishings 220,471.67
Services 17,801,224.20
External work 757,268.77
Preliminaries 3,665,896.39
TOTAL: 56,103,612.65