TIME AND DELAY
•COMPENSATIONFORDELAY
–WITHMAXIMUMRATE@1%(ONEPERCENT)PERMONTHOF
DELAYTOBECOMPUTEDONPERDAYBASISBASEDON
QUANTUMOFDAMAGESUFFEREDDUETOSTATEDDELAYON
THEPARTOFCONTRACTOR
•INCENTIVESFOREARLYCOMPLETION
–INCASE,THECONTRACTORCOMPLETESTHEWORKAHEADOF
STIPULATEDDATEOFCOMPLETIONORJUSTIFIEDEXTENDED
DATEOFCOMPLETION,
[email protected]%(ZEROPOINTFIVE
PERCENT)OFTHETENDEREDVALUEPERMONTHCOMPUTED
ONPERDAYBASIS,SHALLBEPAYABLETOTHECONTRACTOR,
SUBJECTTOAMAXIMUMLIMITOF2%(TWOPERCENT)OF
THETENDEREDVALUE.
THISISSIMILARTOOTHERCONTRACTS.ABOVECRITERIONMAY
CHANGEFROMORGANISATIONTOORGANISATION.ABOVE
CRITERIONISOFCPWD