Determining Activities' Duration in the
Construction Schedule
Muhammad Zubair
B.E., MS (UK), PMP
y rN EDGE
a Ga \s 9 SCHOOL OF
EN i Y || CONSTRUCTION
UMSS À MANAGEMENT
An Activity, Lag, or Event?
% An activity:
= Duration > 0, uses resource and has a budget
€ A lag:
= Duration > 0, does not use resource, does not have budget
% An event (or milestone):
= Duration = 0, does not use resource , does not have budget
= An event likely has a responsibility, i.e. someone responsible
Activities Duration Slide No. 2
Who Determines Durations?
4 % It is strongly recommended for the scheduler not to
assign durations without consulting with the teams
(crews / subcontractors) leaders.
% In the end, the project manager must take a careful
look at the schedule and approve it; perhaps with
some adjustments.
= This implies the approval of all team leaders and subs.
Activities Duration Slide No. 3
How are Durations Determined?
4 Several methods are used to determine durations,
ranging from objective / calculated to subjective /
guesstimated:
a. Calculations based on average past performance or expected
production for a worker or a crew.
8. Calculations based on given equipment production rate.
c. Estimation based on expert opinion.
o. Estimation based on comparing to numbers in a reference.
= With assumptions in all cases.
Activities Duration Slide No. 4
1.
Source of Production Rates
Contractor’s own past records
= How close is the item considered to the one compared to?
. Ask crew leaders / subcontractors
Commercial databases such as RS Means or Spon's
price book
Internet
How reliable?
Activities Duration Slide No. 5
How are Durations Determined?
_1 $ Most importantly: Have all factors impacting the
production been considered?
a. In the “database”, and
8. The considered project and activity?
Activities Duration Slide No. 6
Productivity Numbers
@ When keeping a production rate in the database (or
importing it), some factors have to be considered:
3. Weather conditions 10. QA/QC and safety requirements
a. Design complexity 11. Work minutes / hour
s. Learning curves 12. Jobsite logistics and congestion
6. Fatigue 15. Any unexpected evets?
7. Multi-shift turnover 14. Does it represent “average
ir >
Soil condition (for excavation) production to you!
Activities Duration Slide No. 7
so
Productivity Numbers
% Now you have a “base” number as a reference, you
need to make proper adjustments based on the
current job situation.
= You can start with the same previous factors.
= For cost estimating purpose, there are other factors too.
Activities Duration Slide No. 8
Adjusting Numbers
Factors that have to do
with:
= The design of the project
= The climate / weather:
+ Temperature, humidity,
wind, precipitation,
visibility, lightning,
= Location / terrain /
elevation
= Jobsite congestion and
condition
Activities Duration
Workforce type and skill
level
Crew composition
Type and condition of
equipment and tools
used
Availability and readiness
of materials
Management style
Safety regulations
Slide No. 9
Importance of Durations Accuracy
. Knowing how long the crews are needed
4:
Calculating the cost of the activity
Determining the dates for dependent / succeeding
activities
Calculating the expected finish date for the project
So in general, the accuracy of activities’ duration
impacts both the time and cost aspects of the project.
‚Activities Duration Slide No. 10
Inaccurate Durations
% Impact of inaccurate durations
Delayed crews
Subcontractors conflicts
Wasted money
Shortage of materials / crews (if actual date is earlier)
Possible problems with cash flow
Disrupted plans and chaos
Impact on succeeding activities as well as the entire project
031113351000 | Flat plate, job-built plywood, to 15° high, 1 use sE a
—Q 031113351050 2use a
031113251100 3use a
031113351150 ause e
IL 031113351500 15' to 20' high ceilings, 4 use (a
031113351600 21' to 35' high ceilings, 4 use @
031113352000 Flatsleb, drop penels, job-built plywood, to 15' high, 1 use e
031113352050 2use SF e
031113352100 3 use SE a
031113352150 4use SE a
031113352250 15' to 20' high cej SE a 480.00 0.100
031113352350 20' to 35H ceilings, 4 use SE a 435.00 0.110
4,200 SF Elevated slab, 4 use, 18’ high
EN | a wre] Duration = 4200 / 495 = 8.5 x 9 days
Er an mu | ss zus | Labor hours = 4200 x 0.097 = 407.4, or
ELA, Daly Tos Fr] ET =6x8x8.5 = 408
‚Activities Duration Slide No. 14
Multi-Stage Activities
% Those activities performed by the same crew but with
different nature or location
= Wood framing
= Flooring
$ Those activities performed by different crews but
result in completion of same finished product
= Reinforced concrete items
4 Keep it as one activity or split it?
4 Use the KISS principle!
ad
Activities Duration Slide No. 15
Pictures from zum = A J l 1 |
CE Pl
| |
De No.16 à
Concrete Work
Picture from
Simplify...
4 4 In general, it is better to break the activity whenever
its portions are separated physically or by time.
= This simplifies all calculations: productivity, time, and money
= This also reduces the use of Start-to-Start (SS) and Finish-to-
Finish (FF) relationships and lags, which simplifies even more.
4 Calculate adiusted: Bare Mater Bare LabcBare Equipn Bare Total Total O&P
J : 0% 06 18 19
ı. Daily production
2. Labor hours / unit
3. Unit cost
‚Activities Duration Slide No. 27
Duration Adjustment
+ Adjusted daily production:
= 800 CY/day * (100% - 20%) = 640 CY / day
Adjusted labor hours per unit:
= 0.015 / (100% - 20%) = 0.01875 = 0.019
= Or Labor hours per day _ = = 0.01875 = 0.019
’ Crew Production per day ~ 64
4 Note that as one parameter increases, the other one
decreases, and vice versa
Activities Duration Slide No. 28
Let’s Not Forget...
1 $ The accurate estimation of crew production is important
to both estimating and scheduling
Crew Cost per day <———— Constant
4 Unit Price - ——— ———
Crew Production per day < Variable
Total Quantity <——— Constant
Crew Production per day < Variable
% Unit price and duration are inversely proportional to
$ Duration =
production rate
Activities Duration Slide No. 29
Activities with Variable (Non-
Linear) Production
4 There are several ways to deal with activities with
non-linear production:
1. If the productivity variation (non-linearity) is small, you can
ignore it. For example, installing concrete blocks for a 5' or 6’
wall.
2. Split the activity to homogeneous activities (each with
assumed linearity)
3. Use the software tools to divide the activity into steps and
distribute the resources per step
Activities Duration Slide No. 30
Duration Risk Management
% How do you account for risk in the project?
= At the activity level, i.e. part of the duration?
= At the entire project level, i.e. independent of activities’
duration? or
= Both?
Activities Duration Slide No. 31
Duration Risk
Allowance
Duration Uncertainty
Xp
>
Most Likely
Duration
Expected
Duration
11
Activities Duration
=.—>
1
Pessimistic
Duration
18
Slide No. 32
Time Contingency
1% It is not recommended to add extra time to activity
duration due to risk calculations, but the risk impact is
estimated for the entire path, and added within the
project but outside the activities.
= If added within the activity, it will be used no matter what.
= It will become the “norm” for next time.
= So keep the activities durations lean!
= Activity duration may still have little “fluff” due to rounding.
® When updating the schedule, officially or unofficially,
certain activities will be off the track; ahead or behind.
= If the schedule variance is small, it can be dismissed as
normal and expected variation.
= If the schedule variance is major, you need to analyze and
pinpoint the cause:
A. Something went wrong with this activity,
B. Certain factors were not considered when estimating the
duration, or
C. The number in the database was inaccurate
Activities Duration Slide No. 35
Duration While Updating
$ Example: An excavation activity, 11,500 CY, using a
crew with an estimated production of 700 CY/day.
= Estimated duration = 11,500 / 700 = 16.43 x 17 days
= Five days later, 2,420 CY only were excavated:
+ Baseline % complete = 30.4%, Actual % complete = 21.0%
= If everything was normal, i.e. no unexpected problems, then
remaining duration must be corrected based on actual
production, 484 CY/day:
+ RD = 24-5 = 19 days, and WOT 17-5 = 12 days