Flowchart of WorkFlowchart of WorkFlowchart of Work.pptx

achmadsyaifudin1011 19 views 23 slides Sep 30, 2024
Slide 1
Slide 1 of 23
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23

About This Presentation

Flowchart of Work


Slide Content

START GENERAL SUBMISSION CHECK NO YES FINISH GIVAUDAN JAYA PHASE TWO (JPT) WORK FLOW FOR WP03 & WP09 - EHS PLAN - QUALITY PLAN ENGINEERING SUBMISSION CHECK - SITE SURVEY - SHOP DWG NO YES PROCURING SUBMISSION - PROCURE PLAN - MATERIAL APPROVAL CHECK NO

INTERIOR WALL WALL WORK CEMENT-SAND BRICK WORK PU WALL PANEL OPENING & INSTALL WORK DOORS WINDOW/LOUVRE CEILING WORK FLOOR FINISH WORK EPOXY DIECAST PU CEILING PANEL PAINTING WORK EXTERIOR WALL

START PREPARATION 3 LINE BASE M ARKING I NSTALL PRACTICAL COLUMN EVERY 3 M LONG INSTALL 6-8 LAYER OF BRICK INSTALL REBAR DOWEL AT 3-4 LAYER OF BRICK CHECK CHECK YES NO YES NO FINISH WALL WORK CEMENT-SAND BRICK WORK INSTALL FORMWORK PRACTICAL COLUMN CASTING CONCRETE PRACTICAL COLUMN REPEAT STEP ABOVE UNTIL EL. +3.500 INSTALL PRACTICAL BEAM EL. +3.500 CHECK YES NO INSTALL FORMWORK PRACTICAL BEAM CASTING CONCRETE PRACTICAL BEAM REPEAT ALL STEP BEFORE UNTIL EL. +7.000 INSTALL BAN-BANAN EVERY 1-2 M CHECK YES NO APPLY MIX SAND - CEMENT APPLY CEMENT MORTAR FINISH FLATTING SURFACE WITH IRON ROD CHECK YES NO APPLY PAINTING CHECK YES NO YES

START PREPARATION LINE BASE M ARKING INSTALL C RUNNER INSTALL PU WALL PANEL CHECK CHECK YES NO YES NO FINISH WALL WORK POLYURETHANE PANEL C UTTING OPENING INSTALL EXTRUSION ANGLE AND CURVING CHECK YES NO REPEAT ALL STEP CHECK NO YES

START PREPARATION LINE BASE M ARKING INSTALL CNP SUPPORT INSTALL SUSPENSION ROD CHECK CHECK YES NO YES NO FINISH CEILING WORK POLYURETHANE PANEL INSTAL EXTRUSION T-BAR INSTALL PU PANEL CEILING CHECK YES NO REPEAT ALL STEP CHECK NO YES INSTAL EXTRUSION ANGLE

START PREPARATION 2 LINE BASE M ARKING I NSTALL PRACTICAL COLUMN EVERY 3 M LONG INSTALL 6-8 LAYER OF BRICK INSTALL REBAR DOWEL AT 3-4 LAYER OF BRICK CHECK CHECK YES NO YES NO FINISH WALL WORK POLYURETHANE WALL WORK INSTALL FORMWORK PRACTICAL COLUMN CASTING CONCRETE PRACTICAL COLUMN REPEAT STEP ABOVE UNTIL EL. +3.500 INSTALL PRACTICAL BEAM EL. +3.500 CHECK YES NO INSTALL FORMWORK PRACTICAL BEAM CASTING CONCRETE PRACTICAL BEAM REPEAT ALL STEP BEFORE UNTIL EL. +7.000 INSTALL BAN-BANAN EVERY 1-2 M CHECK YES NO APPLY MIX SAND - CEMENT APPLY CEMENT MORTAR FINISH FLATTING SURFACE WITH IRON ROD CHECK YES NO

START TIGHTENING BOLT FINISH VERTICALITY STEEL STRUCTURE INSTALL BONDECK POSITIONING MOBILE PUMP AND CONCRETE PIPE INSTALL REBAR BRICK WALL PLASTERING INSTALL STUD REMOVE FORMWORK CURING PAINTING INSTALL RELAT PIPE INSTALL SCREEDER DOOR-WINDOW-LOUVRE APPLY FLOOR HARDENER STEEL TROWEL FINISH PROTECTION CONCRETE SURFACE GROUTING PEDESTAL COLUMN INSTALL SCAFFOLDING AND BARRICADE INSTALL FORMWORK POURING CONCRETE PROTECTION CONCRETE SURFACE

START PREPARATION SETTING OUT EXCAVATION CUT PILE LEAN CONCRETE INSTALL MS BAR PILE CAP REBAR WORK CHECK PILE CAP FORM WORK CHECK CASTING CONCRETE YES NO YES NO FINISH

START PEDESTAL COLUMN REBAR WORK CHECK INSTALL HD BOLT ANCHOR CHECK CASTING CONCRETE PEDESTAL COLUMN YES NO YES NO FINISH PEDESTAL COLUMN FORMWORK CHECK YES NO

GROUND BEAM FORMWORK START EXCAVATION GROUND BEAM CHECK CASTING CONCRETE GROUND BEAM YES NO FINISH CHECK YES NO LEAN CONCRETE GROUND BEAM REBAR WORK

GROUND BEAM FORMWORK START EXCAVATION BEAM CHECK CASTING CONCRETE BEAM YES NO FINISH CHECK YES NO LEAN CONCRETE GROUND BEAM REBAR WORK PREPARATION LEVELING AND COMPACTION CHECK YES NO BEAM BOTTOM FW

COMPACTION BASECORSE START BACKFILL SOIL CHECK INSTALL SLAB REBAR YES NO FINISH CHECK YES NO COMPACTED SUBGRADE FILL BASECORSE CHECK YES NO INSTALL FORMWORK SLAB CHECK NO CASTING CONCRETE SLAB YES

LEAN CONCRETE LEAN CONCRETE START BACKFILL SOIL CHECK INSTALL SLAB REBAR YES NO FINISH CHECK YES NO COMPACTED & LEVELING SUBGRADE CHECK YES NO INSTALL FORMWORK SLAB CHECK NO CASTING CONCRETE SLAB YES

LEAN CONCRETE LEAN CONCRETE AND PU PLASTIC SHEET START BACKFILL SUB BASE - SUBGRADE CHECK INSTALL STAINLESS STEEL GUTTER & FRAME GI GRATING YES NO FINISH CHECK YES NO COMPACTED & LEVELING SUB BASE - SUBGRADE CHECK YES NO INSTALL FORMWORK SLAB, PLINTH, AND TRENCH CHECK NO CASTING CONCRETE SLAB AND PLINTH YES INSTALL SLAB & PLINTH REBAR

BEAM FORMWORK START EXCAVATION BEAM CHECK CASTING CONCRETE BEAM YES NO FINISH CHECK YES NO LEAN CONCRETE BEAM REBAR WORK PREPARATION LEVELING AND COMPACTION CHECK YES NO BEAM BOTTOM FW

H EAVIEST CRANE MOVE TO WORKING ROAD START CHECK MOVE TEST, JACKING TEST, LOAD TEST NO FINISH STACKING STEEL PLATES AT WORKING ROAD LEVELING AND COMPACTION WORKING ROAD CHECK YES NO READY TO STEEL ERECTION YES

START STEEL STRUCTURE VERTICALLITY CHECK TIGHTENING BOLT CHECK INSTALL SCAFFOLDING & BARRICADE YES NO YES NO FINISH G ROUTING COLUMN CHECK YES NO CHECK YES NO

START INSTALL BONDECK CHECK INSTALL FORMWORK CHECK PREPARATION OF CONCRETE YES NO YES NO FINISH INSTALL STUD & REBAR CHECK YES NO CHECK YES NO

START TIGHTENING BOLT FINISH VERTICALITY STEEL STRUCTURE INSTALL BONDECK POSITIONING MOBILE PUMP AND CONCRETE PIPE INSTALL REBAR PREPARATION WORK INSTALL FLOOR INSTALL STUD REMOVE FORMWORK CURING CASTING CONCRETE INSTALL RELAT PIPE INSTALL SCREEDER APPLY FLOOR HARDENER FINISHING APPLY FLOOR HARDENER STEEL TROWEL FINISH PROTECTION CONCRETE SURFACE GROUTING PEDESTAL COLUMN INSTALL SCAFFOLDING AND BARRICADE INSTALL FORMWORK POURING CONCRETE PROTECTION CONCRETE SURFACE

START PREPARATION CURING MATERIAL CHECK YES NO FINISH PREPARATION CURING TOOL CHECK YES NO REMOVE SIDE FORMWORK CHECK CURING YES NO INSTALL FLOOR PROTECTION CHECK

START PREPARATION HARDENER MATERIAL CHECK YES NO FINISH PREPARATION HARDENER TOOL CHECK YES NO PREPARATION CURING MATERIAL CHECK BRIEFING WORKER YES NO A PPLY HARDENER

START PREPARATION CONCRETE SUPPLY CHECK INSTALL RELAT LEVELING CHECK INSTALL SCREEDER YES NO YES NO FINISH POSITIONING CONCRETE MOBILE PUMP CHECK YES NO CHECK YES NO PREPARATION CONCRETING TOOLS CHECK BRIEFING WORKER YES NO POURING CONCRETE
Tags