START GENERAL SUBMISSION CHECK NO YES FINISH GIVAUDAN JAYA PHASE TWO (JPT) WORK FLOW FOR WP03 & WP09 - EHS PLAN - QUALITY PLAN ENGINEERING SUBMISSION CHECK - SITE SURVEY - SHOP DWG NO YES PROCURING SUBMISSION - PROCURE PLAN - MATERIAL APPROVAL CHECK NO
INTERIOR WALL WALL WORK CEMENT-SAND BRICK WORK PU WALL PANEL OPENING & INSTALL WORK DOORS WINDOW/LOUVRE CEILING WORK FLOOR FINISH WORK EPOXY DIECAST PU CEILING PANEL PAINTING WORK EXTERIOR WALL
START PREPARATION 3 LINE BASE M ARKING I NSTALL PRACTICAL COLUMN EVERY 3 M LONG INSTALL 6-8 LAYER OF BRICK INSTALL REBAR DOWEL AT 3-4 LAYER OF BRICK CHECK CHECK YES NO YES NO FINISH WALL WORK CEMENT-SAND BRICK WORK INSTALL FORMWORK PRACTICAL COLUMN CASTING CONCRETE PRACTICAL COLUMN REPEAT STEP ABOVE UNTIL EL. +3.500 INSTALL PRACTICAL BEAM EL. +3.500 CHECK YES NO INSTALL FORMWORK PRACTICAL BEAM CASTING CONCRETE PRACTICAL BEAM REPEAT ALL STEP BEFORE UNTIL EL. +7.000 INSTALL BAN-BANAN EVERY 1-2 M CHECK YES NO APPLY MIX SAND - CEMENT APPLY CEMENT MORTAR FINISH FLATTING SURFACE WITH IRON ROD CHECK YES NO APPLY PAINTING CHECK YES NO YES
START PREPARATION LINE BASE M ARKING INSTALL C RUNNER INSTALL PU WALL PANEL CHECK CHECK YES NO YES NO FINISH WALL WORK POLYURETHANE PANEL C UTTING OPENING INSTALL EXTRUSION ANGLE AND CURVING CHECK YES NO REPEAT ALL STEP CHECK NO YES
START PREPARATION LINE BASE M ARKING INSTALL CNP SUPPORT INSTALL SUSPENSION ROD CHECK CHECK YES NO YES NO FINISH CEILING WORK POLYURETHANE PANEL INSTAL EXTRUSION T-BAR INSTALL PU PANEL CEILING CHECK YES NO REPEAT ALL STEP CHECK NO YES INSTAL EXTRUSION ANGLE
START PREPARATION 2 LINE BASE M ARKING I NSTALL PRACTICAL COLUMN EVERY 3 M LONG INSTALL 6-8 LAYER OF BRICK INSTALL REBAR DOWEL AT 3-4 LAYER OF BRICK CHECK CHECK YES NO YES NO FINISH WALL WORK POLYURETHANE WALL WORK INSTALL FORMWORK PRACTICAL COLUMN CASTING CONCRETE PRACTICAL COLUMN REPEAT STEP ABOVE UNTIL EL. +3.500 INSTALL PRACTICAL BEAM EL. +3.500 CHECK YES NO INSTALL FORMWORK PRACTICAL BEAM CASTING CONCRETE PRACTICAL BEAM REPEAT ALL STEP BEFORE UNTIL EL. +7.000 INSTALL BAN-BANAN EVERY 1-2 M CHECK YES NO APPLY MIX SAND - CEMENT APPLY CEMENT MORTAR FINISH FLATTING SURFACE WITH IRON ROD CHECK YES NO
START PREPARATION SETTING OUT EXCAVATION CUT PILE LEAN CONCRETE INSTALL MS BAR PILE CAP REBAR WORK CHECK PILE CAP FORM WORK CHECK CASTING CONCRETE YES NO YES NO FINISH
START PEDESTAL COLUMN REBAR WORK CHECK INSTALL HD BOLT ANCHOR CHECK CASTING CONCRETE PEDESTAL COLUMN YES NO YES NO FINISH PEDESTAL COLUMN FORMWORK CHECK YES NO
GROUND BEAM FORMWORK START EXCAVATION GROUND BEAM CHECK CASTING CONCRETE GROUND BEAM YES NO FINISH CHECK YES NO LEAN CONCRETE GROUND BEAM REBAR WORK
GROUND BEAM FORMWORK START EXCAVATION BEAM CHECK CASTING CONCRETE BEAM YES NO FINISH CHECK YES NO LEAN CONCRETE GROUND BEAM REBAR WORK PREPARATION LEVELING AND COMPACTION CHECK YES NO BEAM BOTTOM FW
COMPACTION BASECORSE START BACKFILL SOIL CHECK INSTALL SLAB REBAR YES NO FINISH CHECK YES NO COMPACTED SUBGRADE FILL BASECORSE CHECK YES NO INSTALL FORMWORK SLAB CHECK NO CASTING CONCRETE SLAB YES
LEAN CONCRETE LEAN CONCRETE START BACKFILL SOIL CHECK INSTALL SLAB REBAR YES NO FINISH CHECK YES NO COMPACTED & LEVELING SUBGRADE CHECK YES NO INSTALL FORMWORK SLAB CHECK NO CASTING CONCRETE SLAB YES
LEAN CONCRETE LEAN CONCRETE AND PU PLASTIC SHEET START BACKFILL SUB BASE - SUBGRADE CHECK INSTALL STAINLESS STEEL GUTTER & FRAME GI GRATING YES NO FINISH CHECK YES NO COMPACTED & LEVELING SUB BASE - SUBGRADE CHECK YES NO INSTALL FORMWORK SLAB, PLINTH, AND TRENCH CHECK NO CASTING CONCRETE SLAB AND PLINTH YES INSTALL SLAB & PLINTH REBAR
BEAM FORMWORK START EXCAVATION BEAM CHECK CASTING CONCRETE BEAM YES NO FINISH CHECK YES NO LEAN CONCRETE BEAM REBAR WORK PREPARATION LEVELING AND COMPACTION CHECK YES NO BEAM BOTTOM FW
H EAVIEST CRANE MOVE TO WORKING ROAD START CHECK MOVE TEST, JACKING TEST, LOAD TEST NO FINISH STACKING STEEL PLATES AT WORKING ROAD LEVELING AND COMPACTION WORKING ROAD CHECK YES NO READY TO STEEL ERECTION YES
START STEEL STRUCTURE VERTICALLITY CHECK TIGHTENING BOLT CHECK INSTALL SCAFFOLDING & BARRICADE YES NO YES NO FINISH G ROUTING COLUMN CHECK YES NO CHECK YES NO
START INSTALL BONDECK CHECK INSTALL FORMWORK CHECK PREPARATION OF CONCRETE YES NO YES NO FINISH INSTALL STUD & REBAR CHECK YES NO CHECK YES NO
START PREPARATION CURING MATERIAL CHECK YES NO FINISH PREPARATION CURING TOOL CHECK YES NO REMOVE SIDE FORMWORK CHECK CURING YES NO INSTALL FLOOR PROTECTION CHECK
START PREPARATION HARDENER MATERIAL CHECK YES NO FINISH PREPARATION HARDENER TOOL CHECK YES NO PREPARATION CURING MATERIAL CHECK BRIEFING WORKER YES NO A PPLY HARDENER
START PREPARATION CONCRETE SUPPLY CHECK INSTALL RELAT LEVELING CHECK INSTALL SCREEDER YES NO YES NO FINISH POSITIONING CONCRETE MOBILE PUMP CHECK YES NO CHECK YES NO PREPARATION CONCRETING TOOLS CHECK BRIEFING WORKER YES NO POURING CONCRETE