Free CAPM Exam Sample Question

pmpodcast 8 views 4 slides Aug 08, 2023
Slide 1
Slide 1 of 4
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4

About This Presentation

CAPM Exam sample question of the week from The CAPM Exam Simulator


Slide Content

CAMP Exam
Sample Q & A

The failure rate is an example of which of the following?
A. Quality metrics
B. Process metrics
C. Quality checklists
D. Quality control measurements
HINT: Note that failure rate is a product attribute.
QUESTION:

The correct answer is A.
Quality metrics are usually about a project or product attributes and used in both quality
assurance and quality control to ensure the project meets the quality objectives such as
on-time milestones, failure rate, or requirement stability. While quality control
measurements and process metrics are about the process indicators, a quality checklist is
a list used to verify that a set of steps has been performed.
ANSWER:

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.