Free CAPM Exam Sample Question of the Week

pmpodcast 15 views 4 slides Aug 13, 2024
Slide 1
Slide 1 of 4
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4

About This Presentation

Here is our free CAPM exam sample question for this week.

*Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.


Slide Content

CAMP Exam
Sample Q & A

Which of the following needs to be updated during the closing phase of a project?
A. WBS
B. Quality management plan
C. Benchmarks
D. Operational and support documents
HINT: Think which option is a valid output to the Close Project or Phase process.
QUESTION:

The correct answer is D.
The Close Project or Phase process has the following outputs:
1. Project document updates
2. Final product, service, or result transition
3. Final report
4. Organizational process assets updates
The organizational process assets that are updated as a result of the Close Project or Phase
process include project documents, operational and support documents, project or phase
closure documents, and lessons learned repository.
ANSWER:

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.