Durgapur - Haldia Pipeline Scope: Main Line: 30"X 113 Km & 24"X151 Km, CGS Kolkata: 18" X 19 Km, IOCL Haldia: 18"x11 Km. Benefits: Pipeline will supply natural gas to IOCL, Haldia, CGS Kolkata & other CGD enroute.
SV stations in 3B section Section A Station Mouzas /Block Status SV 35 Goligram/Galsi-II Bardhaman Construction under process SV 36 Malkita /Bardhaman-I Construction under process Construction under process SV 37 Baje Rasulpur / Memari -II SV 38 Torgram /Pandua Hooghly Registration not done IP 08 Rajarambati /Mogra- Chunsura Registration not done Section B SV 39 Garjji / Bhadreshwar Registration not done SV 40 Singjor / Chanditala-1 Registration not done SV 41 Serpur / Amta -I Howrah Registration not done SV 42 Chandanapara / Bagnan-II Construction not yet started SV 43 Bhubankalua / Tamluk -I Purba Medinipur Registration completed SV 44 Sitalpur / Nandkumar Registration not done RT Haldia Barbajitpur/ Sutahata -II Construction not yet started IOCL Haldia Refinery Shobharampur / Sutahata 3(1) not cleared by SLAO Section C RT Gayeshpur Gayeshpur / Chakadah Nadia Registration not done
Major Issues for Execution Slow disbursement/ Low payment percentage of compensation which is a cause of hindrance Continuous , all season cultivation N numerous reroutes Demand for Higher Compensation by Road Side Plot owners Land record issues