LDWAUG 27, 2022 JASBUILT ACCOMPLISHMENT.pptx

16tiktoktreats 25 views 24 slides Oct 01, 2024
Slide 1
Slide 1 of 24
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24

About This Presentation

Weekly Report


Slide Content

PARK RESIDENCES Brgy. Tagapo, City of Santa Rosa Laguna WEEKLY ACCOMPLISHMENT REPORT JASBUILT CONSTRUCTION LAND DEVELOPMENT WORKS Date Covered: AUG 20, 2022-AUG 27,2022

Accomplishment Report Park Residences OVER ALL ACCOMPLISHMENT (REVISED SCHEDULE) LAND DEVELOPMENT WORKS ITEM TO DATE (AUG 20, 2022) THIS PERIOD (AUG 20-27, 2022) TO DATE (AUG 27, 2022) TARGET ACCOMPLISHMENT 99.72% 0.10% 99.82% ACTUAL ACCOMPLISHMENT 71.11% 0.01% 71.12% VARIANCE (%) -28.61% -0.09% -28.7% TIME ELAPSED 98.68% 0.44% 99.12% NO. OF DAYS AHEAD/ DELAY 192 DAYS 1 DAY 193 DAYS

Accomplishment Report Park Residences PHASE 1 ACCOMPLISHMENT (REVISED SCHEDULE) LAND DEVELOPMENT WORKS ITEM TO DATE (AUG 20, 2022) THIS PERIOD (AUG 20-27, 2022) TO DATE (AUG 27, 2022) TARGET ACCOMPLISHMENT 99.72% 0.10% 99.82% ACTUAL ACCOMPLISHMENT 77.15% 0.03% 77.18% VARIANCE (%) -22.57% -0.07% -22.64% TIME ELAPSED 98.68% 0.44% 99.12% NO. OF DAYS AHEAD/ DELAY 152 DAYS 1 DAY 153 DAYS

Accomplishment Report Park Residences PHASE 2 ACCOMPLISHMENT (REVISED SCHEDULE) LAND DEVELOPMENT WORKS ITEM TO DATE (AUG 20, 2022) THIS PERIOD (AUG 20-27, 2022) TO DATE (AUG 27, 2022) TARGET ACCOMPLISHMENT 99.72% 0.10% 99.82% ACTUAL ACCOMPLISHMENT 63.24% VARIANCE (%) -36.48% TIME ELAPSED 98.68% 0.44% 99.12% NO. OF DAYS AHEAD/ DELAY 245 DAYS

BACK LOG TOTAL VOLUME (BACK LOG): 18.0 m 3 DESCRIPTION ESTIMATED VOLUME (m³) EQUIVALENT LINEAR METER DESIGN MIX DATE OF POURING PARKING AREA INFRONT OF BUILDING B 3 m³ 5 lm 3500 psi AUG 28, 2022 PARKING – NEAR BLDG. G 15 m³ 17 lm 3500 psi AUG 28, 2022 CONCRETE MONITORING (AS PER CONCRETE PAVEMENT SCHEDULE ) Park Residences

TRENCH CANAL Park Residences CONCRETE POURING OF BOTTOM SLAB AT TRENCH CANAL

PCCP Park Residences CONCRETE POURING OF ENCASEMENT FOR CURBS & GUTTER

BACK LOG TOTAL VOLUME (BACK LOG): 72.2m 3 DESCRIPTION ESTIMATED VOLUME (m³) EQUIVALENT LINEAR METER DESIGN MIX DATE OF POURING PARKING – NEAR BLDG. G AND POOL 31.2 m³ 31.2 lm 3500 psi DECEMBER 1, 2021 ROAD 1 - RIGHT LANE NEAR BLDG. G 38.5 m³ 55 lm 3500 psi DECEMBER 1, 2021 ROAD 1 LEFT LANE NEAR BLDG. G 2.50 m³ 3.56 lm 3500 psi AUG 23, 2022 CONCRETE MONITORING (AS PER CONCRETE PAVEMENT SCHEDULE ) Park Residences DESCRIPTION ESTIMATED VOLUME (m³) EQUIVALENT LINEAR METER DESIGN MIX DATE OF POURING PARKING – NEAR BLDG. G AND POOL 31.2 m³ 31.2 lm 3500 psi AUG 23, 2022 ROAD 1 - RIGHT LANE NEAR BLDG. G 38.5 m³ 55 lm 3500 psi AUG 23, 2022

PCCP Park Residences word ROAD PAVEMENT = 85.96 % PARKING = 49.66 % ACCOMPLISHMENT CONCRETE POURED (ROAD) CONCRETE POURED (PARKING) CONCRETE POURED (SIDEWALK AND CURBS & GUTTER)

TRENCH CANAL Park Residences TRENCH CANAL (1mx1m) TOTAL QUANTITY: 113 linear meter DONE: 93 linear meter ONGOING: 17 linear meter REMAINING: 3 linear meter TRENCH CANAL (1mx0.8m) TOTAL QUANTITY: 18.446 linear meter DONE: 7 linear meter ONGOING: NA REMAINING: 11.446 linear meter

TRENCH CANAL (1X1M) Park Residences DONE (93 LM) REMAINING (3 LM) ON GOING (17LM) ACTUAL ACCOMPLISHMENT: 82.30%

TRENCH CANAL (1X0.8LM) Park Residences DONE (7 LM) REMAINING (11.446) ON GOING (NA) ACTUAL ACCOMPLISHMENT: 61.15%

BOX CULVERT Park Residences BOX CULVERT (1mx1m) TOTAL QUANTITY: 27 LINEAR METER DONE: 27 LINEAR METER ONGOING: NA REMAINING: NA BOX CULVERT (1mx0.8m) TOTAL QUANTITY: 47.36 LINEAR METER DONE: 42.9 LINEAR METER ONGOING: NA REMAINING: 4.5 LINEAR METER

BOX CULVERT (1X0.8M) Park Residences DONE (42.9 LM) REMAINING (4.5 LM) ON GOING (NA) ACTUAL ACCOMPLISHMENT: 90.60 %

ENCASEMENT Park Residences CONCRETE POURING OF ENCASEMENT

CURBS & GUTTER Park Residences CONCRETE POURING OF CURBS AND GUTTER

ECE AUXILLARY Park Residences

STORM DRAINAGE SYSTEM Park Residences MANHOLE TOTAL QUANTITY: 81 pcs. DONE: 59 pcs. ONGOING: 4 pcs. REMAINING: 18 pcs. RCP TOTAL QUANTITY: 1592 pcs. DONE: 1048 pcs. ONGOING: 3 pcs. REMAINING: 540 pcs. PERCENTAGE 72.83 % 4.93 % 22.22 % PERCENTAGE 65.83% 0.25 % 33.92%

STORM DRAINAGE SYSTEM Park Residences

STORM DRAINAGE SYSTEM Park Residences

FIRE PROTECTION SYSTEM Park Residences

MANPOWER LOADING Park Residences DIRECT WORKERS ENGINEER 5 OPERATOR 2 SAFETY OFFICER 1 DRIVER 1 TIMEKEEPER/DOCS CON 1 TOTAL 33 INDIRECT WORKERS FOREMAN 2 SKILLED/ADMIN 4 RUNNER 1 SAFETY CREW 1 LABOR 7 CARPENTER 2 SUBCON MATTIAS 4 ELECTRICIAN 2

ISSUES AND CONCERNS Park Residences ITEM NO. RFA/RFI No. Transmittal Sheet No. Item Description Date of Submittal AGING/REMARKS JASBUILT to ACMC ACMC to JASBUILT JASBUILT to ACMC Forwarded Received ITEM RFI/RFA NO. TRANS. NO. DESCRIPTION DATE OF SUBMITTAL AGING/ REMARKS 1.0 RFI-JSBLT-PARK-AR-012 480 PARKING FINISH MAY 17, 2022 15 DAYS 2.0 RFI-JSBLT-PARK-AR-013 482 DESIGN FINISH AROUND THE CLUBHOUSE JUNE 1, 2022 3.0 RFA-JSBLT-PARK-AR-015 291 SAMPLE BOARD FOR CLUBHOUSE FEBRUARY 24, 2022 99 DAYS