PARK RESIDENCES Brgy. Tagapo, City of Santa Rosa Laguna WEEKLY ACCOMPLISHMENT REPORT JASBUILT CONSTRUCTION LAND DEVELOPMENT WORKS Date Covered: AUG 20, 2022-AUG 27,2022
Accomplishment Report Park Residences OVER ALL ACCOMPLISHMENT (REVISED SCHEDULE) LAND DEVELOPMENT WORKS ITEM TO DATE (AUG 20, 2022) THIS PERIOD (AUG 20-27, 2022) TO DATE (AUG 27, 2022) TARGET ACCOMPLISHMENT 99.72% 0.10% 99.82% ACTUAL ACCOMPLISHMENT 71.11% 0.01% 71.12% VARIANCE (%) -28.61% -0.09% -28.7% TIME ELAPSED 98.68% 0.44% 99.12% NO. OF DAYS AHEAD/ DELAY 192 DAYS 1 DAY 193 DAYS
Accomplishment Report Park Residences PHASE 1 ACCOMPLISHMENT (REVISED SCHEDULE) LAND DEVELOPMENT WORKS ITEM TO DATE (AUG 20, 2022) THIS PERIOD (AUG 20-27, 2022) TO DATE (AUG 27, 2022) TARGET ACCOMPLISHMENT 99.72% 0.10% 99.82% ACTUAL ACCOMPLISHMENT 77.15% 0.03% 77.18% VARIANCE (%) -22.57% -0.07% -22.64% TIME ELAPSED 98.68% 0.44% 99.12% NO. OF DAYS AHEAD/ DELAY 152 DAYS 1 DAY 153 DAYS
Accomplishment Report Park Residences PHASE 2 ACCOMPLISHMENT (REVISED SCHEDULE) LAND DEVELOPMENT WORKS ITEM TO DATE (AUG 20, 2022) THIS PERIOD (AUG 20-27, 2022) TO DATE (AUG 27, 2022) TARGET ACCOMPLISHMENT 99.72% 0.10% 99.82% ACTUAL ACCOMPLISHMENT 63.24% VARIANCE (%) -36.48% TIME ELAPSED 98.68% 0.44% 99.12% NO. OF DAYS AHEAD/ DELAY 245 DAYS
BACK LOG TOTAL VOLUME (BACK LOG): 18.0 m 3 DESCRIPTION ESTIMATED VOLUME (m³) EQUIVALENT LINEAR METER DESIGN MIX DATE OF POURING PARKING AREA INFRONT OF BUILDING B 3 m³ 5 lm 3500 psi AUG 28, 2022 PARKING – NEAR BLDG. G 15 m³ 17 lm 3500 psi AUG 28, 2022 CONCRETE MONITORING (AS PER CONCRETE PAVEMENT SCHEDULE ) Park Residences
TRENCH CANAL Park Residences CONCRETE POURING OF BOTTOM SLAB AT TRENCH CANAL
PCCP Park Residences CONCRETE POURING OF ENCASEMENT FOR CURBS & GUTTER
BACK LOG TOTAL VOLUME (BACK LOG): 72.2m 3 DESCRIPTION ESTIMATED VOLUME (m³) EQUIVALENT LINEAR METER DESIGN MIX DATE OF POURING PARKING – NEAR BLDG. G AND POOL 31.2 m³ 31.2 lm 3500 psi DECEMBER 1, 2021 ROAD 1 - RIGHT LANE NEAR BLDG. G 38.5 m³ 55 lm 3500 psi DECEMBER 1, 2021 ROAD 1 LEFT LANE NEAR BLDG. G 2.50 m³ 3.56 lm 3500 psi AUG 23, 2022 CONCRETE MONITORING (AS PER CONCRETE PAVEMENT SCHEDULE ) Park Residences DESCRIPTION ESTIMATED VOLUME (m³) EQUIVALENT LINEAR METER DESIGN MIX DATE OF POURING PARKING – NEAR BLDG. G AND POOL 31.2 m³ 31.2 lm 3500 psi AUG 23, 2022 ROAD 1 - RIGHT LANE NEAR BLDG. G 38.5 m³ 55 lm 3500 psi AUG 23, 2022
PCCP Park Residences word ROAD PAVEMENT = 85.96 % PARKING = 49.66 % ACCOMPLISHMENT CONCRETE POURED (ROAD) CONCRETE POURED (PARKING) CONCRETE POURED (SIDEWALK AND CURBS & GUTTER)
TRENCH CANAL Park Residences TRENCH CANAL (1mx1m) TOTAL QUANTITY: 113 linear meter DONE: 93 linear meter ONGOING: 17 linear meter REMAINING: 3 linear meter TRENCH CANAL (1mx0.8m) TOTAL QUANTITY: 18.446 linear meter DONE: 7 linear meter ONGOING: NA REMAINING: 11.446 linear meter
TRENCH CANAL (1X1M) Park Residences DONE (93 LM) REMAINING (3 LM) ON GOING (17LM) ACTUAL ACCOMPLISHMENT: 82.30%
TRENCH CANAL (1X0.8LM) Park Residences DONE (7 LM) REMAINING (11.446) ON GOING (NA) ACTUAL ACCOMPLISHMENT: 61.15%
BOX CULVERT Park Residences BOX CULVERT (1mx1m) TOTAL QUANTITY: 27 LINEAR METER DONE: 27 LINEAR METER ONGOING: NA REMAINING: NA BOX CULVERT (1mx0.8m) TOTAL QUANTITY: 47.36 LINEAR METER DONE: 42.9 LINEAR METER ONGOING: NA REMAINING: 4.5 LINEAR METER
BOX CULVERT (1X0.8M) Park Residences DONE (42.9 LM) REMAINING (4.5 LM) ON GOING (NA) ACTUAL ACCOMPLISHMENT: 90.60 %
ENCASEMENT Park Residences CONCRETE POURING OF ENCASEMENT
CURBS & GUTTER Park Residences CONCRETE POURING OF CURBS AND GUTTER
MANPOWER LOADING Park Residences DIRECT WORKERS ENGINEER 5 OPERATOR 2 SAFETY OFFICER 1 DRIVER 1 TIMEKEEPER/DOCS CON 1 TOTAL 33 INDIRECT WORKERS FOREMAN 2 SKILLED/ADMIN 4 RUNNER 1 SAFETY CREW 1 LABOR 7 CARPENTER 2 SUBCON MATTIAS 4 ELECTRICIAN 2
ISSUES AND CONCERNS Park Residences ITEM NO. RFA/RFI No. Transmittal Sheet No. Item Description Date of Submittal AGING/REMARKS JASBUILT to ACMC ACMC to JASBUILT JASBUILT to ACMC Forwarded Received ITEM RFI/RFA NO. TRANS. NO. DESCRIPTION DATE OF SUBMITTAL AGING/ REMARKS 1.0 RFI-JSBLT-PARK-AR-012 480 PARKING FINISH MAY 17, 2022 15 DAYS 2.0 RFI-JSBLT-PARK-AR-013 482 DESIGN FINISH AROUND THE CLUBHOUSE JUNE 1, 2022 3.0 RFA-JSBLT-PARK-AR-015 291 SAMPLE BOARD FOR CLUBHOUSE FEBRUARY 24, 2022 99 DAYS