INSPECTION,
MAINTENANCE AND
REHABILITATION OF
BRIDGES
S.JASWANT KUMAR
JOINT DIRECTOR (V & E)
INSPECTION AND MAINTENANCE OF BRIDGES
MAINTENANCE
NEED TO MAINTAIN IN TRAFFIC WORTHY CONDITION
TO FACILITATE UNINTERRUPTED FLOW OF TRAFFIC
PERIODIC MAINTENANCE INSPECTION BY
RESPONSIBLE OFFICERS ARE NECESSARY TO TAKE
TIMELY REMEDIAL MEASURES
MAINTENANE OF RECORDS FOR BRIDGES
MAINTENANCE OF MANUAL FOR MAJOR BRIDGES
MAINTENANCE OF RECORDS
OF BRIDGES
A bridge register should be maintained
For each bridge there must be
Original bridge report
Inspection report.
Original bridge report shall be maintained on the basis of
completion drawings. In case of old bridges where
sufficient data is not available a responsible officer shall
inspect and compile the same.
ORIGINAL BRIDGE REPORT
Original bridge report should contain
Bridge number
Date of investigation
Name location
Description ( type of structure, foundations etc )
Skew, spans, total length and road way width
Design live load, water way, clearances
Railing, alignment, restrictions
Miscellaneous
Date of completion
Availability of as built drawings.
MAITENANCE MANUAL FOR
MAJOR BRIDGES
The Engineers who are associated in the
construction of the project should also prepare
detailed maintenance manual indicating the
critical points needing special attention
subsequently during its service period.
INSPECTION AND MAINTENANCE OF BRIDGES
INSPECTION
ROUTINE INSPECTION
PRINCIPAL INSPECTION
SPECIAL INSPECTION
Routine inspection
Will rely mainly on visual assessment. Purpose is to
determine fairly obvious deficiencies in the bridge
structure. The frequency shall be at least once a year
but preferably twice a year before and after monsoon.
Shall be carried out by competent engineers. Up to 30
m length-A.E.E
60 m length -Dy E.E
60-200 m -E.E
200m and above -S.E
500 m -C.E
INSPECTION
Principal Inspection
This is a more intensive and detailed inspection
involved in close examination of elements of structure to
determine the nature and degree of distress in every
component of a bridge.
The first principle inspection shall be before expiry of
defect liability period but not later than six months after
completion and opening to traffic
The frequency there after shall not be more than 3 years
by a senior level engineer with comprehensive check list.
INSPECTION
Special inspection
This shall be undertaken in the event of
unusual occurrences such as earth quakes,
accidents, passage of unusual roads or floods,
unusual settlement of foundations and
substantial change in traffic pattern etc.
May require a good deal of supplementary
testing and structural analysis which will
invariably require detailed involvement of design
organizations and experts in the relevant fields
INSPECTION PROCEDURE
The inspection should follow a
predetermined pattern to ensure that no
component is over looked.
TYPICAL PATTERN
FOUNDATIONS
ABUTMENTS
WINGS / RETURNS
PIER COLUMNS, BEARINGS
SOFFITS OF THE DECK INCLUDING BEAMS
DETAILS UNDER THE DECK
CONDITION OF ROAD SURFACE, DRAINAGE, PARAPETS
EXPANSION JOINTS
CONDITION OF APPROACHES
CONDITION OF PROTECTIVE WORKS
Wyra Bridge
Wyra Bridge
INSPECTION AND MAINTENANCE OF BRIDGES
MEANS OF ACCESS
BUILTINACCESS
•MANHOLE,BUILTINLADDERS,PERMANENT CATWALKS
SEMI–MOBILEACCESS
•ACCESS LADDERS, SEMI-STATIONARY INSPECTION
EQUIPMENT
MOBILEEQUIPMENT
•EQUIPMENTOPERATINGUNDERTHEBRIDGEFROMRIVER
BED/BARGES
•EQUIPMENTOPERATINGFROMBRIDGEDECK
•MOBILEINSPECTIONUNIT
AVERYVERSATILE EQUIPMENT FORSPEEDY
INSPECTIONOFLARGENUMBEROFBRIDGES.
Mobile Inspection Vehicle
Inspection from Mobile Inspection Unit
ASSESSMENT TECHNIQUE & EQUIPMENT
NON DESTRUCTIVE TESTS (NDT)
REBOUND AND PENETRATION TESTS
ULTRA SOUND AND PENETRATION TESTS
COVER METERS
RESISTIBILITY TESTS
HALF CELL POTENTIAL MEASUREMENT
GAMMA RADIOGRAPH
DESTRUCTIVE / PARTIALLY DESTRUCTIVE
TESTS
By taking concrete core samples drilled from
the structure using a coring machine
CARBONATION
MOISTURE CONTENT
PULL OUT STRENGTH
ASSESSMENT TECHNIQUE & EQUIPMENT
LABORATORY TESTS
COMPRESSIVE STRENGTH OF CONCRETE
CEMENT CONTENT AND AIR VOIDS IN CONCRETE
MODULUS OF ELASTICITY
SPLITTING TENSILE STRENGTH
TENSILE STRENGTH OF STEEL
SULPHATE CONTENT
PERMEABIITY TESTING
REPTOGRAPHIC EXAMINATION OF AGGREGATE TO CHECK
ALKALI AGGREGATE REACTION
ULTRASONIC METHODS :
ULTRASONIC PULSE VELOCITY (UPV) TEST…
a. On opposite faces
b. On adjacent faces
c. On same face
REPETITIVE VOLTAGE PULSES ARE GENERATED
ELECTRONICALLY ANDTRANSFORMED INTOWAVEBURSTS
OFMECHANICAL ENERGY BYTHE TRANSMITTING
TRANSDUCER, WHICHMUSTBECOUPLEDTOTHECONCRETE
SURFACE THROUGH ASUITABLEMEDIUM SUCH AS
PETROLEUMJELLY,LIQUIDSOAPORGREASE.
OPERATION :
ULTRASONIC PULSE VELOCITY (UPV) TEST…
ASIMILARRECEIVING TRANSDUCER ISALSO
COUPLED TOTHECONCRETE ATAKNOWN
DISTANCE FROM THE TRANSMITTER AND
MECHANICAL ENERGY CONVERTED BACKTO
ELECTRICALPULSESOFTHESAMEFREQUENCY.
THEELECTRONICTIMINGDEVICEMEASURES THE
INTERVALBETWEENTHEONSETANDRECEPTION
OFTHEPULSEANDTHISISDISPLAYEDEITHERON
ANOSCILLOSCOPE ORASADIGITALREADOUT.
ULTRASONIC PULSE VELOCITY (UPV) TEST…
OPERATION:
THEBASICPRINCIPLEISTHATTHEPRESENCE OF
STEELAFFECTSTHEFIELDOFANELECTROMAGNET .THIS
MAYTAKETHEFORMOFANIRON-COREDINDUCTOROFTHE
TYPESHOWNINFIGURE.
ANALTERNATINGCURRENTISPASSEDTHROUGH ONEOF
THECOILS,WHILSTTHECURRENTINDUCEDINTHEOTHER
ISAMPLIFIEDANDMEASURED,USUALLYBYAMOVING-COIL
METER.
COVER METER : THEORY
ELECTRO MAGNETIC METHODS…
AREFINEDVERSIONOFTHISTYPEOFEQUIPMENT,
INVOLVINGMORESOPHISTICATEDELECTRONICCIRCUITRY
ISAVAILABLEATPRESENTANDISCAPABLEOFINDICATING
BARDIAMETERANDALSODETECTINGBARSATAGREATER
DEPTH..
COVER METER : THEORY
ELECTRO MAGNETIC METHODS…
MOST COVER METERS CONSIST OFAUNIT
CONTAININGTHEPOWERSOURCE,AMPLIFIERANDDIGITAL
DISPLAYANDASEPARATESEARCHUNITCONTAININGTHE
ELECTROMAGNET WHICHISCOUPLEDTOTHEMAINUNITBY
ACABLE.
INUSE,THEREADINGINTHEDISPLAYUNITWILLBEZERO
ANDTHEHANDHELDSEARCHUNITMOVEDOVERTHE
SURFACEOFTHECONCRETEUNDERTEST.
COVER METER : PROCEDURE
ELECTRO MAGNETIC METHODS…
THEPRESENCE OFREINFORCEMENT WITHINTHE
WORKINGRANGEOFTHEEQUIPMENTWILLBEINDICATED
BYMAKINGABEEPSOUND.
THESEARCHUNITISTHENMOVEDANDROTATEDTO
OBTAINAMAXIMUM READINGANDTHISPOSITIONWILL
CORRESPOND TOTHELOCATIONOFABAR(MINIMUM
COVER).
COVER METER : PROCEDURE
ELECTRO MAGNETIC METHODS…
PRESENCEOFMORETHANONEREINFORCINGBAR.
LAPS,TRANSVERSE STEELASASECOND LAYEROR
CLOSELY-SPACEDBARS(LESSTHANTHREETIMESTHE
COVER)MAYCAUSEMISLEADINGRESULTS.
METALTIEWIRES,WHERETHESEAREPRESENTOR
SUSPECTED,READINGSSHOULDBETAKENATINTERVALS
ALONGTHELINEOFTHEREINFORCEMENT ANDAVERAGED.
COVER METER : LIMITATIONS
ELECTRO MAGNETIC METHODS…
THEMOSTRELIABLEAPPLICATIONOFTHISMETHOD
TOIN-SITUREINFORCEMENT LOCATION ANDCOVER
MEASUREMENT WILLBEFORLIGHTLYREINFORCED
MEMBERS.
ASTHE COMPLEXITY AND QUANTITY OF
REINFORCEMENT INCREASES,THEVALUEOFTHETEST
DECREASESCONSIDERABLY.
COVER METER : LIMITATIONS
ELECTRO MAGNETIC METHODS…
CHLORIDE PENETRATION TEST
CHLORIDEDETERMINATION TESTWILLBECARRIED
OUTONCONCRETE TOESTIMATETHELEVELOFCHLORIDES
INTHECONCRETE.
THEPRESENCEOFHIGHERAMOUNTOFCHLORIDESIN
CONCRETE SURROUNDING THEREINFORCEMENT WILL
RESULTINCORROSIONOFREBARS.
THEQUANTITYOFCHLORIDES INCONCRETE IS
DETERMINED GENERALLY BYCHEMICAL ANALYSISAND
EXPRESSED INTERMSOFPERCENTAGE OFCHLORIDESBY
WEIGHTOFCONCRETE.
* * * * *
INPSECTION REPORT AND FOLLOW UP ACTION
INSPECTION REPORT SHALL BE IN PRESCRIBED FORMAT
WITH SKETCHES OR PHOTOGRAPHS
RECOMMENDATIONS FOR STRENGTHENING AND
REPAIRS OF THE EFFECTED COMPONENTS
IF BRIDGE IS IN DISTRESS
LOAD ON BRIDGES SHALL BE RESTRICTED
BRIDGE CLOSED WHOSE RATED CAPACITY IS LOWER THAN
LEVEL OF TRAFFIC EXPECTED TO PLY
REPLACEMENT OR STRENGTHENING OF BRIDGE
MAINTENANCE OPERATION
Maintenance operations can be of ordinary
maintenance and specialized maintenance . The
important aspects to be kept in view are
Bridges in severe exposure condition
mainly in coastal regions are vulnerable to
corrosion. Hence any sign of distress,
cracks are to be observed twice a year.
In case of bridges in major alluvial rivers
deep scour may occur near piers even with
smaller discharges. Hence soundings
before, during and after floods are to be
taken at all foundations.
MAINTENANCE
MAINTENANCE OF SUBMERSIBLE BRIDGES
TRAFFIC ON THE BRIDGE TO BE SUSPENDED
IMMEDIATELY IF THE WATER REACHES SPECIFIED LEVEL
VENTS PROVIDEDIN SUPERSTRUCTUE TO BE CHECKED
SUPERSTRUCTURE TO BE CLEARED FREE OF DEBRIS
AFTER RECEDING OF FLOOD
GUIDE POSTS, SUPERSTRUCTURE TO BE EXAMINED FOR
DISTRESS
MISCELLANEOUS ITEMS
WEARING COAT
DRAINAGE SPOUT
FOOTPATHS
EXPANSION JOINTS
HAND RAILS
MAINTENANCE
Protective works
Most careful patrolling and watch is necessary
during each flood season especially the first
flood season to detect any weakness in
construction.
Engineer-in-charge should acquaint himself
with past history of the protective works and the
behavior of the river
It is advisable to have a reserve quantity of
stone which can be used in case of any
emergency for aprons, slope pitching etc.
REPAIR AND REHABILITATION
REHABILITATION OF BRIIDGES
The bridges are vital links in the highway
network and it for any reason the bridge goes
out of commission, the resultant disruption of
traffic effects the network. Hence it is well
recognized that bridges not only require
systematic maintenance but also strengthening
or rehabilitation during their service life.
APPROACH FOR
REHABILITATION
The best strategy can be only be determined in the light
of
Thorough investigation
Diagnosis of the causes of deterioration, faults and
weakness and
Assessment of the current condition of the bridge
Wherever possible root cause should be eliminated
before repairs are undertaken. Repair and strengthening
operations should be mechanically and chemically
compatible with the properties of the original or
surrounding material and basic structural concept.
REHABILITATION
Major causes of distress
•Single main cause of premature
deterioration of concrete bridges is
corrosion of steel . High humidity, porosity
of concrete, inadequacy of cover, cracks in
cover concrete, use of rusted steel
reinforcement without proper cleaning and
lack of proper grouting in cable ducts are
some of the factors which aggravate the
problem
CAUSES OF DISTRESS (contd)
Aggregate alkali reaction and alkali silica reaction
resulting in either in pop-outs or cracks in concrete
caused by expansion of reactive aggregate.
Leaching action and sulphate attack
Poor detailing, lack of strict quality control during
execution
Foundation movements due to scour, seismic activity
Manufacturing and damage to expansion joints
Excessive displacement of bearings
Lack of preventive routine maintenance
SIGNS OF DISTRESS
Cracking due to corrosion or map cracking.
Scaling which is local flaking or peeling off of
surface portion of concrete
Delaminations parallel to the concrete surface
at or near the level of reinforced steel indicating
corrosion and ultimate spalling of concrete
Leaching in the form of accumulation of white
salt or lime deposits on concrete surface
SIGNS OF DISTRESS (contd)
Deformation in the form of localized swelling or
expansion indicating compressive failure of
concrete or initial stages of spilling
Excessive deflection of super structure or
movement of bearings indicated by closing or
widening of expansion joints, tilting of
piers/abutments and well foundations.
Displacement of railings longitudinally and
transversely .
REPAIR
CRITERIA FOR SELECTION OF MATERIALS &
TECHNIQUES
CAUSE OF DISTRESSES, EFFICACY OF MATERIALS
AND IN PRESERVING / INCREASING THE LOAD
CARRYING CAPACITY OF THE STRUCTURE
AVAILABILITY OF MATERIAL / EQUIPMENT
IMPORTANCE OF THE BRIDGE
TIME AVAILABLE
LIFE EXPECTANCY
FEASIBILITY OF TRAFFIC DIVERSION
REPAIR
REPAIRS OF FOUNDATION
EROSION PROBLEMS
•STONE RIP RAP IS PLACED ON A MATTRESS AT (OR)
BENEATH BED LEVEL
PROBLEMSAGAINSTSCOUR
•SPURDYKES
•DEFLECTIONS TODIVERTWATERAWAYFROMPIERS
GARLANDING TECHNIQUE WITHSTONESAROUND PIER
FOUNDATIONS
•RCCCURTAINWALLS
•INCREASINGBEARINGCAPACITYBYINJECTINGCEMENT/
CHEMICALGROUT
REPAIR
REPAIRS TO MASONRY STRUCTURES
LOSS OF BOND FOR THE CORNER STONE
•LOWPRESSURECEMENTGROUTORAPOXYMORTAROR
PUSHINGSTONEBACKTOORIGINALPOSITIONBYFLAT
JACKS
LONGITUDINAL CRACKS ALONG DIRECTION OF
TRAFFIC
•RAKEMORTARJOINTSANDREFILLWITHCEMENTMORTAR
TRANSVERSE CRACKS
•INJECTIONOFCEMENT
STRENGTHENING OFARCHRING
•BYADDINGMATERIALTOTHEINTRUDESORTOTHE
EXTRUDES
REPAIR
REPAIRS TO CONCRETE BRIDGES
CLASSIFIED AS
REPAIR OF THE CONCRETE SURFACE
REPAIR OF CRACKS
REPAIR OF CORRODED STEEL REINFORCEMENT
REPAIR OF POROUS CONCRETE AND HOLES
REPAIR OF THE CONCRETE SURFACE
MECHANICAL METHODS
•MILLING, CHIPPING, SAND BLASTING, WATER OR STEAMS
HYDRAULIC METHODS
•WATER JETTING WITH 10 TO 40 MPA PRESSURE
REPAIR
REPLACEMENT OF SUBSTANDARD DEPTH OF CONCRETE
SLABS
REPLACEMENT OF CONCRETE SECTION IS NEEDED WHERE A
SMALLER SURFACE REPAIR IS NOT DESIRABLE
METHODS
SHORTCRETE
SUITABLE FOR REPAIR OF SURFACE DAMAGES,
CONCRETE REPLACEMENT AND FOR STRENGTHENING
OF STRUCTURAL ELEMENTS
•A DRY MIX PROCESS
•A WET MIX PROCESS
POLYMER MODIFIED CEMENT SYSTEM
RESINS
REPAIR
PROTECTION OF REINFORCING STEEL
FOR RUST REMOVAL
•SAND BLASTING,
•NEEDLE HAMMER
•WIRE BRUSHING
PROTECTION COAT WITH CEMENT MORTAR
CEMENT MORTAR WITH POLYMERS
REPAIR
STRENGTHENING OF CONCRETE STRUCTURE
REPLACING POOR QUALITY / DEFECTIVE MATERIAL
PROVIDING ADDITIONAL LOAD BEARING MATERIAL
•HIGH QUALITY CONCRETE, STEEL BARS, THIN PLATES
AND STRAPS, POST TENSIONING TENDONS
JOINT BETWEEN OLD AND NEW CONCRETE MUST BE
CAPABLE OF TRANSFORMING SHEAR STRESS WITHOUT
RELATIVE MOVEMENT
REINFORCEMENT STRENGTHENING
REPLACEMENT OF REINFORCEMENT SEVERELY DAMAGED
ADDITIONAL REINFORCEMENT PLACED
EPOXY BONDED STEEL PLATES
REPAIR
REPAIR TO
EXPANSION JOINTS
NOT EXPECTED TO LAST THROUGHOUT LIFE OF THE
BRIDGE
SEALANT FILLER SHALL BE REPLACED PERIODICALLY
REPLACEMENT OF CRACKED CONCRETE IN THE SONE OF
ANCHORING
BEARINGS
DEFECTS
•CORROSION
•DEFECTIVE SEAL IN NEOPRENE / POT BEARINGS
•PROKEN GUIDES
•CRACKED OR BROKEN ROLLER PLATES
•ACCUMULATION OF DUST / DEBRIS AT THE BEARING
JOINT
REPAIR
REPAIR TO
FOOTPATHS
REPLACEMENT OF DAMAGED / MSSIONG PRECAST
FOOTPATH SLABS
RAILINGS
REPAIR MEASURES ARE SAME AS ARE TO BE DONE FOR
MATERIAL WITH WHICH THEY ARE MADE
REPAIR
HYDRAULIC ASPECTS
ACTUAL DISCHARGE IN EXCESS OF THAT ASSUMED IN THE
DESIGN
INCREASE IN VELOCITY OF THE RIVER / STREAM FROM
THAT FOR WHICH IT WAS DESIGNED
INCREASE IN SCOUR DEPTH
DAMAGE TO THE PIERS OF THE BRIDGE DUE TO IMPACT OF
FLOATING DEBRIS
OBLIQUE FLOW OF THE STREAMS
THE CAUSES OF THESE OCCURANCES SHALL BE
ANALYSED AND SUITABLE REMEDIAL MEASURES TAKEN
MONITORING
AFTERTHEBRIDGESTRUCTURE ISREHABILITATED,
ITISESSENTIALTHATTHESAMEISKEPTUNDER
OBSERVATION ANDITSCONDITION MONITORED
REGULARLY.THEMONITORING METHODS MAY
INVOLVECARRYINGOUTCERTAINLABORATORY AND
FIELDTESTSASWELLASCONDITIONSURVEYSAND
MEASUREMENTS TODETECTEVENSMALLSTRAINS,
MOVEMENT ETC.MOREFREQUENT INSPECTION
DURINGREPAIRSANDATANINTERVALOF6MONTHS
THEREAFTERMAYBEREQUIRED.
Rehabilitation
of
Wyra Bridge
Sign
Board :“ BRIDGE UNDER MAJOR REPAIR, TAKE DIVERSION”
CHRONOLOGY
Commencement of Construction : 1992
of Bridge
Completion of Construction : December 1994
and Commissioning
Noticing of Cracks in girders : December 1995
for the first time
Closure of bridge for traffic : December 1997
**********
Salient features of
the Bridge
SALIENT FEATURES OF THE BRIDGE
Location : Across “Wyra Surplus” at 88 km, Suryapet
Aswaraopet Rd(near Khammam, A.P)
Bridge Structure: R.C. Deck with 3 girders resting on r.c.
piers supported on open foundation
Span : 10 spans each of 16.5 mtrs
[Simply supported spans]
Materials for : Fe-415 Rebars
Construction M20 Concrete for deck
M15 Concrete for piers
DESIGN DETAILS
Number of lanes: Two
Carriage Way : 7.5 m
Loading /Deck : One Lane Class70-R (Wheeled/Tracked)
or
Two Lanes of Class ‘A’ Vehicle
Reference : Std. plans for highway bridges-T Beam
bridges (Vol.III)MOST -1983. Dg. 29
IRC Specifications
CROSS SECTION OF DECK
LONGITUDINAL SECTION OF DECK
VIEW OF DECK BOTTOM
What happened
to the bridge?
DECEMBER 1997
Physical Observations/
Summary
SPANS -S6,S8 AND S9(SEVERE DISTRESS)
1. WIDE CRACKS -VERTICAL /HORIZONTAL
2.SPALLING OF CONCRETE
3.EXPOSURE OF REBARS
4.SAGGING OF SPANS (MAX. ABOUT 75mm)
5. CRUSHING OF CONCRETE AT SUPPORTS
(BY ABOUT 50 mm)
6.SEVERE PERCEIVABLE VIBRATIONS
7. POOR QUALITY CONCRETE
Why Concrete in lower region of Girders is Poor?
Is it because -
1. Defective cement is used.
2. Mix proportion is lean.
3. Quality of aggregates is poor .
4. Water-Cement ratio is high.
5. Curing is not adequate.
6. Form work is not slurry tight.
*******
Decision
Demolition Or
Restoration?
CLIENT :R & B Department, Govt. of A.P
CONSULTANT FOR :Torsteel Research Foundation
RESTORATION in India, Bangalore
INVESTIGATIION : March/April 1998
RESTORATION RepCon Consultancy
AGENCY :& Services, Hyderabad
PERIOD OF :October 1998 to
RESTORATION February 1999
RECOMMISSIONING : March 1999
OF BRIDGE
RESTORATION SCHEME DECIDED FOR
THE BRIDGE PROJECT
STAGE I : Replacement of poor concrete in
girders & diaphragms, by good
concrete.
STAGE II : Replacement of poor concrete in
bearing regions, by good
concrete.
RESTORATION SCHEME DECIDED FOR
THE BRIDGE PROJECT (Contd..)
STAGE III : Replacement of neoprene pads.
STAGE IV : Pressure grouting of girders &
diaphragms.
*****
RESTORATION MATERIALS
Several restoration materials have been developed
in the recent past,which ensure safe and durable
restorations. A few of them are -
Modified Mortars.
Epoxy Mortars.
Cementitious/Epoxy Grouts.
Membrane/Protective Coatings.
Glass Fiber / Carbon Fiber wrappings
Free Flow Micro Concrete.
(Super Fluid Micro Concrete)
Free Flow Micro Concrete is an ideal material for
encasement / Substitution systems
ESSENTIAL REQUIREMENTS OF REPAIR
MATERIALS IN CONCRETE STRUCTURES
•Effective adhesion with parent concrete.
•Development of positive grip with reinforcements .
•Fast gain in strength.
•High degree of impermeability.
•Durability under adverse atmospheric conditions.
Free Flow Micro Concrete satisfies by and large,
these essential requirements and is amenable for
encasement/Substitution techniques.
WHAT IS FREE FLOW MICRO CONCRETE ?
It is nothing but an appropriate synthesis of ‘free flow
grout’ & ‘dust free clean coarse agg.’
General Mix :
1.0 Free flow grout -0.5-coarse agg. by wt.
Expected slump -Collapse slump
Segregation -Nil
It is termed micro-concrete since 6mm agg. is used.
It is a potential restoration material.
CHARACTERISTICS OF FREE
FLOW GROUT
Form : Powder Type, Cementitious
Grain Size : 0 -3 mm in general
Unrestrained Expansion : About 2%
Flowability at max. : About 2000 mm in
consistency of 200 mm gap width of about 25 mm
Comp. Str. at 24 hrs : 250 Kg/Sq.cm min.
with max.consistency
FREE FLOW GROUTS
Grouts often used are -
•Sika grout -from M/s. Sika Qualcrete
•Conbextra GP -from M/s. Fosroc Chemicals
•Master grout CNS-from M/s. Choksey Chemicals
•Emcekrete -from M/s. Mc. Bauchemie
•Shrinkkomp -from M/s. Associated Cement
Company etc...
How does free flow micro
concrete look like?
Execution of Restoration
Scheme
(replacement of poor concrete
by free flow micro concrete)
RESTORATION DESIGN
RESTORATION DESIGN
RESTORATION DESIGN
FREE FLOW MICRO CONCRETE
TO BE POURED WITHOUT
COLD JOINT IN TWO STAGES
FREE FLOW MICRO CONCRETE
RESTORATION DESIGN
Execution of Restoration
Scheme
(restoration of bearing regions
& replacement of bearings)
LIFTING OF BRIDGE DECK FOR CONCRETE
REPLACEMENT AT BEARINGS
LIFTING OF BRIDGE DECK -INSERTION OF JACKS
LIFTING OF BRIDGE DECK -LIFTED DECK IN
POSITION
LIFTING OF BRIDGE DECK -ELEVATION AFTER
LIFTING
Execution of Restoration
Scheme
(pressure grouting of girders
& diaphragms)
Bridge Structure after
Restoration
Post -Restoration
Tests
LOAD / CONFIDENCE
TEST
LOAD / CONFIDENCE TEST DETAILS
Date of Test: 25
th
-28
th
January1999
Total u d l on Deck: 82 tonnes
considered for testing
Impact Factor : 20% of the above
Test load applied: 1.25 [1.2 x 82]
123 tonnes
Stone masonry wall around & 0.95 m depth of
water amounted to about 123 tonnes
RESULTS
Max. defln. under test load: 2.05 mm 1/8000 (span)
Crack width : Zero at 95% test load
< 0.1 mm at test load
Closure on load removal
CONFIDENCE TEST
CONFIDENCE TEST
Economics !
RESTORATION COSTING
Quantum of free flow micro
concrete utilised : 95 Cum
Quantum of addl. reinforcement : 10 tons
bars
Total Cost of Restoration : Rs. 35 lakhs
Cost of Super Structure : Rs. 85 lakhs
(As on 1997)
Recommissioning of
the Bridge
Recommissioning of Bridge
Present Status
Performing very well
Free from any distress