MECHANIC ACTIVITY REPORT
RABU, 24 APRIL 2024
PLANT DEPT SITE BORNEO BARA TIMUR MANDIRI
Created by: Daniel Kristanto
P5M DAY SHIFT I
Hari/Tanggal : Rabu, 24 April 2024
Lokasi : Workshop Area
PEMATERI :
1.DwiHeruWibowo(Toolkeeper)
-4 langkahkeselamatan
-kondisiarea kerjalicinpascahujan
2.Sugiyanto(SpvPlant)
-melakukanpekerjaandenganSOP yang ditetapkan
perusahaan
-bekerjasamaantardepartemendenganSOP yang benar
-team mechanic wajibmenerapkanhasiltraining BMC
demi meningkatkanefektifdan efisiendalambekerja
3.Rohadi(Fr FOG)
-penyampaianprosedurkerjasamadenganrekankerja
-komunikasiduaarahdalammelakukanpekerjaan
NB : kondisisite hujansejakawalshift
ACTIVITY REPAIR AND MAINTENANCE
Training BMC
Training BMC Modul 3 Batch 3
Herman
Prima Firdaus
ACTIVITY REPAIR AND MAINTENANCE
Periodic Service 500
DT030-026
Progres :
-Replace Oil Engine 40 Lt
-Replace Oil Filter 1 Pcs
-Replace Fuel Filter 1 Pcs
-Replace Waterseparator1 Pcs
-Cleaning Filter AC
-TigthenBolt sasis
-Check Air Radiator
TEMUAN
-Bushing ShockbreakerCabin RH+LH
Broken
-Wiper malfungsiStatus (Close)
-Rubber Front Spring LH Broken Status
(Open)
Start: 14:25
Finish: 15:22
Manpower : Lalu, Tarsudi, Wisnu, Ilham
ACTIVITY REPAIR AND MAINTENANCE
PeriodicService500
DT030-026
Progres :
-Check Water accu
-Check Head Accu
-Check All Slack Adjuster
-Check all Spring
-Check All Rubber Spring
-Repair Hose wiper
TEMUAN
-Bushing ShockbreakerCabin RH+LH
Broken
-Wiper malfunction Status (Close)
-Rubber Front Spring LH Broken Status
(Open)
Start: 14:25
Finish: 15:22
Manpower : Lalu, Tarsudi, Wisnu, Ilham
ACTIVITY REPAIR AND MAINTENANCE
PeriodicService500
DT030-026
Progres :
-Check Water accu
-Check Head Accu
-Check All Slack Adjuster
-Check all Spring
-Check All Rubber Spring
-Repair Hose wiper
TEMUAN
-Bushing ShockbreakerCabin RH+LH
Broken
-Wiper malfunction Status (Close)
-Rubber Front Spring LH Broken Status
(Open)
Start: 14:25
Finish: 15:22
Manpower : Lalu, Tarsudi, Wisnu, Ilham
ACTIVITY REPAIR AND MAINTENANCE
Periodic Service 500
TL006-012
Progres :
-Replace Oil Engine 4 Lt
-Replace Oil Filter 1 Pcs
-Replace Fuel Filter 1 Pcs
-Replace Air Cleaner New 1 Pcs
-Add Air Radiator 500 ML
-Check V-Belt Engine
-Check Worklamp
TEMUAN
-Lamp ONonly3pcs
-Tombolstart abnormal
Start: 16:35
Finish: 17:03
Manpower : Lalu, Tarsudi, Wisnu, Ilham
ACTIVITY REPAIR AND MAINTENANCE
Periodic Service 500
TL006-012
Progres :
-Replace Oil Engine 4 Lt
-Replace Oil Filter 1 Pcs
-Replace Fuel Filter 1 Pcs
-Replace Air Cleaner New 1 Pcs
-Add Air Radiator 500 ML
-Check V-Belt Engine
-Check Worklamp
TEMUAN
-Lamp ONonly3pcs
-Tombolstart abnormal
Start: 16:35
Finish: 17:03
Manpower : Lalu, Tarsudi, Wisnu, Ilham
NIGHT SHIFT
ACTIVITY REPAIR AND MAINTENANCE
P5M DAY SHIFT II
Hari/Tanggal : Rabu, 24 April 2024
Lokasi : Workshop Area
PEMATERI :
1.Heru Setiawan (Acting GL Plant)
•Selalukomunikasi2 arahagar pekerjaanlancardan
aman
•pembagianjob desc