Regional 2 – 2024 Production Outlook Minyak As of 5 Mei 2024 Analisa Performa Produksi Minyak ( Januari -April 2024) Performa Produksi Minyak Z Bulan RK Est LPO ( bbls ) Real LPO ( bbls ) Remark 6 Mar Riser replacement 12" ZELB outgoing ZELE 6,816 Plan Mei 6 Mar Repair SWGR 35kV KARA 2,274 987 Done 6 Apr Riser replacement 12" WIDE inc Aida 9,444 7,465 Done 5 May LIMA TAR 45,050 Plan June 2024 5 May KLA TAR 35,700 Plan June 2024 6 Apr Riser replacement 16" 3P WIDH outgoing WIDC 3,180 2,778 Done 6 Jun Riser Replacement 16” 3P Rama-B Incoming Gita-A 33,760 Plan July 2024 5 Jun Engine Change Out MMFK01BX 7,800 Z Bulan RK Est Gain ( bopd ) Real Gain ( bbls ) Remark 5 Feb Infill BL-10 525 Waiting test result. IP Unload 5 Mar Infill ED-15 250 IP 7 Apr BOR ABG-24 232 IP 7 Apr BOR CLU-INF2 276 230 Done 7 Apr BOR CLU-INF1 171 IP 7 Apr BOR BBS-022 213 IP Facility Unplanned S/D SubSurface / Existing Planned S/D Zona 5 Leak at subsea pipeline 8" 3phase FNB-FNA (-4,111 bbls ) Leak at 12" riser inc. ZUG-ZUJ1 (-16,033 bbls ) 8" 3Phase line BQA-BH subsea pipeline leaks (-2,067 bbls ) PF wells manually S/I for preparation permanent repair riser MOL PF-PC (2,270 bbls ) 8" 3-Phase FNB-FNA subsea pipeline leaks (-2,865 bbls ) Zona 6 Leaking Incoming Riser GITA at RAMB (-6,060 bbls ) Leaking 12” Incoming Riser AIDA at WIDE (-1,336 bbls ) Partial Outage CINP (-1,929 bbls ) Zona 7 JAS-26 VSD Problem (-693 bbls ) GTG Trip at Xray (-751 bbls ) Power, dist &trans (-4,321 bbls ), Gap runrate awal tahun : -3400 bopd (Z5 -700, Z6 -1100, Z7 -1600) Zona 5 Production YYA-1RWST below target (1000/150 bopd ) BM-7ST S/I due to found sand problem (-2,013 bbls ) FK-1ST found low performance (-300 bopd ) ZUA-1 & ZUG-13 S/I due to ESP problem (-350 bopd ) EH-1S S/I due to found blowing gas (-100 bopd ) Zona 6 Artificial lift Equipment @ OSES : -39,969 bbls . Zona 7 Decline production ABG, JAS, BBS wells Zona 5 Optimasi SIMOPS BL-10 (target 3,758 bbls , realisasi 3,215 bbls ) Optimasi SIMOPS BF-5ST (target 1,416 bbls , realisasi 559 bbls ) Optimasi SIMOPS ED (target 2894 bbls , real 1778 bbls ) Optimasi tie-in PRRP EPRO- Junc (+24,500 bbls ), FPRO-ECOM (+11,500 bbls ) Zona 6 Optimasi Riser replacement 12" WIDE inc Aida (target 9,444 bbls , real 7,465 bbls ) Optimasi Riser Replacement 16" Widuri -H Outgoing Widuri C (target 3,180 bbls , real 2,778 bbls ) Zona 7 Optimasi Perbaikan TOH SP Tambun (target 600 bbls , realisasi bbls ) BOR WO WI/ WS BOR: Target 13 sumur , Realisasi 6 sumur . LLD-22: 320/31 bopd ABG-023: 300/288 bopd BL-10: 525/- bopd , waiting test result (WC masih 100%) TGP-ST06: 320/- bopd , waiting test result (WC masih 100%) BF-5ST : 192/226 bopd CLU-INF2 : 276/230 bopd In progress : Bor CLU-INF1 , SBG-023, BBS-022, ABG-024 WO: Target 18 sumur , Realisasi 18 sumur . BBS-19: 67/66 bopd PDM-13: 37/0 bopd , low influx JTB-088: 0/0 bopd , pekerjaan ditunda krn CTU pindah sumur BBS-21: 69/28 bopd CMS-023: 75/- bopd , menunggu tes RDG-057 : 76/0 bopd GTR-001 : 61.6/- bopd CLU-008 : 79/0 bopd , KA 100% Zona 5 Target/ Realisasi : 68/59 smr ZUA-1 : 250/327 bopd YYA-1RWST : 0/145 bopd Zona 6 Target/ Realisasi : 36/56 smr NWAA-C3 : 215/416 bop WIDA-01 : 54/311 bopd KITA-04 : 70/647 bopd Zona 7 Target/ Realisasi : 66/58 smr JAS-33 : 30/165 bopd HGD-003 : 68/317 bopd Prognosa Major Losses (TW 2 2024) Prognosa Major RK Peningkatan Produksi (TW 2 2024) JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 56.9 55.5 53.6 54.4 55.3 55.1 58.2 60.6 59.7 60.9 61.6 60.9 Drilling WO WI/WS Existing Prognosa 2024 RKAP 2024 SIMOPS BL-10 - PRRP EPRO-Junction - PRRP FPRO-ECOM LIMA & KLA TAR Riser replacement 12" WIDE inc Aida Riser replacement 12“ : - WIDH inc outgoing WIDC - ZELB outgoing ZELE SIMOPS LLB Engine C/O & Stripping Down B1C-03-C-2A PRRP Pipa Terminal FSO AA Ph.2 Engine C/O MMF-K-01-BX SIMOP BF SIMOP ZUA TITA-16: sudah dikerjakan , menunggu surf fac (Jun 2024) TBN-060: 4/9 bopd JAS-002: 0 bopd ( sumur injeksi ) RDG-055: 0.9/ 0 bopd SIMOPS BF-5ST SIMOPS ED