engineering new product introduction weekly report


Slide Content

OPERATION MEETING NPI WW1122 ENGINEERING TEAM AMMAR & MARAN

CONTENTS TASK SUMMARY (PASS & CURRENT) TASK (PLAN FOR NEXT) COST SAVING

TASK TASK DESCRIPTION(ASM PROJEK) STATUS ( DONE/ IN-PROGRESS) 1 RF BAR/BRANCH(1024-401-1)- PROCESS DRAWING -JOB ROUTER DONE 2 BRKT-SP HEATER(1016-463-1)- PROCESS DRAWING -JOB ROUTER DONE 3 SENSOR JOB/SUS(1015-947-1)- PROCESS DRAWING -JOB ROUTER DONE 4 RF BAR /LOWER RC(1016-233-1)- PROCESS DRAWING -JOB ROUTER DONE 5 FIXER(1032-471-1)- PROCESS DRAWING -JOB ROUTER DONE TASK SUMMARY (PASS & CURRENT)

TASK DESCRIPTION ELABORATION RF BAR/BRANCH(1024-401-1) MATERIAL: A5052 4MM PROCESS 1.LASERCUT 2.BUFFING 3. IPQA BUYOFF 4. MACHINING COUNTERSUNK 5.IPQA BUYOFF 6. BENDING 7.IPQA BUYOFF 8. IQA BUYOFF 9.FINISHING:CHROMATE 10. IQA BUYOFF 11. WIP STORE PICTURE (If Available) TASK 1

TASK DESCRIPTION ELABORATION BRKT-SP HEATER(1016-463-1) MATERIAL: SUS304 1MM PROCESS 1.LASERCUT 2.BUFFING 3. IPQA BUYOFF 4. BENDING 5.IPQA BUYOFF 6.IQA BUYOFF 7. FINISHING: PICKLING AND PASSIVATE 8.IQA BUYOFF 9. WIP STORE PICTURE (If Available) TASK 2

TASK DESCRIPTION ELABORATION SENSOR JOB/SUS(1015-947-1) MATERIAL: SUS304 1.5MM PROCESS 1.LASERCUT 2.BUFFING 3.IPQA BUYOFF 4. BENDING 5.IPQA BUYOFF 6.IQA BUYOFF 7. FINISHING: PICKLING AND PASSIVATE 8.IQA BUYOFF 9. WIP STORE PICTURE (If Available) TASK 3

TASK DESCRIPTION ELABORATION RF BAR /LOWER RC(1016-233-1) MATERIAL: A5052 4.0MM PROCESS 1.LASERCUT 2.BUFFING 3.IPQA BUYOFF 4.IQA BUYOFF 5.FINISHING:CHROMATE 6. IQA BUYOFF 7. WIP STORE PICTURE (If Available) TASK 4

TASK DESCRIPTION ELABORATION FIXER(1032-471-1) MATERIAL: SUS304 5MM, 10.0MM PROCESS PART 1 1.LASERCUT 2.BUFFING 3.IPQA BUYOFF 4.BENDING 5. IPQA BUYOFF 6. WIP STORE PROCESS PART 2 1.LASERCUT 2.BUFFING 3.IPQA BUYOFF 4. WIP STORE ASSEMBLY 1.WELDING 2.BUFFING 3.IPQA BUYOFF 4.IQA BUYOFF 5. FINISHING: PICKLING AND PASSIVATE 6.IQA BUYOFF 7.WIP STORE PICTURE (If Available) TASK 5

TASK TASK DISCRIPTION TARGET DATE TO COMPLETE 1 BENCHMARK CARD CLAMP(EMP4260A80H03L-LF)- PROCESS DRAWING -JOB ROUTER 23/3/2022 2 ASM COVER-DUCT-A(1024-666-01)-PROCESS DRAWING -JOB ROUTER 22/3/2022 3 ASM STOPPER-DOOR(1036-074-01)-PROCESS DRAWING -JOB ROUTER 24/3/2022 4 ASM COVER-/RF-R(1023-557-01)-PROCESS DRAWING -JOB ROUTER 25/3/2022 5 ASM COVER-/RF-L(1023-558-01)-PROCESS DRAWING -JOB ROUTER 26/3/2022 6 7 TASK (PLAN FOR NEXT)

COST SAVING SLOT TAB Tab and slot - Reduce cost for fabricate jig to positioning and clamp the part - Reduce cycle time