Overview What is Outside Processing? A means of providing supplier-sourced components and processes as an integral part of the manufacturing process
Overview Outside processing (OSP) Consists of the use of inventory items and resources to model supplier-sourced services OSP resources are used to schedule and cost supplier-sourced services within manufacturing routings OSP allows for routing operation steps to be converted into purchase requisitions wherein the req line item is the OSP item WIP automatically requisitions material and purchase orders are charged directly to work orders Close loop, fully integrated solution
Overview OSP Features Multiple OSP operations on a work order and multiple OSP resources per operation Supplier provided components are included in BOM and referenced as supply type = supplier Automatic requisition generation Full tracability of work orders on purchase orders, receipts, & receiving transactions Automatic resource charging and move transactions Automatic work order completions
Overview: OSP Integration Oracle Purchasing Oracle Work in Process Oracle Inventory Oracle Bills of Material Oracle Outside Processing Oracle Mobile Supply Chain Oracle Cost Mgmt
Setup: Inventory Outside Processing Unit Type Assembly – OSP resource charges are based on the work order quantity Resource – OSP resource charges are based on the work order quantity x the resource run rate List Price Enter a list price
Setup: Resources Outside Processing Resource Charge type :- PO Move
Setup: Resources Standard Costing Considerations Type = Currency UOM = Dollars Average Costing Considerations Type = Amount UOM = Each Department Locations need to be setup
Setup: Routings Operation Resources Attached the resource to OSP department.
Setup: BOM Supply Type In Bill of Material supply type : Supplier
Setup: WIP Shop Floor Status Allow Moves = Unchecked
Setup: WIP WIP Parameters Attached shop floor status in WIP parameter. Shop floor status need to define in setup.
Setup: WIP WIP Parameters Shop Floor Status for PO Move Resources Determines which shop floor status is assigned to the Queue intra operation step of an outside processing operation when you create discrete jobs and repetitive schedules.
Setup: Cost Cost Rollup Once cost rollup completed we can see same resource in cost roll up report.
Execution: WIP Create and Release WIP Job
Execution: WIP Perform Move Operation Move material from operation 10, Queue, to operation 10, To Move Perform transaction save Remember, WIP Parameter Requisition Creation Time = @ Operation
Execution: WIP Perform Move Operation
Execution: WIP WIP Components In material requirement, material status (required, issued & open) perform as per the operation
Execution: WIP WIP Components : Supplier
Execution: Purchasing Perform Requisition Import
Execution: Purchasing Perform Requisition Import Select Import source as “WIP”
Execution: Purchasing Requisition Summary OSP item list price x work order assembly quantity If you charge an outside resource at standard, any variance between there source standard cost and the actual purchase price is written to the variance account associated with the outside resource.
Execution: Purchasing Requisition Summary Approved Status
Execution: Purchasing Auto Create Purchase Order & Approve
Execution: Purchasing Auto Create Purchase Order & Approve