Pert and cpm

ShashankKapoor16 1,409 views 29 slides Feb 24, 2018
Slide 1
Slide 1 of 29
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29

About This Presentation

Detail description of PERT and CPM from the point of algorithmist, Computer Science


Slide Content

PERT & CPM Submitted By:- Shashank kapoor Mechanical , 154169

What is the PERT & CPM ? It is nothing but the technique used in Network analysis of project management, such as planning , management and control of project. So, what is project ?? “ A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…..then work your plan

Project Evaluation & Review Techniques (PERT) In PERT is basically a method to analyze the tasks involved in completing a given project , especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. – Multiple time estimates – Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.

Critical Path Method ( CPM) In CPM activities are shown as a network of precedence relationships using activity-on-node network construction. – Single estimate of activity time – Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience .

KEY ELEMENTS Arrows:- leading from tail to head directionally Indicate Activity Nodes:- Indicate Event, a point in time where one or more activities start and/or finish. Earliest time: It is categorized in two sub elements. 1. Earliest Starting time (ES):- Time at which the activity can start 2. Earliest finishing time(EF):- Equals to the earliest start time for the activity plus the time required to complete the activity Latest time : It is categorized in two sub elements. 1.Latest Starting time (LS):- Time in which the activity can be completed without delaying 2.Latest Finishing time (LF):- equal to the latest finish time minus the time required to complete the activity. S lack time:- The difference between its earliest and latest start time. Critical Path:- The path of activities having zero Slack time.

KEY ELEMENTS Optimistic time (a): – It is the shortest time in which the activity can be completed. Most likely time ( m ) – It is the probable time required to perform the activity. Pessimistic time (b) – It is the longest estimated time required to perform an activity . Expected time ( Te ) – approximation time taken to complete an activity. T e Standard deviation (  ) – Higher the SD is the greater amount of uncertainty exists Variance ( Large variance indicates great uncertainty, a small variance indicates a more accurate estimate     

ILLUSTRATION ON PERT

SOLUTION Activity Optimistic Time (a) Most likely Time(m) Pessimistic Time (b) Expected Time ( Te ) Standard Deviation  1-2 1 1 7 2 1 1-3 1 4 7 4 1 1-4 2 2 8 3 1 2-5 1 1 1 1 3-5 2 5 14 6 2 4-6 2 5 8 5 1 5-6 3 6 15 7 2

SOLUTION

CRITICAL PATH Paths:- 1-2-5-6 = 2+1+7=10 1-3-5-6 = 4+6+7=17 1-4-6 = 3+5=8 1-3-5-6 is critical path since it take maximum time.

CRITICAL PATH NODE LC-ES TOTAL 1 0-0 2 9-2 7 3 4-4 4 12-3 9 5 10-10 6 17-17 On Analyzing the Node which having total =0 is 1-3-5-6 Hence it is critical path

PROBABILISTIC DETERMINATION What is the Probability of it taking 20 weeks? Critical Path = 1 -3-5-6 = 17 weeks T = 2 weeks C = 17 weeks   (Variance)   = 1   Look up Z value in normal distribution table P z = .8413 or 8 4 . 13 % Going over 20 weeks would be 100 – 84.13 = 15.87% (Probability of it taking 20 weeks)

ILLUSTRATION ON CPM

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

SOLUTION

CRITICAL PATH Paths:- 1-2-5-7-8=2+1+2+1=6 days 1-3-5-7-8=3+2+2+1=8 days 1-3-6-7-8=3+5+3+1=12days 1-4-6-7-8=4+7+3+1=15 days 1-4-6-7-8 is critical path since it take maximum time.

CRITICAL PATH NODE LC-ES TOTAL 1 0-0 2 11-2 9 3 6-3 3 4 4-4 5 12-5 7 6 11-11 7 14-14 8 15-15 On Analyzing the Node which having total =0 is 1-4-6-7-8 Hence it is critical path

What happen if we have large number of Network problem??

Conclusion For large number of network problem Ford F ulkerson Max Flow Algorithm is the point that can give us the optimal critical path since it is use for finding the maximum flow in a flow network for single source and single sink.

THANK YOU