Physical Unit Operation-�Screening, Grit Removal,�Equalization

11,975 views 49 slides May 23, 2016
Slide 1
Slide 1 of 49
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49

About This Presentation

screening
greet removal
in water and waste water engg.


Slide Content

TOPIC - Physical Unit Operation- Screening, Grit Removal, Equalization NAME ENROLL NO. PATEL JIMI 131100106029 PATEL MILIND 131100106035 PATEL VIRAJ 131100106040 PATEL YASH 131100106042 SHAH ASHIT 131100106051 GUIDED BY : Prof. MANALI Prof. UTTEJANA A. CHAUDHARY

Physical Unit Operations - Screening

Screening Screening is the first Unit Operation employed in wastewater treatment. Screening is necessary to retain floating matter and coarse solids as pieces of cloths garbage so as to protect pumps and other units from clogging. Thus retained material at screens is called as screenings . Screens may consist of vertical or inclined bars (bar racks or bar screens), wire mesh or perforated plates having either circular or rectangular openings.

Design Criteria for Bar Screens ( Bar Racks) Design Parameters Manually Cleaned Mechanically Cleaned 1. Velocity through Rack ( m/s) 0.3- 0.6 0.6- 1.0 2. Bar Size Width (mm) Depth (mm) 4-8 25-50 8-10 50-75 3. Spacing Between Bars (mm) 25-75 10-50 4. Slope from Horizontal Degrees 45-60 75-85 5. Allowable head loss in clogged condition mm 150 150

Head Loss through the bar rack is calculated from the following formulae. HL= = 0.0728 (V 2 - v 2 ) HL= H v . Sin θ ………………..(2) Where, H L = Head Loss through bar rack in meters V= Velocity through Rack, m/s v = Velocity in upstream of bar Rack, m/s G= Acceleration due to Gravity = 9.81 m/sec 2  

W= Maximum Cross Sectional Width of bars facing the wastewater flow, meters b = minimum clear bar spacing H v = Velocity head of wastewater flow approaching the bar in meters = Bar Shape factor Value of Bar Shape factor for Clean Bar Rack are Given Below Sharp Edge Rectangular Bar- 2.42 Rectangular with Semi circular faceing Upstream- 1.79 Rectangular with both ends Semi-circular – 1.67 Circular Bars – 1.83  

Characteristics Quantity & Composition of Screenings Quantity of Screenings depends upon the type of screen, weather, & Characteristics of wastewater. Narrow opening will collect more screenings & hot weather shall increase the use of water & Wastewater formation shall be more thereby increasing screenings.

Quantity of screenings may be 0.03 to 0.08 m 3 / ML with an average of around 0.05 m 3 /ML Screening contain approximately 80 % moisture and has a normal wt. density of 960 kg/ m 3 . Screening are odorous and attract flies.

Design of BAR Screens Following Information are Required for design: Peak Wet Weather flow. Peak Dry Weather flow. Hydraulic Design of Influent Conduit. Treatment Plant Design Criteria Specified by Bureau of Indian Standards or other Recognized agency. Equipment Manufacturers, their specifications for equipment. Velocity through bars Information on Existing facility if plant is to be expanded. Bar Spacing and head loss constrained through the rack & Through entire plant. Existing Site Plan with Contours. Velocities through Screen Chamber.

Design Example Design Bar Screen for a Peak flow of 50 MLD. Assume Other data, Maximum Rate of flow in m 3 /Sec = 50 x 10 6 x 10 -3 = 0.5787 m 3 /sec 24 x 60 x 60 Let Us Assume the velocity through the screen as 0.8 m/sec Net Area of Screen= 0.5787 0.8 = 0.7234 m 2

Let us use bars of 10 mm x 50 mm with 10 mm dimensions facing the flow, at a spacing of 40 mm between the bars. So, Gross Area = s + t Net Area s = Clear Spacing + Bar Thickness Clear Spacing Therefore, Gross area in our Case = Net Area x { Clear Spacing + Bar Thickness } Clear Spacing Gross Area = 0.7234 x 40 + 10 40 = 0.9043 Keep Screen at 45 Inclination with horizontal then Gross Area required = 0.9043 Sin 45 = 1.2788 m 2

Velocity in the approach Channel i.e. Slightly Upstream of Bar Rack = 0.8 x 40 50 = 0.64 m/sec Thus we have V= 0.8 m/sec v= 0.64 m/sec

Therefore, HL= = 0.0729 ( V 2 - v 2 ) = 0.0729 ( 0.8 2 – 0.64 2 ) = 0.017 m = 1.7 cm This will be the head-loss when the screen is clean If it is half Clogged.  

V= 2 x 0.8 = 1.6 m/sec & H L = 0.0729 ( 1.6 2 – 0.64 2 ) = 0.157 m = 15.7 cm So to reduce the head loss frequently cleaning of screen is required.

Physical Unit Operations - Grit Chamber

Grit Removal in Grit Chamber Sand, ash, Cinder, Bone Chip, egg shells, etc., of size less than 0.2 mm are included in grit. It is therefore possible to remove grit from the waste water easily by reducing the wastewater velocity in long channel called as grit channel. The velocity is reduced to about 0.3 m/sec. The settled grit is washed before its disposal.

Grit Chamber is provided for the purpose of removal of silt and sand particles mainly so that the same will not cause, the wear and tear of vanes of pumps, clogging of pipes, as well as, valve operation difficult. Cementing effects are also prevented in settling tanks and digester by removal of grit.

Grit Removal Unit may be a grit Channel, Grit Chamber or a Grit Basin. The Word grit chamber shall be used in subsequent discussion. There are two types of grit chambers Horizontal flow Grit Chambers Aerated Grit Chamber

Horizontal flow grit chamber are designed to maintain a velocity of around 0.3 m/sec . Such a velocity falls then the organic particles also settle down and if velocity becomes high grit particles will not settle. The Waste water flow varies and therefore it is required to maintain the constant velocity by providing proportional flow weirs, partial flumes and palmer- Bowlup flumes.

Aerated Grit Chambers are Used for Selective Removal of Grit in medium and large sized wastewater treatment plants.

Aerated Grit Chambers

Grit Collection & Removal Mechanical Grit Collection in velocity controlled horizontal flow grit chambers and aerated grit chambers is achieved by the conventional equipment In some cases steep bottom slope is provided which will collect the grit at Central Point of Removal.

Grit Removal is achieved by air pumps for small aerated grit chambers. Grit can also be removed by tubular conveyors, buckets type collectors, elevators screws conveyors, grit pumps and clam shell buckets.

Quantity of Grit Grit Quantity varies greatly. It depends upon the following factors: Type of Sewerage System i.e. Separate or Combined Sewerage System Climate Condition Soil Type Sewer Grades Type of Industrial Wastewaters Relative Use of Garbage and grinders The grit quantity may range from 5 to 200 m 3 / Million Cubic Meter of Wastewater. The typical Value can be Considered as 30 m 3 / million Cubic meter of wastewater.

Grit Disposal Various methods are Used for Grit Disposal Sanitary Landfill : In low lying areas or large natural pits the grit is disposed. Such a method of disposal is preferred when site of disposal is far away from city or town. Land Spreading Incineration with Sludge : Incineration is burning at very high temperature in excess Oxygen. City solid waste can be incinerated. Sludge and grit can be taken to the incinerator for burning. Grit can also be buried when its quantity is small.

Sanitary Landfill

Land Spreading

Incineration with Sludge

Design of Grit Chambers Following Information should be collected for designing of the grit chambers Wastewater Characteristics and Size of Grit particles to be removed. Design average, peak and lowest flow. Information about existing plant if it is to be expanded. Type of Grit Chamber to be provided i.e. Horizontal flow, aerated etc. Influent pipe data and static head force main and hydraulic grade line in case grit removal preceded pumping station. Head loss constraints for Grit Removal Efficiency. Treatment plant design criteria by Bureau of Indian Standards.

Design Criteria for Horizontal Flow Grit Chambers Detention Time = 40 to 60 Sec Horizontal flow velocity = 15 to 30 cm/sec approximately = 4 Where g= Acceleration due to Gravity= 9.81 m/sec 2 Ss= Sp Gravity of Grit = 2.65 D = dia of Grit in m.  

Surface Overflow Rate (SOR) = 500-1500 m 3 /m 2 /day Length to Breadth Ratio = 6 to 15 Length to depth Ratio = 10 to 30 Depth = (1.5 to 2) + free board Free Board = 0.75 to 1.0 m

Design Example Design a Suitable Grit Chamber to Cater a town of 2 Lakh population with 150 l/capita/day Sewage Contribution Assume Peak Factor = 1.5 Maximum Sewage Contribution per day = Average Contribution x Peak factor = 150 x 200000 x 1.5 litres = 150 x 200000 x 1.5 m 3 1000 = 45000 m 3

45000 m 3 sewage produced daily i.e. in 24 x 60 x 60= 86400 Seconds Therefore Maximum Sewage Discharge = 45000 m 3 / Sec 86400 = 0.52 m 3 /Sec Assume horizontal velocity 0.3 m/sec and detention time 50 sec Therefore Length of the tank Required = Velocity x Detention Time = 0.3 x 50 = 15 m

Now Settling Velocity of Grit Particles are governed by Hazen’s Modified Equation as Given Below: Vs= 60.6 (Ss-1) d (3t + 70) 100 Where, t= temp of Waste water C d= dia of particle in cm V s = Settling Velocity in cm/sec S s = Sp Gravity of Grit, 2.65 If Ss= 2.65 above equation becomes Vs= d (3t + 70) Taking, t= 27 C V s = 3 m/sec

We want to remove 0.2 mm particle so Settling Velocity = 3 cm/sec Therefore Depth of Tank= 3.0 cm/sec x 50 sec. 3 = 150 cm = 1.5 m Taking Length to Width Ratio as 10 : 1 Width of the tank = 1.5m

Now, Check for SOR Surface Overflow Rate Width= 1.5 m Length=15 m Plan Area= 1.5 x 15 = 22.5 m 2 Max Sewage flow = 45000 m 3 /day Max SOR = 45000 m 3 /day 22.5 = 2000 m 3 /m 2 /day Which is higher than permitted as per Criteria

So, take length: Width ratio as 6:1 Therefore Width= 2.5 m Therefore Plan Area= 2.5 x 15 = 37.5 m 2 Therefore Max SOR= 45000 m 3 / day 37.5 m 2 = 1200 m 3 /m 2 /day Which is less than 1500 therefore O.K .

Grit Chamber

Physical Unit Operations - Equalization Flow equalization is damping of flow rate variation so that a constant or nearly constant flow rate is achieved. This technique can be applied in a number of situation depending upon the characteristics of collecting system.

Types of Equalization In- line equalization In this case, all the flow passes through the equalization basin and helps in achieving reducing fluctuations in pollutant concentration and flow rate.

Off- line equalization In this case, only over-flow above a predetermined value is diverted into the basin . It helps in reducing the pumping requirements. Off-line equalization is commonly used for the capture of the “first flush” from combined collections systems.

Location of Equalization Basin In some cases Equalization may be provided after primary treatment & before biological treatment. The design must provide for sufficient mixing to prevent solid deposition & concentration variation. It is also necessary to provide aeration system to avoid odour nuissance .

Determination of the volume of flow equalization basin It is determined by using an inflow mass diagram in which cumulative inflow volume is plotted versus the time of day.

Data requirement Hourly flow data i.e. wastewater discharge during 0-1, 1-2, …, 23-24 hous of the day. Design criteria of the component agency of state. (BIS, GPCB) Location of equalization basin in the flow sheet. List of manufacturers of equipments like pumps, pipe etc… price etc… of equipment.

References W ater & Waste WaterEngineering By Prof B.R.Shah Prof A M Malek Google Images
Tags