Post tensioning company method statement | shivforce.in

sathishmhr 1,307 views 48 slides Oct 09, 2020
Slide 1
Slide 1 of 48
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48

About This Presentation

Shivforce is an expert in post tensioned and pre tensioned system contractors in chennai, TN, India. This PT slab Company helps its partners design and build more imaginative, efficient and durable post tensioned structures in chennai, Coimbatore,TN, India.

SF ENGINEERING SYSTEMS (INDIA) PVT LT...


Slide Content

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
1
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
PROJECT :
REVISION :
DATE :
Checked by : Approved by :
Mr. S. Durai Pandian
(Executive Director)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
1
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
PROJECT :
REVISION :
DATE :
Checked by : Approved by :
Mr. S. Durai Pandian
(Executive Director)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
1
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
PROJECT :
REVISION :
DATE :
Checked by : Approved by :
Mr. S. Durai Pandian
(Executive Director)

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
2
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
METHOD STATEMENT
CONTENTS
1 General 3
2 Scope of Work 3
3 References 3
4 Design data 4
5 Handling and storage of materials 4
6 General work procedure 5
7 Installation Procedure 5
8 Stressing Procedures 7
9 Grouting Procedure 12
Annexure 1 P.T Work Sequence-flowchart 16
Annexure 2 P.T Components and Equipments 21
Annexure 3 Checklist 28
Annexure 4 Admixture 32
Annexure 5 Safety 35
Annexure 6 Quality Assurance Policy (QAP) 39
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
2
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
METHOD STATEMENT
CONTENTS
1 General 3
2 Scope of Work 3
3 References 3
4 Design data 4
5 Handling and storage of materials 4
6 General work procedure 5
7 Installation Procedure 5
8 Stressing Procedures 7
9 Grouting Procedure 12
Annexure 1 P.T Work Sequence-flowchart 16
Annexure 2 P.T Components and Equipments 21
Annexure 3 Checklist 28
Annexure 4 Admixture 32
Annexure 5 Safety 35
Annexure 6 Quality Assurance Policy (QAP) 39
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
2
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
METHOD STATEMENT
CONTENTS
1 General 3
2 Scope of Work 3
3 References 3
4 Design data 4
5 Handling and storage of materials 4
6 General work procedure 5
7 Installation Procedure 5
8 Stressing Procedures 7
9 Grouting Procedure 12
Annexure 1 P.T Work Sequence-flowchart 16
Annexure 2 P.T Components and Equipments 21
Annexure 3 Checklist 28
Annexure 4 Admixture 32
Annexure 5 Safety 35
Annexure 6 Quality Assurance Policy (QAP) 39

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
3
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
1.General:
SF Post Tensioning Systems are developed and main tained by SF
Engineering Systems (India) Pvt Ltd.
Our systems comply with international specifications and recommendations
e.g.BS, EUROCODE, FIP, IS CODE, etc. The quality of SF products and
services is in full compliance with the above.
This method statement has been developed to provide a clear guidance for
all individuals involved in the project in using SF systems which covers the
installation, stressing and grouting activity.
2.Scope of work:
a)Supply of required Pre stressing components like anchoragehead, Wedge
Plates, Sheathing, Wedges and miscellaneous materials as per the
specification.
b)Assembling of tendon units in the Post Tensioning slab
according to the drawings provided.
c)Supplying necessary hydraulic jacks & stressingall the
tendons to therequired pressure
d)Supplying the grout pump & completegrouting all the tendons.
e)To verify the quality of Prestressing components delivered
to site & ensure that the entire process is done as per the
specification.
3.References:
Drawing no
Design Report
Prestressing notes and procedure.
Codal provision(IS 1343: 2012 , IS456 : 2000, BS 8110)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
3
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
1.General:
SF Post Tensioning Systems are developed and main tained by SF
Engineering Systems (India) Pvt Ltd.
Our systems comply with international specifications and recommendations
e.g.BS, EUROCODE, FIP, IS CODE, etc. The quality of SF products and
services is in full compliance with the above.
This method statement has been developed to provide a clear guidance for
all individuals involved in the project in using SF systems which covers the
installation, stressing and grouting activity.
2.Scope of work:
a)Supply of required Pre stressing components like anchoragehead, Wedge
Plates, Sheathing, Wedges and miscellaneous materials as per the
specification.
b)Assembling of tendon units in the Post Tensioning slab
according to the drawings provided.
c)Supplying necessary hydraulic jacks & stressingall the
tendons to therequired pressure
d)Supplying the grout pump & completegrouting all the tendons.
e)To verify the quality of Prestressing components delivered
to site & ensure that the entire process is done as per the
specification.
3.References:
Drawing no
Design Report
Prestressing notes and procedure.
Codal provision(IS 1343: 2012 , IS456 : 2000, BS 8110)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
3
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
1.General:
SF Post Tensioning Systems are developed and main tained by SF
Engineering Systems (India) Pvt Ltd.
Our systems comply with international specifications and recommendations
e.g.BS, EUROCODE, FIP, IS CODE, etc. The quality of SF products and
services is in full compliance with the above.
This method statement has been developed to provide a clear guidance for
all individuals involved in the project in using SF systems which covers the
installation, stressing and grouting activity.
2.Scope of work:
a)Supply of required Pre stressing components like anchoragehead, Wedge
Plates, Sheathing, Wedges and miscellaneous materials as per the
specification.
b)Assembling of tendon units in the Post Tensioning slab
according to the drawings provided.
c)Supplying necessary hydraulic jacks & stressingall the
tendons to therequired pressure
d)Supplying the grout pump & completegrouting all the tendons.
e)To verify the quality of Prestressing components delivered
to site & ensure that the entire process is done as per the
specification.
3.References:
Drawing no
Design Report
Prestressing notes and procedure.
Codal provision(IS 1343: 2012 , IS456 : 2000, BS 8110)

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
4
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
4.Design data:
Coefficient of Friction (µ) 0.2 (As per Consultant Requirement)
Wobble Factor (k) 0.0017 / m
Draw in wedge 6mm
Stressing Anchorage Flat Anchorage , Multi Anchorage
Loss in Jack 2% (Varies from 0–2)
5.Handling and storage of materials:
a)The pre-stressing strands shall be free of grease and corrosion enhancing
materials.
b)No flame cutting of strands is allowed.
c)Care should be taken in the handl ing of strands in order to avoid
mechanical damage to the strands.
d)Strands should be raised above ground to avoid contamination.
e)Webbing slings shall be used for loading and unloading in order to avoid
mechanical damage to the strand coils.
f)All Post Tensioning components must be handled and stored such that any
contamination,mechanical damage or corrosion can be avoided.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
4
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
4.Design data:
Coefficient of Friction (µ) 0.2 (As per Consultant Requirement)
Wobble Factor (k) 0.0017 / m
Draw in wedge 6mm
Stressing Anchorage Flat Anchorage , Multi Anchorage
Loss in Jack 2% (Varies from 0–2)
5.Handling and storage of materials:
a)The pre-stressing strands shall be free of grease and corrosion enhancing
materials.
b)No flame cutting of strands is allowed.
c)Care should be taken in the handl ing of strands in order to avoid
mechanical damage to the strands.
d)Strands should be raised above ground to avoid contamination.
e)Webbing slings shall be used for loading and unloading in order to avoid
mechanical damage to the strand coils.
f)All Post Tensioning components must be handled and stored such that any
contamination,mechanical damage or corrosion can be avoided.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
4
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
4.Design data:
Coefficient of Friction (µ) 0.2 (As per Consultant Requirement)
Wobble Factor (k) 0.0017 / m
Draw in wedge 6mm
Stressing Anchorage Flat Anchorage , Multi Anchorage
Loss in Jack 2% (Varies from 0–2)
5.Handling and storage of materials:
a)The pre-stressing strands shall be free of grease and corrosion enhancing
materials.
b)No flame cutting of strands is allowed.
c)Care should be taken in the handl ing of strands in order to avoid
mechanical damage to the strands.
d)Strands should be raised above ground to avoid contamination.
e)Webbing slings shall be used for loading and unloading in order to avoid
mechanical damage to the strand coils.
f)All Post Tensioning components must be handled and stored such that any
contamination,mechanical damage or corrosion can be avoided.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
5
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
6.General Work Procedures:
6.1Pre requisite for commencement of P.T Activity:
a)Shuttering work for the intended P.T slab to be casted
has to be made readyin all respect.
b)Bottom layer of the slab reinforcement& perimeter RCC
beam reinforcement has to be in place / fabricated in
accordance with the approved drawing.
c)Required numbers of pre fabricated bar chairs &
bursting links should be made available
6.2Preparation:
a)H.T Strand will be uncoiled using coil dispenser.
b)Ensure the straightness of the strand and cut the
strand as per the required length using disc Cutter /
cutting Wheel.
7.Installation Procedures:
For PT Slab Tendons:
Markthe anchorage position onto the reinforcement links / bottom
shutteringas per the approved tendon profile drawing.
Secure the anchorage head (pre assembled with recess former) either by
placing of horizontal support bars across the links (if required) or by tying
directly to the top reinforcement bars of perimeter RCC beam.
Lay the empty GI sheathing in one direction and joint them with the
couplers &connect the same with the anchorage head to form a tendon.
Care should be taken to avoid other trade laborers stepping on to the
empty sheathing laid / formed tendons.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
5
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
6.General Work Procedures:
6.1Pre requisite for commencement of P.T Activity:
a)Shuttering work for the intended P.T slab to be casted
has to be made readyin all respect.
b)Bottom layer of the slab reinforcement& perimeter RCC
beam reinforcement has to be in place / fabricated in
accordance with the approved drawing.
c)Required numbers of pre fabricated bar chairs &
bursting links should be made available
6.2Preparation:
a)H.T Strand will be uncoiled using coil dispenser.
b)Ensure the straightness of the strand and cut the
strand as per the required length using disc Cutter /
cutting Wheel.
7.Installation Procedures:
For PT Slab Tendons:
Markthe anchorage position onto the reinforcement links / bottom
shutteringas per the approved tendon profile drawing.
Secure the anchorage head (pre assembled with recess former) either by
placing of horizontal support bars across the links (if required) or by tying
directly to the top reinforcement bars of perimeter RCC beam.
Lay the empty GI sheathing in one direction and joint them with the
couplers &connect the same with the anchorage head to form a tendon.
Care should be taken to avoid other trade laborers stepping on to the
empty sheathing laid / formed tendons.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
5
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
6.General Work Procedures:
6.1Pre requisite for commencement of P.T Activity:
a)Shuttering work for the intended P.T slab to be casted
has to be made readyin all respect.
b)Bottom layer of the slab reinforcement& perimeter RCC
beam reinforcement has to be in place / fabricated in
accordance with the approved drawing.
c)Required numbers of pre fabricated bar chairs &
bursting links should be made available
6.2Preparation:
a)H.T Strand will be uncoiled using coil dispenser.
b)Ensure the straightness of the strand and cut the
strand as per the required length using disc Cutter /
cutting Wheel.
7.Installation Procedures:
For PT Slab Tendons:
Markthe anchorage position onto the reinforcement links / bottom
shutteringas per the approved tendon profile drawing.
Secure the anchorage head (pre assembled with recess former) either by
placing of horizontal support bars across the links (if required) or by tying
directly to the top reinforcement bars of perimeter RCC beam.
Lay the empty GI sheathing in one direction and joint them with the
couplers &connect the same with the anchorage head to form a tendon.
Care should be taken to avoid other trade laborers stepping on to the
empty sheathing laid / formed tendons.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
6
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Inserting in / threading of strands into the empty sheathing will be
commenced.
Ensure enough stressing length (400mm) of strand has been allowed to
protrude outside the perimeter RCCbeam.
Make bulb on to the other end of the strand to form as the dead end of
the tendon.
Mark the profile of the other direction tendons at the crossover points
either on the shuttering / upon the tendon already laid.
Lay the empty GI sheathing in other direction and joint them with the
couplers &connect the same with the anchorage head to form a tendon.
Ensure the layer of tendons as per the profile drawing isachieved on site.
Seal offall the coupler jointsof sheathing laidwith the help of OPP tape to
ensure the cement slurry shall notingresses through these joints.
As per the approved tendon profile drawing, elevate the assembled
tendons to the required height with the help of the bar chairs & secure
them with the binding wires.
Spread the bulb formed strands at the dead end to have 450mm in width
& tie them on to a horizontal barresting on the required profile bar chair.
Erect theside shuttering with holes for protruding strands & complete the
same to receive concrete.
For PT Beam Tendons:
Install bottom reinforcements,side reinforcements andshearlinks.But no
capping links shall be installed till the commencement of tendon
installation.
Install tendons in accordance with theshop drawings.
Install top reinforcements and capping links of the beam.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
6
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Inserting in / threading of strands into the empty sheathing will be
commenced.
Ensure enough stressing length (400mm) of strand has been allowed to
protrude outside the perimeter RCCbeam.
Make bulb on to the other end of the strand to form as the dead end of
the tendon.
Mark the profile of the other direction tendons at the crossover points
either on the shuttering / upon the tendon already laid.
Lay the empty GI sheathing in other direction and joint them with the
couplers &connect the same with the anchorage head to form a tendon.
Ensure the layer of tendons as per the profile drawing isachieved on site.
Seal offall the coupler jointsof sheathing laidwith the help of OPP tape to
ensure the cement slurry shall notingresses through these joints.
As per the approved tendon profile drawing, elevate the assembled
tendons to the required height with the help of the bar chairs & secure
them with the binding wires.
Spread the bulb formed strands at the dead end to have 450mm in width
& tie them on to a horizontal barresting on the required profile bar chair.
Erect theside shuttering with holes for protruding strands & complete the
same to receive concrete.
For PT Beam Tendons:
Install bottom reinforcements,side reinforcements andshearlinks.But no
capping links shall be installed till the commencement of tendon
installation.
Install tendons in accordance with theshop drawings.
Install top reinforcements and capping links of the beam.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
6
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Inserting in / threading of strands into the empty sheathing will be
commenced.
Ensure enough stressing length (400mm) of strand has been allowed to
protrude outside the perimeter RCCbeam.
Make bulb on to the other end of the strand to form as the dead end of
the tendon.
Mark the profile of the other direction tendons at the crossover points
either on the shuttering / upon the tendon already laid.
Lay the empty GI sheathing in other direction and joint them with the
couplers &connect the same with the anchorage head to form a tendon.
Ensure the layer of tendons as per the profile drawing isachieved on site.
Seal offall the coupler jointsof sheathing laidwith the help of OPP tape to
ensure the cement slurry shall notingresses through these joints.
As per the approved tendon profile drawing, elevate the assembled
tendons to the required height with the help of the bar chairs & secure
them with the binding wires.
Spread the bulb formed strands at the dead end to have 450mm in width
& tie them on to a horizontal barresting on the required profile bar chair.
Erect theside shuttering with holes for protruding strands & complete the
same to receive concrete.
For PT Beam Tendons:
Install bottom reinforcements,side reinforcements andshearlinks.But no
capping links shall be installed till the commencement of tendon
installation.
Install tendons in accordance with theshop drawings.
Install top reinforcements and capping links of the beam.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
7
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
7.1Tolerance:
Vertical Tendon Profile ± 5mm (For High and Low Points)
Horizontal Tendon Profile ± 150mm (To avoid M& E openings)
Note:
Designer shall be consulted for tolerance more than ± 150mm.
7.2Points to be taken care while Concreting:
Careshould be taken to ensure that the sheathing does not get
damaged during concreting.
All the strands projecting outside the slab willbe covered with an
empty short sheathing to protect it from the spilled concrete falling on
to it.
Ensure the minimum gra de of concrete for Post–Tensioning work
should be M–35.
8.Stressing Procedures:
Stressing shall not commence unless the main contractor has confirmed the
member has achieved its minimum cube strength at transfer stage.
Compressive strength required for commencing the stressing activity shall be
minimum27N/mm
2
for M–35 grade of concrete(75 % of fckis required).
8.1Preparation of Stressing:
Immediately after the removal of side shuttering, the recess former
shall be removed.
The strands projecting outside the anchorages willbe cleaned and the
anchor block along with the wedges shall be slotted on to them.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
7
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
7.1Tolerance:
Vertical Tendon Profile ± 5mm (For High and Low Points)
Horizontal Tendon Profile ± 150mm (To avoid M& E openings)
Note:
Designer shall be consulted for tolerance more than ± 150mm.
7.2Points to be taken care while Concreting:
Careshould be taken to ensure that the sheathing does not get
damaged during concreting.
All the strands projecting outside the slab willbe covered with an
empty short sheathing to protect it from the spilled concrete falling on
to it.
Ensure the minimum gra de of concrete for Post–Tensioning work
should be M–35.
8.Stressing Procedures:
Stressing shall not commence unless the main contractor has confirmed the
member has achieved its minimum cube strength at transfer stage.
Compressive strength required for commencing the stressing activity shall be
minimum27N/mm
2
for M–35 grade of concrete(75 % of fckis required).
8.1Preparation of Stressing:
Immediately after the removal of side shuttering, the recess former
shall be removed.
The strands projecting outside the anchorages willbe cleaned and the
anchor block along with the wedges shall be slotted on to them.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
7
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
7.1Tolerance:
Vertical Tendon Profile ± 5mm (For High and Low Points)
Horizontal Tendon Profile ± 150mm (To avoid M& E openings)
Note:
Designer shall be consulted for tolerance more than ± 150mm.
7.2Points to be taken care while Concreting:
Careshould be taken to ensure that the sheathing does not get
damaged during concreting.
All the strands projecting outside the slab willbe covered with an
empty short sheathing to protect it from the spilled concrete falling on
to it.
Ensure the minimum gra de of concrete for Post–Tensioning work
should be M–35.
8.Stressing Procedures:
Stressing shall not commence unless the main contractor has confirmed the
member has achieved its minimum cube strength at transfer stage.
Compressive strength required for commencing the stressing activity shall be
minimum27N/mm
2
for M–35 grade of concrete(75 % of fckis required).
8.1Preparation of Stressing:
Immediately after the removal of side shuttering, the recess former
shall be removed.
The strands projecting outside the anchorages willbe cleaned and the
anchor block along with the wedges shall be slotted on to them.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
8
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Wedges shallbe mildly rammedwith a steel pipe to ensurefortheir
even seating.
8.2Pre requisite for Stressing:
Jacks used for stressing shouldbe supplied with necessary calibration
certificate.
All stressing equipments willbe cleaned and checked before put into
operation.
Theoretical elongation calculation shall be prepared and put forwarded
to the consultants review & kept ready.
Compressive strength of concrete should be confirmed to have
achieved27N/mm
2
8.3Sequence of Stressing:
For Flat Anchorage (FA) System
Each strand in the tendon shall be stressed to 25% of the jacking force
and the datum shall be marked.
The stressing jack has to be inserted back to its position and each
strand has to be stressed for its final pressure.
The elongation for each strand will be checked by measuring the mark
datum.
Measure the distance of the datum mark to the wedge plate. This will
reflect the strand’s elongation from 25% to 100% force. ( assume X
mm )
Add the wedge draw-in of 6mm to the X.
Effective strand’s elongation from 25% to 100% stressing force, Y
Y = X + 6mm (Wedge Draw in)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
8
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Wedges shallbe mildly rammedwith a steel pipe to ensurefortheir
even seating.
8.2Pre requisite for Stressing:
Jacks used for stressing shouldbe supplied with necessary calibration
certificate.
All stressing equipments willbe cleaned and checked before put into
operation.
Theoretical elongation calculation shall be prepared and put forwarded
to the consultants review & kept ready.
Compressive strength of concrete should be confirmed to have
achieved27N/mm
2
8.3Sequence of Stressing:
For Flat Anchorage (FA) System
Each strand in the tendon shall be stressed to 25% of the jacking force
and the datum shall be marked.
The stressing jack has to be inserted back to its position and each
strand has to be stressed for its final pressure.
The elongation for each strand will be checked by measuring the mark
datum.
Measure the distance of the datum mark to the wedge plate. This will
reflect the strand’s elongation from 25% to 100% force. ( assume X
mm )
Add the wedge draw-in of 6mm to the X.
Effective strand’s elongation from 25% to 100% stressing force, Y
Y = X + 6mm (Wedge Draw in)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
8
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Wedges shallbe mildly rammedwith a steel pipe to ensurefortheir
even seating.
8.2Pre requisite for Stressing:
Jacks used for stressing shouldbe supplied with necessary calibration
certificate.
All stressing equipments willbe cleaned and checked before put into
operation.
Theoretical elongation calculation shall be prepared and put forwarded
to the consultants review & kept ready.
Compressive strength of concrete should be confirmed to have
achieved27N/mm
2
8.3Sequence of Stressing:
For Flat Anchorage (FA) System
Each strand in the tendon shall be stressed to 25% of the jacking force
and the datum shall be marked.
The stressing jack has to be inserted back to its position and each
strand has to be stressed for its final pressure.
The elongation for each strand will be checked by measuring the mark
datum.
Measure the distance of the datum mark to the wedge plate. This will
reflect the strand’s elongation from 25% to 100% force. ( assume X
mm )
Add the wedge draw-in of 6mm to the X.
Effective strand’s elongation from 25% to 100% stressing force, Y
Y = X + 6mm (Wedge Draw in)

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
9
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
The total elongation (from 0% to 100% force) shall be calcu lated by
extrapolation of the value Y.
Total elongation = (Y / 75) X 100
The value will be recorded & documented duly signed by P.T Engineer
/ Clients / Consultants.
Strands willbe cut after 24 hrs from completion of stressing activity.
Strand protruding beyond the wedge will be cut 2 times the diameter
of the strand or 25mm away from wedge face using cutting wheel.
ForMultiplane Anchorage(MA) System
The multistrand jack shall be secured and hoisted to the anchorage’s
level by chain blocks or crane.
All strands shall be inserted through the jack’s guide pipes.
Connect jack to hydraulic pump.
At the beginning of stressing the strands are locked in the jack pulling
head.
The pressure readings and the measured elongation are recorded in
the stressing report.
Stress initially to10Mpato remove slack in the strands.
Proceed stressing and record the strands’ elongation for every
incremental of 10MPa pressure.
When the jack has reached the end of its stroke or the desired force
has been obtained, the pressure in the jack is released and the strands
will locked uniformly by the wedges in the wedge plate.
The jack piston returns.
Stressing is continued in as many stages as are necessary to obtain
the required forces.
Note:De-Shuttering at pour strip area can be carried out after completion of
concreting in that area and after achievement of required compressive strength.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
9
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
The total elongation (from 0% to 100% force) shall be calcu lated by
extrapolation of the value Y.
Total elongation = (Y / 75) X 100
The value will be recorded & documented duly signed by P.T Engineer
/ Clients / Consultants.
Strands willbe cut after 24 hrs from completion of stressing activity.
Strand protruding beyond the wedge will be cut 2 times the diameter
of the strand or 25mm away from wedge face using cutting wheel.
ForMultiplane Anchorage(MA) System
The multistrand jack shall be secured and hoisted to the anchorage’s
level by chain blocks or crane.
All strands shall be inserted through the jack’s guide pipes.
Connect jack to hydraulic pump.
At the beginning of stressing the strands are locked in the jack pulling
head.
The pressure readings and the measured elongation are recorded in
the stressing report.
Stress initially to10Mpato remove slack in the strands.
Proceed stressing and record the strands’ elongation for every
incremental of 10MPa pressure.
When the jack has reached the end of its stroke or the desired force
has been obtained, the pressure in the jack is released and the strands
will locked uniformly by the wedges in the wedge plate.
The jack piston returns.
Stressing is continued in as many stages as are necessary to obtain
the required forces.
Note:De-Shuttering at pour strip area can be carried out after completion of
concreting in that area and after achievement of required compressive strength.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
9
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
The total elongation (from 0% to 100% force) shall be calcu lated by
extrapolation of the value Y.
Total elongation = (Y / 75) X 100
The value will be recorded & documented duly signed by P.T Engineer
/ Clients / Consultants.
Strands willbe cut after 24 hrs from completion of stressing activity.
Strand protruding beyond the wedge will be cut 2 times the diameter
of the strand or 25mm away from wedge face using cutting wheel.
ForMultiplane Anchorage(MA) System
The multistrand jack shall be secured and hoisted to the anchorage’s
level by chain blocks or crane.
All strands shall be inserted through the jack’s guide pipes.
Connect jack to hydraulic pump.
At the beginning of stressing the strands are locked in the jack pulling
head.
The pressure readings and the measured elongation are recorded in
the stressing report.
Stress initially to10Mpato remove slack in the strands.
Proceed stressing and record the strands’ elongation for every
incremental of 10MPa pressure.
When the jack has reached the end of its stroke or the desired force
has been obtained, the pressure in the jack is released and the strands
will locked uniformly by the wedges in the wedge plate.
The jack piston returns.
Stressing is continued in as many stages as are necessary to obtain
the required forces.
Note:De-Shuttering at pour strip area can be carried out after completion of
concreting in that area and after achievement of required compressive strength.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
10
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SAMPLE JACKING FORCE CALCULATION
UTS of Strand=183.7KN(for 0.5” Strand)
260.7KN(for 0.6” Strand)
Jack Loss= 2%
= 1+ 2=1.02
100
Applying force= 75%of UTS
Ram Area of SF T-25 Jack = 3300 mm
2
(or) 33cm
2
Formula
Jacking force=PressureX Jack Loss
Area
(Nos of StrandsXUTSX75%XJack Loss)/JackRam Area
Jacking force= (1x183.7x 100) x 75% x 1.02=425.85 Kg/cm
2
(For 0.5” Strand) 33
Jacking force =(1x260.7 x 100) x 75% x 1.02=604.35Kg/cm
2
(For 0.6” Strand) 33
Note:
TheJacking forcevalue may change depending upon the type ofHydraulic Jack and
its Ram Areaused at site.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
10
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SAMPLE JACKING FORCE CALCULATION
UTS of Strand=183.7KN(for 0.5” Strand)
260.7KN(for 0.6” Strand)
Jack Loss= 2%
= 1+ 2=1.02
100
Applying force= 75%of UTS
Ram Area of SF T-25 Jack = 3300 mm
2
(or) 33cm
2
Formula
Jacking force=PressureX Jack Loss
Area
(Nos of StrandsXUTSX75%XJack Loss)/JackRam Area
Jacking force= (1x183.7x 100) x 75% x 1.02=425.85 Kg/cm
2
(For 0.5” Strand) 33
Jacking force =(1x260.7 x 100) x 75% x 1.02=604.35Kg/cm
2
(For 0.6” Strand) 33
Note:
TheJacking forcevalue may change depending upon the type ofHydraulic Jack and
its Ram Areaused at site.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
10
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SAMPLE JACKING FORCE CALCULATION
UTS of Strand=183.7KN(for 0.5” Strand)
260.7KN(for 0.6” Strand)
Jack Loss= 2%
= 1+ 2=1.02
100
Applying force= 75%of UTS
Ram Area of SF T-25 Jack = 3300 mm
2
(or) 33cm
2
Formula
Jacking force=PressureX Jack Loss
Area
(Nos of StrandsXUTSX75%XJack Loss)/JackRam Area
Jacking force= (1x183.7x 100) x 75% x 1.02=425.85 Kg/cm
2
(For 0.5” Strand) 33
Jacking force =(1x260.7 x 100) x 75% x 1.02=604.35Kg/cm
2
(For 0.6” Strand) 33
Note:
TheJacking forcevalue may change depending upon the type ofHydraulic Jack and
its Ram Areaused at site.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
11
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
INTERPRETATION OF STRESSING RESULTS
Note:
(P)The Engineer shall be informed andconsulted for more investigation and design
check
Check Elongation (X) for
individual Tendon
Within±
8%
ok
Average deviation
per pour/over beam
section within±8%
ok
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
11
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
INTERPRETATION OF STRESSING RESULTS
Note:
(P)The Engineer shall be informed andconsulted for more investigation and design
check
Check Elongation (X) for
individual Tendon
Not Within
±8%
X<-8%
Average deviation
per pour/over beam
section within±8%
Average deviation
per pour/over beam
section < 8%
stress the tendon with X<-8%
to max of 80% UTS
Average deviation per
pour/over beam
section within±8%
ok
Average deviation per
pour/over beam
section< 8%
See (P)
Average deviation
per pour/ over
beam section
within±8%
ok
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
11
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
INTERPRETATION OF STRESSING RESULTS
Note:
(P)The Engineer shall be informed andconsulted for more investigation and design
check
Average deviation per
pour/over beam
section< 8%
X> +8%
Average deviation
per pour/ over
beam section
within±8%
ok
Average
deviation per
pour/over beam
section > 8%
Hold the
final
pressure for
15 sec

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
12
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
9.GroutingProcedures:
After the stressing and trimming of strands are completed, sealingof
tendons recesses will be doneusing cement mortar as per specifications.
Water will be potable,free from impurities and cement(OPC–53 grade)
willbe used andthe same should befreefrom anylumps.
Water and cement will be mixed as per the details given in the Codal
specification using mixer andagitate the mix continuously.
TheW/cratio will be kept as 0.45 and mixing time of grout willbe 2–3
minutes and approved non-aluminum based expanding agent may be
added as per Codal specifications.
Grout in the collection drum willbe kept in continuous slow agitation by
meansof agitator until pumped into the duct.
Grout will be pumped into the duct by inlet.
Start filling the duct with the specified grout mix, consistency ofthe grout
hasto be checked from the other end grout vent, and if it reaches the
same, close both the vent. Build the grout pressure from 3 to 5kg/cm2
and maintain the pressure for 15-20 seconds and seal the other end by
tying with binding wire.
The inlet will be closed and pressure willbe released from grout pump by
releasing thereturn valve in the groutpump.
Same procedure willbe adopted for remaining cables.
During grouting workers will wear protective goggles, helmets, and hand
gloves.
All the data willbe recorded in the format.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
12
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
9.GroutingProcedures:
After the stressing and trimming of strands are completed, sealingof
tendons recesses will be doneusing cement mortar as per specifications.
Water will be potable,free from impurities and cement(OPC–53 grade)
willbe used andthe same should befreefrom anylumps.
Water and cement will be mixed as per the details given in the Codal
specification using mixer andagitate the mix continuously.
TheW/cratio will be kept as 0.45 and mixing time of grout willbe 2–3
minutes and approved non-aluminum based expanding agent may be
added as per Codal specifications.
Grout in the collection drum willbe kept in continuous slow agitation by
meansof agitator until pumped into the duct.
Grout will be pumped into the duct by inlet.
Start filling the duct with the specified grout mix, consistency ofthe grout
hasto be checked from the other end grout vent, and if it reaches the
same, close both the vent. Build the grout pressure from 3 to 5kg/cm2
and maintain the pressure for 15-20 seconds and seal the other end by
tying with binding wire.
The inlet will be closed and pressure willbe released from grout pump by
releasing thereturn valve in the groutpump.
Same procedure willbe adopted for remaining cables.
During grouting workers will wear protective goggles, helmets, and hand
gloves.
All the data willbe recorded in the format.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
12
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
9.GroutingProcedures:
After the stressing and trimming of strands are completed, sealingof
tendons recesses will be doneusing cement mortar as per specifications.
Water will be potable,free from impurities and cement(OPC–53 grade)
willbe used andthe same should befreefrom anylumps.
Water and cement will be mixed as per the details given in the Codal
specification using mixer andagitate the mix continuously.
TheW/cratio will be kept as 0.45 and mixing time of grout willbe 2–3
minutes and approved non-aluminum based expanding agent may be
added as per Codal specifications.
Grout in the collection drum willbe kept in continuous slow agitation by
meansof agitator until pumped into the duct.
Grout will be pumped into the duct by inlet.
Start filling the duct with the specified grout mix, consistency ofthe grout
hasto be checked from the other end grout vent, and if it reaches the
same, close both the vent. Build the grout pressure from 3 to 5kg/cm2
and maintain the pressure for 15-20 seconds and seal the other end by
tying with binding wire.
The inlet will be closed and pressure willbe released from grout pump by
releasing thereturn valve in the groutpump.
Same procedure willbe adopted for remaining cables.
During grouting workers will wear protective goggles, helmets, and hand
gloves.
All the data willbe recorded in the format.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
13
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GROUT MIX
Cement = Ordinary Portland Cement (53 –grade) 50 Kg
Water = 0.45 x 50Kg (Per bag of cement) = 22.5 litres
Per Batch = 3 bags of cement
Admixture = Conplast P 211M (Fosroc)0.2% weight of cement (50Kg)
Cebex 100(Fosroc) 225g per bag of cement (50Kg)
Mixing Sequence = Water–Cement–Admixture
Mixing Time =2–3min
a)For Conplast P 211 M:(Refer Annexure –4)
CementRequired= 3 bags(150 Kg)
Water Required for 3 bags of cement =68 litres
Admixture Required for 3 bags of cement =300ml
b)For Cebex 100:(Refer Annexure –4)
Cement Required = 3 bags(150 Kg)
Water Required for 3 bags of cement =68 litres
Admixture Required for 3 bags of cement =675g
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
13
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GROUT MIX
Cement = Ordinary Portland Cement (53 –grade) 50 Kg
Water = 0.45 x 50Kg (Per bag of cement) = 22.5 litres
Per Batch = 3 bags of cement
Admixture = Conplast P 211M (Fosroc)0.2% weight of cement (50Kg)
Cebex 100(Fosroc) 225g per bag of cement (50Kg)
Mixing Sequence = Water–Cement–Admixture
Mixing Time =2–3min
a)For Conplast P 211 M:(Refer Annexure –4)
CementRequired= 3 bags(150 Kg)
Water Required for 3 bags of cement =68 litres
Admixture Required for 3 bags of cement =300ml
b)For Cebex 100:(Refer Annexure –4)
Cement Required = 3 bags(150 Kg)
Water Required for 3 bags of cement =68 litres
Admixture Required for 3 bags of cement =675g
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
13
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GROUT MIX
Cement = Ordinary Portland Cement (53 –grade) 50 Kg
Water = 0.45 x 50Kg (Per bag of cement) = 22.5 litres
Per Batch = 3 bags of cement
Admixture = Conplast P 211M (Fosroc)0.2% weight of cement (50Kg)
Cebex 100(Fosroc) 225g per bag of cement (50Kg)
Mixing Sequence = Water–Cement–Admixture
Mixing Time =2–3min
a)For Conplast P 211 M:(Refer Annexure –4)
CementRequired= 3 bags(150 Kg)
Water Required for 3 bags of cement =68 litres
Admixture Required for 3 bags of cement =300ml
b)For Cebex 100:(Refer Annexure –4)
Cement Required = 3 bags(150 Kg)
Water Required for 3 bags of cement =68 litres
Admixture Required for 3 bags of cement =675g

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
14
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
9.1 Tests for Grouting:
Viscosity Test
Compressive Strength
Viscosity Test:
 Viscosity test will be executed by means of a flow cone.
 Flow time is measured with a stop watch.
 It is the measurement of time that the grout takes to completely
flow out of the cone.
 It is carried out after the 2-3min minimum mixing time.
 The flow time should be between 10 to 25 seconds.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
14
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
9.1 Tests for Grouting:
Viscosity Test
Compressive Strength
Viscosity Test:
 Viscosity test will be executed by means of a flow cone.
 Flow time is measured with a stop watch.
 It is the measurement of time that the grout takes to completely
flow out of the cone.
 It is carried out after the 2-3min minimum mixing time.
 The flow time should be between 10 to 25 seconds.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
14
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
9.1 Tests for Grouting:
Viscosity Test
Compressive Strength
Viscosity Test:
 Viscosity test will be executed by means of a flow cone.
 Flow time is measured with a stop watch.
 It is the measurement of time that the grout takes to completely
flow out of the cone.
 It is carried out after the 2-3min minimum mixing time.
 The flow time should be between 10 to 25 seconds.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
15
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Compressive Strength:
6 test cubes of 100 x 100 x 100 mm shall be prepared per grouting
session.
After 24 hours, remove cubes from mould and store in the water
storage tank.
Compressive strength at 7 and 28 days for 3 cubes each shall be
tested.
According to specification, average compressive strength of 3 cubes shall be as
follows:
7-Days 17 N/mm
2
28-Days 30 N/mm
2
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
15
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Compressive Strength:
6 test cubes of 100 x 100 x 100 mm shall be prepared per grouting
session.
After 24 hours, remove cubes from mould and store in the water
storage tank.
Compressive strength at 7 and 28 days for 3 cubes each shall be
tested.
According to specification, average compressive strength of 3 cubes shall be as
follows:
7-Days 17 N/mm
2
28-Days 30 N/mm
2
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
15
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Compressive Strength:
6 test cubes of 100 x 100 x 100 mm shall be prepared per grouting
session.
After 24 hours, remove cubes from mould and store in the water
storage tank.
Compressive strength at 7 and 28 days for 3 cubes each shall be
tested.
According to specification, average compressive strength of 3 cubes shall be as
follows:
7-Days 17 N/mm
2
28-Days 30 N/mm
2

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
16
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –1
P.T WORK SEQUENCE –FLOW CHART
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
16
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –1
P.T WORK SEQUENCE –FLOW CHART
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
16
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –1
P.T WORK SEQUENCE –FLOW CHART

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
17
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Post-Tensioning
Laying
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
17
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Post-Tensioning
Stressing Grouting
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
17
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Grouting

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
18
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Laying
Bottom
Shuttering
BottomRebar
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
18
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
BottomRebar
Installation of
ductwith HT
Strands
Fixingof casting
and joining with
duct
Wrapping of
ductjointswith
opp tape
Profile chair
fixing
Top Rebar
Casting the
member
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
18
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Top Rebar
Casting the
member

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
19
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Stressing
Removal of side
Shuttering and
recess former
Fixing of wedge plate
and wedges
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
19
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Removal of side
Shuttering and
recess former
Fixing of wedge plate
and wedges
Insertion of jack to
the strands in
position
Initial pressure
25% for slack
removal
Initial marking of
strand with
marker
Final pressure as
per specification
Checking the
elongation and
recording the values
Chopping of protruding
strand after 24 hours
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
19
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Final pressure as
per specification
Checking the
elongation and
recording the values
Chopping of protruding
strand after 24 hours

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
20
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
20
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Grouting
Patching the
recess pocket with
cement mortar
After 48 hour
preparation of
grouting activity
Mixing (Cement +
Water + Additive)
Mixing the
components in
grout pump for 3-
5 Min
Inject the grout
through the grout
inlet
Flow of grout
through outlet
with same
consistency
Lock the outlet
and withold
pressure for 3-5
bars for 15 sec
Adopt same
procedure for
remaining tendons
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
20
SF ENGINEERING SYSTEMS (INDIA) PVT LTD

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
21
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –2
P.T COMPONENTS & EQUIPMENTS
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
21
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –2
P.T COMPONENTS & EQUIPMENTS
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
21
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –2
P.T COMPONENTS & EQUIPMENTS

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
22
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Strands:
Strands 0.50” 0.60”
Nominal Diameter 12.7mm 15.24mm
Nominal Area 100mm
2
140mm
2
Nominal Weight 0.785kg/m 1.102kg/m
Tensile Strength 1860N/mm
2
1860N/mm
2
Modulus of elasticity 195kN/mm
2
195kN/mm
2
Min breaking load 183.7kN 260.7kN
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
22
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Strands:
Strands 0.50” 0.60”
Nominal Diameter 12.7mm 15.24mm
Nominal Area 100mm
2
140mm
2
Nominal Weight 0.785kg/m 1.102kg/m
Tensile Strength 1860N/mm
2
1860N/mm
2
Modulus of elasticity 195kN/mm
2
195kN/mm
2
Min breaking load 183.7kN 260.7kN
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
22
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Strands:
Strands 0.50” 0.60”
Nominal Diameter 12.7mm 15.24mm
Nominal Area 100mm
2
140mm
2
Nominal Weight 0.785kg/m 1.102kg/m
Tensile Strength 1860N/mm
2
1860N/mm
2
Modulus of elasticity 195kN/mm
2
195kN/mm
2
Min breaking load 183.7kN 260.7kN

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
23
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GI-Duct:
Strips Type = GI (Galvanized Iron)
Duct Type = FlatDuct(FA) ,Round Duct(MA)
Strip Thickness = 0.3mm
FA Duct Dimension = 5s & 4s (80 x 20mm)
3s & 2s (60 x 20mm)
MA Duct Diameter = 68mm to 135mm
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
23
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GI-Duct:
Strips Type = GI (Galvanized Iron)
Duct Type = FlatDuct(FA) ,Round Duct(MA)
Strip Thickness = 0.3mm
FA Duct Dimension = 5s & 4s (80 x 20mm)
3s & 2s (60 x 20mm)
MA Duct Diameter = 68mm to 135mm
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
23
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GI-Duct:
Strips Type = GI (Galvanized Iron)
Duct Type = FlatDuct(FA) ,Round Duct(MA)
Strip Thickness = 0.3mm
FA Duct Dimension = 5s & 4s (80 x 20mm)
3s & 2s (60 x 20mm)
MA Duct Diameter = 68mm to 135mm

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
24
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Anchorage:
Flat Anchorage (FA):
Multi Anchorage (MA):
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
24
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Anchorage:
Flat Anchorage (FA):
Multi Anchorage (MA):
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
24
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Anchorage:
Flat Anchorage (FA):
Multi Anchorage (MA):

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
25
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Wedges:
Tendon Sample :
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
25
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Wedges:
Tendon Sample :
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
25
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Wedges:
Tendon Sample :

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
26
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
T–10 Hydraulic Jack:
T–25 Hydraulic Jack & Pump
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
26
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
T–10 Hydraulic Jack:
T–25 Hydraulic Jack & Pump
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
26
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
T–10 Hydraulic Jack:
T–25 Hydraulic Jack & Pump

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
27
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GroutPump:
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
27
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GroutPump:
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
27
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
GroutPump:

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
28
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –3
CHECK LIST
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
28
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –3
CHECK LIST
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
28
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –3
CHECK LIST

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
29
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FORINSTALLATION
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1 Placement of Type of Duct
2 Placement ofNumbers of Tendons
3 Placement of Tendons Spacing
4 Correct Numbers of strand Installation within duct
5 Length of strands are enough for stressing
6 Position and correct type of casting at live end
7 Position and correct type of dead end
8 Profile of Tendons at supports points
9 Placement of correct type and no of bursting steel
10Placement of correct spacing links
11Ensureall grout portsareprovided
Comments: (RCC)
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
29
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FORINSTALLATION
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1 Placement of Type of Duct
2 Placement ofNumbers of Tendons
3 Placement of Tendons Spacing
4 Correct Numbers of strand Installation within duct
5 Length of strands are enough for stressing
6 Position and correct type of casting at live end
7 Position and correct type of dead end
8 Profile of Tendons at supports points
9 Placement of correct type and no of bursting steel
10Placement of correct spacing links
11Ensureall grout portsareprovided
Comments: (RCC)
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
29
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FORINSTALLATION
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1 Placement of Type of Duct
2 Placement ofNumbers of Tendons
3 Placement of Tendons Spacing
4 Correct Numbers of strand Installation within duct
5 Length of strands are enough for stressing
6 Position and correct type of casting at live end
7 Position and correct type of dead end
8 Profile of Tendons at supports points
9 Placement of correct type and no of bursting steel
10Placement of correct spacing links
11Ensureall grout portsareprovided
Comments: (RCC)
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
30
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FOR STRESSING
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1PreparationFor Stressing
2Fixing of correct Type of Anchorages
3Fixing of correct Type of Wedges
4Applied forces for 75% UTS
5Elongation to be Measured and For the limit
6Cut off the Excess Stressing strands.
Comments :
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
30
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FOR STRESSING
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1PreparationFor Stressing
2Fixing of correct Type of Anchorages
3Fixing of correct Type of Wedges
4Applied forces for 75% UTS
5Elongation to be Measured and For the limit
6Cut off the Excess Stressing strands.
Comments :
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
30
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FOR STRESSING
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1PreparationFor Stressing
2Fixing of correct Type of Anchorages
3Fixing of correct Type of Wedges
4Applied forces for 75% UTS
5Elongation to be Measured and For the limit
6Cut off the Excess Stressing strands.
Comments :
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
31
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FOR GROUTING
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1Filling of therecess pockets left out for stressing
2W/cratioMaintainedas per the methodology
3Cement and Admixturesfollowingas per the methodology
41st Stage of Tendon flushing with water
52nd Stage of Tendon filled withGrout
6Grouting Completed after cut of the Excess hose
Comments :
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
31
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FOR GROUTING
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1Filling of therecess pockets left out for stressing
2W/cratioMaintainedas per the methodology
3Cement and Admixturesfollowingas per the methodology
41st Stage of Tendon flushing with water
52nd Stage of Tendon filled withGrout
6Grouting Completed after cut of the Excess hose
Comments :
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
31
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
CHECKLIST FOR GROUTING
PROJECT NAME DATE
LOCATION/FLOOR
DRAWING
NO
GRID NO /POUR
DRAWING
REV
Tendon ID :-
S.NO ELEMENTS TO BE CHECKED OK
NOT
OK
REMARKS
1Filling of therecess pockets left out for stressing
2W/cratioMaintainedas per the methodology
3Cement and Admixturesfollowingas per the methodology
41st Stage of Tendon flushing with water
52nd Stage of Tendon filled withGrout
6Grouting Completed after cut of the Excess hose
Comments :
SFEC REPRESENTATIVE CONTRACTOR REPRESENTATIVE CLIENT REPRESENTATIVE
NAME :- NAME :- NAME :-
DESIGNATION:- DESIGNATION:- DESIGNATION:-
DATE :- DATE :- DATE :-
SIGN :- SIGN :- SIGN :-

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
32
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –4
ADMIXTURE
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
32
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –4
ADMIXTURE
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
32
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –4
ADMIXTURE

䍥扥
x
㄰0





䍥扥x ㄰0
*

(Formerly Conbex 100)



Plasticised expanding grout admixture


啳敳

䍥扥x ㄰0 楳 慮 慤浩硴畲e 景r 捥浥湴楴楯畳 杲潵瑳 睨敲攠愠
r敤畣e搠 睡瑥爯捥浥n 琠 r慴io 慮d 灯獩瑩v攠 數灡湳楯 n 楳
r敱畩r敤⸠ 䅰灬楣慴楯湳 楮捬畤e 扥d gr潵瑩湧, 摵捴 gr潵瑩湧Ⱐ
湯n-獨物湫 楮晩汬楮g 慮d 橯楮瑩湧.

䅤癡湴慧敳

! 䝡獥潵 s 數灡湳楯 n 獹獴em 捯浰敮獡瑥 s 景r 灬慳瑩挠
獨物湫 慧攠慮d 獥瑴汥浥n t in 灲潰敲ly 摥獩杮ed
捥浥湴楴楯畳 gr潵琮
! 剥摵捥 d 睡瑥爯捥浥n 琠 牡瑩o 浩硥s in 瑨e 杲潵t 浩砠
敮獵re猠汯w 灥牭敡扩汩t y 慮d 汯ng 瑥rm 摵牡扩汩ty 楮
獥牶楣攮
! 䝩癥s 桩杨 gr潵t 晬畩摩瑹 睩瑨 汯w 睡瑥爯捥浥湴 牡瑩漬 瑨畳
浡歩湧 灬慣敭敮t 潲 楮橥捴楯n 潦 瑨e gr潵t 敡sy.
! 乯 浥瑡汬楣 ir潮 捯湴敮t 瑯 捯rr潤e 慮d 捡畳e 獴慩湩湧 潲
摥瑥物潲慴楯n 摵e 瑯 牵獴 數灡湳楯n 楮 瑨e 杲潵琮
! 䍯浰潳楴楯n 慬汯睳 桩杨 敡牬礠獴r敮杴h 摥v敬潰浥湴 楮
gr潵瑳, 睩瑨潵t 瑨e 畳e 潦 捨汯物摥献

却慮摡牤s 捯浰汩慮捥

䍥扥x ㄰0 楳 a 獵楴慢汥 灲e-獴牥獳楮g 杲潵t 慤浩硴畲e 睨敮
捯浰汹楮g 睩瑨 䉓 㠱㄰ 偡牴 ㄬ ㄹ㠵, 獥捴楯n 㠮㤮㐮㘮

䑥獣物灴楯n

䍥扥x ㄰0 楳 獵灰汩敤⁡s a 灯睤敲 慤浩硴畲攮 周e 浡瑥物al 楳
愠 捯浢楮慴楯n 潦 愠 灬慳瑩捩獩湧 慧敮t 慮d 愠 条s 灲潤畣楮朠
數灡湳楯n 浥摩畭. 周e 灬慳瑩捩獩湧 慧敮t 慬汯睳 瑨e 畳e 潦
a r敤畣ed 睡瑥爯捥浥n 琠 牡瑩o 睩th 捯湳敱略n t 楮cr敡獥搠
獴r敮杴桳 慮d 摵牡扩汩ty. 周e 數灡湳楶e 浥摩畭 捯畮瑥牡捴猠
瑨攠湡瑵牡l 獥瑴汥m敮t 慮搠灬慳瑩c 獨物湫慧e 潦 瑨攠gr潵t 慮搠
慩摳 獴慢楬楴y 慮d 捯桥獩潮.

卵晦楣楥湴 r敳瑲慩湥d 數灡湳楯n 楳 摥癥汯灥d 瑯⁥湳ure a 桩杨
摥gr敥 潦 楮瑥牦慣楡l 捯湴慣琮

印散楦楣慴楯n

Performance specification

䅬l 杲潵瑩湧 ⡳灥捩晹 摥瑡楬s 慮d ar敡s 潦 慰灬楣慴楯温 浵獴 扥
捡牲楥d 潵t 睩th a 捥浥nt 扡獥d gr潵琠 楮捯牰潲慴楮 朠 愠
灬慳瑩捩獥d, 數灡湤楮g 灯睤er 慤浩硴ure. 周e 慤浩硴ure 浵獴
扥 ir潮-fr敥 慮d 捨汯物摥-fr敥 慮d 獨慬l 扥 慤摥搠瑯 瑨e gr潵琠
楮⁴桥 pr潰潲瑩潮s ㈲㔠g 潦 慤浩硴ure 灥r 㔰g 潦 捥浥湴⸠
T桥 慤浩硴ure 獨慬l pr潶楤e 慮 數灡湳楯n 潦 異 瑯 㐥 楮 瑨攠
灬慳瑩c 杲潵琬 批 浥慮s 潦 a 条獥潵s 獹獴敭. 周e 慤浩硴ur攠
浵獴 扥 獴潲敤, 桡湤汥d 慮d 浩硥d 獴物捴汹 楮 慣捯r摡湣攠
睩瑨 瑨e 浡湵晡捴u r敲❳ 楮獴牵捴楯湳.








Supplier specification

䅬l 杲潵瑩湧 ⡳灥捩晹 摥瑡楬s 慮d 慲敡s 潦 慰灬楣慴楯温畳t 扥
捡牲楥d 潵t 畳楮g a 捥浥nt 扡獥d 杲潵t, 楮捯牰潲慴楮朠† 䍥扥x
㄰0 浡湵晡捴畲e d by 䙯獲oc 慮d 慰灬楥d 獴物捴ly in 慣捯牤慮捥
睩瑨 瑨e 浡湵晡捴畲敲❳ 瑥捨湩捡l 摡瑡 獨敥琮

偲潰敲瑩敳

Chloride content : 乩l 瑯 䉓 㔰㜵
Compressive strength : 周e 灬慳瑩捩獩湧 慣瑩潮 潦
䍥扥x ㄰0 慬汯睳 牥摵捴楯渠
潦⁴桥 睡瑥爯捥浥湴 牡瑩o 潦
捥浥湴楴楯畳 杲潵瑳 睨楬獴
浡楮瑡楮楮g 晬潷 灲潰敲瑩敳⸠
周楳 杩癥s 業灲潶敭敮t 楮
獴牥湧瑨 慮d 汯湧 瑥牭
摵牡扩汩瑹 睨敮 捵牥d 畮摥r
†††††††††††††††††††††††††牥獴牡楮琮
Setting times : 䍥扥x ㄰0 摯敳 湯琠
獩杮楦楣慮瑬y a晦散t 瑨攠
獥瑴楮g 瑩浥s 潦 捥浥湴
扡獥d gr潵瑳.
Expansion characteristics: 周e 捯湴r潬汥d 灯獩瑩癥
數灡湳楯n 楮 畮獥t gr潵瑳
楮捯牰潲慴楮g 䍥扥x ㄰〠
潶er捯浥s 灬慳瑩挠
獥瑴汥浥湴 睨敮 浥慳ur敤
楮⁡捣or摡湣e 睩瑨
䅓呍 䌸㈷⸠ 䅮
畮r敳瑲慩湥d 數灡湳楯n 潦
†††††††††††††††††††††††††異 瑯 㐥 楳 瑹灩捡氮
Time for expansion : ㄵ 浩湵瑥s - 2 桯畲献
T敭灥牡瑵牥s 慢潶e 20°C
浡y 獬楧桴汹 r敤畣e 瑨敳e
†††††††††††††††††††††††††瑩浥献
Compatibility : 䍥扥x ㄰0 楳 捯浰慴楢汥
睩瑨 慬l 瑹灥s 潦 偯牴污湤
捥浥湴. 䍥扥x ㄰0 浡y 扥
畳敤⁩渠浩硥猠捯湴慩湩湧
捥牴慩n 潴桥r 䙯sr潣
慤浩硴ur敳. 䍯湳畬t 䙯sr潣
†††††††††††††††††††††††††景r 晵牴桥r 楮景牭慴楯渮

Instructions for use

Mixing

For best results Fosroc MR3 mixer must be used. For
quantities up to 50 kg a slow speed drill fitted with a high
shear paddle is suitable. Larger quantities will require a high
shear vane mixer.

It is essential that machine mixing capacity and labour
availability is adequate to enable the grouting operation to be
carried out continuously. This may require the use of a holding
tank with provision for gentle agitation to maintain fluidity.

The selected water content should be accurately measured
into the mixer. Slowly add the cement (and sand if required)
and Cebex 100. Mix continuously for 5 minutes, making sure
that a smooth even consistency is obtained.

Application

Areas to be grouted should be prepared to ensure substrates
are clean, sound, and then pre-wetted. The unrestrained
surface area of the grout must be kept to a minimum. Place
the grout within 20 minutes of mixing to gain the full benefit
of the expansion process. Adopt usual placing or pumping
procedures ensuring a continuous operation.

Curing

On completion of the grouting operation, any exposed areas
which are not to be cut back should be thoroughly cured by
means of water application, Concure* curing membrane or
wet hessian.

Cleaning

Grouts mixed with Cebex 100 should be removed from tools
and equipment with clean water immediately after use.
Remove cured material mechanically or with Fosroc Acid Etch.

Limitations

Cebex 100 is not compatible with High Alumina Cement.
Estimating

Supply
Cebex 100 : 5 kg packs & 225 g tins

Dosage
OPC Concreting Water Conbex Approx
sand 100 yield
50 kg - 20-22 litres 225 g 36 litres
50 kg 50 kg 22-24 litres 225 g 57 litres

Note: For grout, mortar or concrete mixes with an aggregate/
cement ratio more than 1, use 4x225 g units or 900 g
of Cebex 100 per 100 kg of cement.

Effects of overdosing

Overdosing of Cebex 100 increases expansion and may cause
frothing.

Storage

Cebex 100 has a shelf life of 12 months if kept in a dry store in
its original packaging. High temperature and humidity storage
may reduce this period.

Precautions

Health and safety

Cebex 100 is of low hazard.

Contact with the skin and eyes, or inhalation of dust should
be avoided. Wear suitable protective clothing, gloves, eye/
face protection and dust mask. After contact with skin, wash
off with clean water. In case of contact with eyes, rinse
immediately with plenty of water and seek medical attention.

For further information see Product Material Safety Data sheet.




* Denotes the trademark of Fosroc International Limited


See separate data sheet



Al Gurg Fosroc LLC REGIONAL SALES OFFICES IN :

P. O. Box 657
Dub ai
United Arab Emirates

TEL : (04) 858606
FAX : (04) 859649
DUBAI
Al Gurg Fosroc

TEL : 858787
FAX : 852023
ABU DHABI
Al Gurg Fosroc

TEL : 731779
FAX : 731449
BAHRAIN
YBA Kanoo

TEL : 735454
FAX : 732828
KUWAIT
Boodai

TEL : 4817618
FAX : 4832124
OMAN
GETCO

TEL : 7715080
FAX : 7717554
QATAR
Tadmur

TEL : 4413628
FAX : 4440812

Important note

Fosroc products are guaranteed against defective materials and manufacture and are sold subject to its standard terms and conditions of sale, copies of
which may be obtained on request. Whilst Fosroc endeavours to ensure that the technical information on this data sheet is correct at the time of printing,
it is the customer’s responsibility to satisfy himself, by checking with the company that this information is still current at the time of use, that the product is
suitable for the intended application, and that the actual conditions of use are in accordance with those recommended. Because Fosroc has no control over
the conditions of use of its products, all recommendations or suggestions regarding the use of these products are made without guarantee.

www.fosrocgulf.com

UAE/0321/00/A

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
35
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –5
SAFETY
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
35
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –5
SAFETY
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
35
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –5
SAFETY

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
36
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Safety Work Procedure sfor Post Tensioning Work
1.Installation of Tendon Operations:
Lifting of Post Tensioning Materials
Lifting operation to comply with Operation Crane regulations
Ensure Lifting Supervisors / Signal Man are qualified.
To explain about the work process to the workers dealing with
lifting work before the work starts.
Installation of Strand Dispenser
Ensure the dispenser is sufficiently stable to prevent from collapse.
Ensure no personnel standing in front of dispenser when uncoiling
strand.
Use safety gloves when working.
Usage of electrical equipments
Ensure proper industrial socket, plug and connectors are used
before starting of work.
The wires should be raised above ground level.
Proper shelter should be provided for all electrical components at
wet weather conditions.
Use safety gloves and shoes at time of work.
Cutting of PT Strand
Cutting machine should have a safety guard covered to it before
starting the work.
Use gloves and safety goggles at time of work.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
36
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Safety Work Procedure sfor Post Tensioning Work
1.Installation of Tendon Operations:
Lifting of Post Tensioning Materials
Lifting operation to comply with Operation Crane regulations
Ensure Lifting Supervisors / Signal Man are qualified.
To explain about the work process to the workers dealing with
lifting work before the work starts.
Installation of Strand Dispenser
Ensure the dispenser is sufficiently stable to prevent from collapse.
Ensure no personnel standing in front of dispenser when uncoiling
strand.
Use safety gloves when working.
Usage of electrical equipments
Ensure proper industrial socket, plug and connectors are used
before starting of work.
The wires should be raised above ground level.
Proper shelter should be provided for all electrical components at
wet weather conditions.
Use safety gloves and shoes at time of work.
Cutting of PT Strand
Cutting machine should have a safety guard covered to it before
starting the work.
Use gloves and safety goggles at time of work.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
36
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Safety Work Procedure sfor Post Tensioning Work
1.Installation of Tendon Operations:
Lifting of Post Tensioning Materials
Lifting operation to comply with Operation Crane regulations
Ensure Lifting Supervisors / Signal Man are qualified.
To explain about the work process to the workers dealing with
lifting work before the work starts.
Installation of Strand Dispenser
Ensure the dispenser is sufficiently stable to prevent from collapse.
Ensure no personnel standing in front of dispenser when uncoiling
strand.
Use safety gloves when working.
Usage of electrical equipments
Ensure proper industrial socket, plug and connectors are used
before starting of work.
The wires should be raised above ground level.
Proper shelter should be provided for all electrical components at
wet weather conditions.
Use safety gloves and shoes at time of work.
Cutting of PT Strand
Cutting machine should have a safety guard covered to it before
starting the work.
Use gloves and safety goggles at time of work.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
37
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Working near edge of the building
Workers have to briefed for working on heights before
commencing the work.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are working at outer periphery of the
building.
Provision of effective barricades.
2.Stressingof Tendon Operations:
Setting up of Stressing Equipment
Only trained personnel are allowed to in stall and operate the
equipment.
Ensure the jack and pressure cage are calibrated.
Stressing area precautions
Stressing area has to be barricaded to avoid other workers entering
the zone till completion of stressing activity.
No workers shall stand behind or at the face of the jack during
stressing.
There should be enough space between the jack and worker who is
handling it at time of stressing the tendons.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are work ing at outer periphery of the
building.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
37
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Working near edge of the building
Workers have to briefed for working on heights before
commencing the work.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are working at outer periphery of the
building.
Provision of effective barricades.
2.Stressingof Tendon Operations:
Setting up of Stressing Equipment
Only trained personnel are allowed to in stall and operate the
equipment.
Ensure the jack and pressure cage are calibrated.
Stressing area precautions
Stressing area has to be barricaded to avoid other workers entering
the zone till completion of stressing activity.
No workers shall stand behind or at the face of the jack during
stressing.
There should be enough space between the jack and worker who is
handling it at time of stressing the tendons.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are work ing at outer periphery of the
building.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
37
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Working near edge of the building
Workers have to briefed for working on heights before
commencing the work.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are working at outer periphery of the
building.
Provision of effective barricades.
2.Stressingof Tendon Operations:
Setting up of Stressing Equipment
Only trained personnel are allowed to in stall and operate the
equipment.
Ensure the jack and pressure cage are calibrated.
Stressing area precautions
Stressing area has to be barricaded to avoid other workers entering
the zone till completion of stressing activity.
No workers shall stand behind or at the face of the jack during
stressing.
There should be enough space between the jack and worker who is
handling it at time of stressing the tendons.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are work ing at outer periphery of the
building.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
38
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
3.Groutingof Tendon Operations:
Lifting of cement bags
Lifting operations to comply with crane regulations.
Lifting done manually the worker has to wear safety helmet, gloves
and goggles along with nose mask.
To explain about the work process to the workers dealing with lifting
work before work starts.
Working near edge of the building
Workers have to briefed for working on heights before
commencing the work.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are working at outer periphery of the
building.
Provision of effective barricades.
Grouting area precautions
Ensure the workers are wearing safety helmet, gloves and goggles
along with nose mask.
Proper hose cleaning should be done after the completion of stressing
activity.
Safe method to check on pressure grout hose to be briefed to the
workers.
Ensure proper patching is done before the commencement of grouting
activity.
Ensure all the tendons is been grouted individually.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
38
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
3.Groutingof Tendon Operations:
Lifting of cement bags
Lifting operations to comply with crane regulations.
Lifting done manually the worker has to wear safety helmet, gloves
and goggles along with nose mask.
To explain about the work process to the workers dealing with lifting
work before work starts.
Working near edge of the building
Workers have to briefed for working on heights before
commencing the work.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are working at outer periphery of the
building.
Provision of effective barricades.
Grouting area precautions
Ensure the workers are wearing safety helmet, gloves and goggles
along with nose mask.
Proper hose cleaning should be done after the completion of stressing
activity.
Safe method to check on pressure grout hose to be briefed to the
workers.
Ensure proper patching is done before the commencement of grouting
activity.
Ensure all the tendons is been grouted individually.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
38
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
3.Groutingof Tendon Operations:
Lifting of cement bags
Lifting operations to comply with crane regulations.
Lifting done manually the worker has to wear safety helmet, gloves
and goggles along with nose mask.
To explain about the work process to the workers dealing with lifting
work before work starts.
Working near edge of the building
Workers have to briefed for working on heights before
commencing the work.
Safety belt connected to jacket has to be anchored to a permanent
structure, if the workers are working at outer periphery of the
building.
Provision of effective barricades.
Grouting area precautions
Ensure the workers are wearing safety helmet, gloves and goggles
along with nose mask.
Proper hose cleaning should be done after the completion of stressing
activity.
Safe method to check on pressure grout hose to be briefed to the
workers.
Ensure proper patching is done before the commencement of grouting
activity.
Ensure all the tendons is been grouted individually.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
39
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –6
Quality Assurance Policy (QAP)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
39
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –6
Quality Assurance Policy (QAP)
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
39
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
ANNEXURE –6
Quality Assurance Policy (QAP)

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
40
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
In House Quality Assurance Policy for SF Systems
Note:
System acceptance test will be conducted from any of the reputed
lab basedonthe requirement and the same will be done on ce in a
year.
Performance test -Material Test Certificate (MTC) will beissued for
every lotto beused at site.
System
Acceptance Test
Anchorage
Efficiency
Test
Load
Transfer Test
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
40
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
In House Quality Assurance Policy for SF Systems
Note:
System acceptance test will be conducted from any of the reputed
lab basedonthe requirement and the same will be done on ce in a
year.
Performance test -Material Test Certificate (MTC) will beissued for
every lotto beused at site.
FIP
Recommentations
Load
Transfer Test
Performance Test
(Materials)
Anchorage Sheathing
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
40
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
In House Quality Assurance Policy for SF Systems
Note:
System acceptance test will be conducted from any of the reputed
lab basedonthe requirement and the same will be done on ce in a
year.
Performance test -Material Test Certificate (MTC) will beissued for
every lotto beused at site.
Performance Test
(Materials)
Strand

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
41
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
System Acceptance Test :
Anchorage Efficiency Test
Objective of the test:
This test is conducted to check and verify the performance of t he
anchorage assembly and to determine any decrease in breaking load of the
Pre–Stressing steal (Strands)due to the influence of the anchorage, and to
observe the elongation and behavior of the wedges.
Test Remarks:
The test will be conducted at any of the reputed lab based on the
requirement which satisfy FIP recommendations.
Frequency:
Theentire test is related to SF system policy and will be conducted
once in a year.
Load TransferTest
Objective of the test:
This test is conducted to verifythe transfer of the pre stressing force
from the mechanical anchorage and its competency to the concrete without
any failure in the anchorage assembly.
Test Remarks:
The test will be conducted at any of the reputed lab based on the
requirement which satisfy FIP recommendations.
Frequency:
Theentire test is related to SF system policy and will be conducted
once in a year.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
41
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
System Acceptance Test :
Anchorage Efficiency Test
Objective of the test:
This test is conducted to check and verify the performance of t he
anchorage assembly and to determine any decrease in breaking load of the
Pre–Stressing steal (Strands)due to the influence of the anchorage, and to
observe the elongation and behavior of the wedges.
Test Remarks:
The test will be conducted at any of the reputed lab based on the
requirement which satisfy FIP recommendations.
Frequency:
Theentire test is related to SF system policy and will be conducted
once in a year.
Load TransferTest
Objective of the test:
This test is conducted to verifythe transfer of the pre stressing force
from the mechanical anchorage and its competency to the concrete without
any failure in the anchorage assembly.
Test Remarks:
The test will be conducted at any of the reputed lab based on the
requirement which satisfy FIP recommendations.
Frequency:
Theentire test is related to SF system policy and will be conducted
once in a year.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
41
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
System Acceptance Test :
Anchorage Efficiency Test
Objective of the test:
This test is conducted to check and verify the performance of t he
anchorage assembly and to determine any decrease in breaking load of the
Pre–Stressing steal (Strands)due to the influence of the anchorage, and to
observe the elongation and behavior of the wedges.
Test Remarks:
The test will be conducted at any of the reputed lab based on the
requirement which satisfy FIP recommendations.
Frequency:
Theentire test is related to SF system policy and will be conducted
once in a year.
Load TransferTest
Objective of the test:
This test is conducted to verifythe transfer of the pre stressing force
from the mechanical anchorage and its competency to the concrete without
any failure in the anchorage assembly.
Test Remarks:
The test will be conducted at any of the reputed lab based on the
requirement which satisfy FIP recommendations.
Frequency:
Theentire test is related to SF system policy and will be conducted
once in a year.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
42
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Quality Assurance Policy at Site
Sl.
No
Work Sequence Formats Objective FieldInspection
1
Monitoring of work prior
to concreting
Checklist on
completion of
laying
To check profile ,
spacing and
number of strands
per tendon
Shop drawing
prepared based on
the design
requirement will
serve as basis
2
Post Concreting
Inspection
Concrete cube
strength
minimum
27N/mm
2
To check concrete
is ready to
withstand Pre
Stressing Force
Theoretical tendon
elongation report
submission for every
pour/slab
3
At the time of stressing
activity
Stressing records
and elongation
reportshas to be
prepared
To check the
satisfactory
performance of
the stressing
carried
On submissionof
stressing record , De
–Shuttering
operations can be
carried out
4
At the time of grouting
activity
Field Test such
as Cube Test and
Viscosity Test
To ensure the
flow character of
the grout and to
check the
strength of the
grout
Viscosity test and
compressive
strength are
conducted before
grouting andthis
test is trulybased
onrequirement of
the clients.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
42
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Quality Assurance Policy at Site
Sl.
No
Work Sequence Formats Objective FieldInspection
1
Monitoring of work prior
to concreting
Checklist on
completion of
laying
To check profile ,
spacing and
number of strands
per tendon
Shop drawing
prepared based on
the design
requirement will
serve as basis
2
Post Concreting
Inspection
Concrete cube
strength
minimum
27N/mm
2
To check concrete
is ready to
withstand Pre
Stressing Force
Theoretical tendon
elongation report
submission for every
pour/slab
3
At the time of stressing
activity
Stressing records
and elongation
reportshas to be
prepared
To check the
satisfactory
performance of
the stressing
carried
On submissionof
stressing record , De
–Shuttering
operations can be
carried out
4
At the time of grouting
activity
Field Test such
as Cube Test and
Viscosity Test
To ensure the
flow character of
the grout and to
check the
strength of the
grout
Viscosity test and
compressive
strength are
conducted before
grouting andthis
test is trulybased
onrequirement of
the clients.
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
42
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
Quality Assurance Policy at Site
Sl.
No
Work Sequence Formats Objective FieldInspection
1
Monitoring of work prior
to concreting
Checklist on
completion of
laying
To check profile ,
spacing and
number of strands
per tendon
Shop drawing
prepared based on
the design
requirement will
serve as basis
2
Post Concreting
Inspection
Concrete cube
strength
minimum
27N/mm
2
To check concrete
is ready to
withstand Pre
Stressing Force
Theoretical tendon
elongation report
submission for every
pour/slab
3
At the time of stressing
activity
Stressing records
and elongation
reportshas to be
prepared
To check the
satisfactory
performance of
the stressing
carried
On submissionof
stressing record , De
–Shuttering
operations can be
carried out
4
At the time of grouting
activity
Field Test such
as Cube Test and
Viscosity Test
To ensure the
flow character of
the grout and to
check the
strength of the
grout
Viscosity test and
compressive
strength are
conducted before
grouting andthis
test is trulybased
onrequirement of
the clients.

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
43
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
HEAD OFFICE:
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
No.118, 13
th
Cross Street, Sri Sai Nagar,
Thoraipakkam, Chennai–600097
M-+91 9840066239, + 91 9551635559, +91 8220373680
E–[email protected],[email protected],[email protected]
REGIONAL OFFICE:
DEHRADUN NEW DELHI
2
nd
Floor, Tilak Plaza, Tilak Road, 220, Ground Floor, Arjun Nagar
Dehradun, Uttrakhand–248001. Sufdurjung Enclave, New Delhi-
M-+91 9045089020 New Delhi-110029
E–[email protected] E–[email protected]
PUNE BANGALORE
F–133, Ashok Mall, 27/53/3, Srinivasa Nilaya,7
th
Main
Oppto Sun & Sand Hotel, Bundgarden Road J.P Nagar, 1
st
Phase, Sarakki
Pune–411001 Kanakpura, Karnataka-560078
M–9850431195 M-8600902222
E–[email protected] [email protected]
COIMBATORE
No.30, 1
st
Floor, Shanthi Nagar,
Vilankuruchi Main Road, Cheran Maa Nagar
Coimbatore–641035
M–9994247766
E–[email protected]
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
43
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
HEAD OFFICE:
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
No.118, 13
th
Cross Street, Sri Sai Nagar,
Thoraipakkam, Chennai–600097
M-+91 9840066239, + 91 9551635559, +91 8220373680
E–[email protected],[email protected],[email protected]
REGIONAL OFFICE:
DEHRADUN NEW DELHI
2
nd
Floor, Tilak Plaza, Tilak Road, 220, Ground Floor, Arjun Nagar
Dehradun, Uttrakhand–248001. Sufdurjung Enclave, New Delhi-
M-+91 9045089020 New Delhi-110029
E–[email protected] E–[email protected]
PUNE BANGALORE
F–133, Ashok Mall, 27/53/3, Srinivasa Nilaya,7
th
Main
Oppto Sun & Sand Hotel, Bundgarden Road J.P Nagar, 1
st
Phase, Sarakki
Pune–411001 Kanakpura, Karnataka-560078
M–9850431195 M-8600902222
E–[email protected] [email protected]
COIMBATORE
No.30, 1
st
Floor, Shanthi Nagar,
Vilankuruchi Main Road, Cheran Maa Nagar
Coimbatore–641035
M–9994247766
E–[email protected]
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
43
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
HEAD OFFICE:
SF ENGINEERING SYSTEMS (INDIA) PVT. LTD.
(Reliable Partner in Specialized Engineering )
No.118, 13
th
Cross Street, Sri Sai Nagar,
Thoraipakkam, Chennai–600097
M-+91 9840066239, + 91 9551635559, +91 8220373680
E–[email protected],[email protected],[email protected]
REGIONAL OFFICE:
DEHRADUN NEW DELHI
2
nd
Floor, Tilak Plaza, Tilak Road, 220, Ground Floor, Arjun Nagar
Dehradun, Uttrakhand–248001. Sufdurjung Enclave, New Delhi-
M-+91 9045089020 New Delhi-110029
E–[email protected] E–[email protected]
PUNE BANGALORE
F–133, Ashok Mall, 27/53/3, Srinivasa Nilaya,7
th
Main
Oppto Sun & Sand Hotel, Bundgarden Road J.P Nagar, 1
st
Phase, Sarakki
Pune–411001 Kanakpura, Karnataka-560078
M–9850431195 M-8600902222
E–[email protected] [email protected]
COIMBATORE
No.30, 1
st
Floor, Shanthi Nagar,
Vilankuruchi Main Road, Cheran Maa Nagar
Coimbatore–641035
M–9994247766
E–[email protected]

Method Statement f or SF Post Tensioning System (SFEC/WP/01)
44
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SFEngineeringSystems(INDIA)PrivateLimited
(ReliablePartnerinSpecializedEngineering)
ASSURINGOURBESTSERVICE&SUPPORTATALLTIMES
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
44
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SFEngineeringSystems(INDIA)PrivateLimited
(ReliablePartnerinSpecializedEngineering)
ASSURINGOURBESTSERVICE&SUPPORTATALLTIMES
Method Statement f or SF Post Tensioning System (SFEC/WP/01)
44
SF ENGINEERING SYSTEMS (INDIA) PVT LTD
SFEngineeringSystems(INDIA)PrivateLimited
(ReliablePartnerinSpecializedEngineering)
ASSURINGOURBESTSERVICE&SUPPORTATALLTIMES