mivan form work a time saving technique for multi story buildings
Size: 802.34 KB
Language: en
Added: May 25, 2016
Slides: 14 pages
Slide Content
MFE FORMWORK TECHNOLOGY SDN. BHD.
ALL RIGHTS RESERVED. NO PART OF THIS PUBLICATION MA Y BE REPRODUCED OR TRANSMITTED IN ANY FORM OR BY AN Y MEANS, INCLUDING PHOTOCOPYING AND RECORDING, WITH OUT THE
WRITTEN PERMISSION OF THE COPYRIGHT HOLDER. APPLICA TION FOR WHICH SHOULD BE ADDRESSED TO THE PUBLISHER . SUCH WRITTEN PERMISSION MUST ALSO BE OBTAINED BEF ORE ANY
PART OF THE PUBLICATION IS STORED IN A RETRIEVAL SY STEM OF ANY NATURE.
WARNING: THE DOING OF AN UNATHORIZED ACT IN RELATIO N TO A COPYRIGHT WORK MAY RESULT IN BOTH CIVIL CLAI M FOR DAMAGES AND CRIMINAL PROSECUTION
1.2.1 Base Control Points
1.2.2 Transferred Setting Out Point
1.2.3 Bench Mark
1.2.4 Temporary Bench Mark (TBM)
1.3 Day to Day Detail Survey
1.3.1 300mm Offset Line
1.3.2 Concrete Level Survey
1.3.3 Kicker Level Survey
1.3.4 Deviation Survey
1.3.5 Analysis of Survey Results
1.3.6 Method of Adjustment
1.3.7 Deviation Survey Not Making Sense
1.3.8 Plumb and Alignment of Walls
1.4 Keeping of Survey Records
1.5 Miscellaneous:
- Simplified Plan of Marking Out Principles
- Control and Adjustment of Vertical Alignment by Packing
- Everyday Survey Check
- Bench Marks
- Plumbing
- Buildings and Tall Structures
3
1.0 Setting Out, Alignment and Verticality
1.1 Introduction
In order to achieve the dimensional and vertical accuracy that is possible with the MFE System
Formwork it is absolutely necessary that the survey control for the building is maintained both
accurately and systematically.
In the first instance the base survey for the building, meaning the primary setting out lines and
reduced level bench marks must be established accurately. These survey control points must also
be transferred accurately up the building as work progresses.
In the second instance the day to day detail survey, meaning marking out of wall alignment and
column positions, kicker level survey, concrete level survey and deviation report must also be
carried out accurately.
Some of the work is usually carried out by the main contractor or by his setting out sub contractor.
However, because of the major impact that surveying and particularly survey accuracy has on the
formwork positioning and thereby the as cast concrete position you must fully understand survey
control and how it affects the formwork.
1.2 Base or Primary Setting Out
The base or primary setting out means the reference lines and levels from which all survey work
should originate from and which all survey work should close back to.
The base survey in terms of our building work means the transferred setting out points and the
temporary bench marks (TBM’s). The Transferred Setting Points and TBM’s should themselves
originate from Base Control Points for the building. The definition of these terms is listed below and
a simplified plan of setting out principles is attached at the back of this section.
1.2.1. Base Control Points
These are established and maintained on the transfer plate level for the duration of the structural
frame construction. They are to be carried vertically up through each and every floor slab using a
plumb bob or preferably an optical or laser plumb. Refer to the attached typical layout plan and
textbook extracts showing suggested methods of setting out and transferring these base control
points.
1.2.2.
Transferred Setting Point
These are the Base Control Points that have been transferred up to the current working level.
4
1.2.3. Bench Mark
This is the reduced level from which all other level measurements on the site are referenced. It is
usually established by Government or registered surveyors.
1.2.4. Temporary Bench Mark (TBM)
The TBM is the reduced level mark for the current working level.
They should be established on every working floor using steel pins or nails secured into the
concrete floor slab. They are transferred each time from the previous TBM.
They are the reference level for the given floor, they are used as the bench mark against which the
kicker level and concrete level surveys are carried out.
Please refer to attached textbook extract for examples of typical TBM’s.
1.3 Day to Day Detail Survey
The day to day detail survey means the setting out measuring and leveling carried out on every
floor cycle to ensure that the formwork has been set accurately to line, level and verticality. You are
reminded that if the MFE Formwork is to achieve the accuracy that it is capable of the Day to Day
Detail survey control must be carried out accurately for every concrete pour.
The definitions and explanations of typical terms used on a project are given below. Please also
refer to the simplified plan of setting out principals attached at the back of this section.
1.3.1 300mm Offset Line
This is the setting out line that is “snapped” onto the concrete surface.
It is offset normally 300mm from the internal face of the external wall. It is to set and check the
formwork alignment and to carry out the deviation survey.
1.3.2 Concrete Level Survey.
By this we mean the reduced level of the concrete surface along the entire plan length of the yet to
be erected inside face wall formwork again the most critical points being the corners.
The level survey is taken from the TBM for the current floor and is carried out immediately after
concreting the floor so that analysis of the levels and corrective action, if necessary, can be carried
out prior to the next erection of formwork.
5
1.3.3 Kicker Level Survey
This means the reduced level of the “kicker” along the entire plan length of the yet to be erected
outside face of the external walls. The level survey is taken from the TBM for the current floor and
is carried out immediately after concreting the floor so that analysis of levels and adjustment of
kickers, if necessary, can be carried out prior to the next erection of formwork. Again the most
critical points are the corners.
1.3.4 Deviation Survey.
This is a measure of the horizontal deviation of the as built plan position of each wall relative to the
design position. The survey is also carried out after concreting and immediately after the new plan
alignments for the walls have been marked out on the current slab. The most critical points are
again at the corners.
1.3.5
Analysis of Survey Results
The results of the deviation survey, kicker level and concrete level survey have to be analyzed for
each and every floor. Corrective action (concrete chipping) and or adjustment (by packing or
sometimes lowering in the case of the kickers) has to be carried out before commencing erecting of
the formwork for the current floor.
1.3.6 Method of Adjustment
The principal control and adjustment for vertical alignment of the building using MFE formwork is
through the kicker and concrete levels. Further adjustment if necessary can be made with props
but this should be kept to a minimum as it can distort the formwork.
The principal measure of achieved vertical alignment is the deviation survey.
The assumption made is that when fully pinned and wedged the formwork forms a relatively rigid
frame. It follows that packing (using plywood shims) or lowering (by chipping concrete or by using
the slotted holes in the kicker) one side of the frame will push in or pull out the plan position of the
top edge of the frame, please refer to attached sketch “Control and Adjustment of Vertical
Alignment by Packing”.
The deviation survey must therefore be analyzed first, any locations that show the wall leaning out,
will require the packing of the kicker in the same plan location to bring in the wall on the next cast.
As a general rule the maximum of 6mm to be adjusted over one floor. If the deviation reports,
shows a deviation from plumb in two directions then this should be improved over two floors, one
for each direction.
The kicker level and concrete level surveys are reviewed together with the deviation report. A
comparison of the information from both sources allows cross checking of the results. At the same
time the level surveys will tell you if the floor to floor heights are being maintained or are they
creeping up, which sometimes happens with grout build up between Wall and T panels i.e. 2 -
3mm per floor over 10no floors can develop a creep of + 25mm.
6
Concrete up to (+ 6mm high) is acceptable, above 6mm must be chipped to the correct level.
Any low points should be packed to the correct level.
Note: in certain cases it is good practice to mark ( + ) plus or ( - ) minus as the survey is being
carried out. This eliminates unnecessary circulation of paper and the supervisor can
identify at a glance the adjustment work that is necessary.
Any high points on the kicker level survey will need to be adjusted downward by means of the
26mm slotted hole in the kicker that allows for this kind of adjustment.
1.3.7 Deviation Survey Not Making Sense?
If for some reason the deviation survey results do not make sense it is easy to check and confirm
the results over a number of floors by hanging a plumb bob down the 2 or 3 floors and checking the
deviation of the concrete face between floors.
This method of check can confirm if the survey results are correct or incorrect.
1.3.8
Plumb and Alignment of Walls
Once wall formwork has been fixed in position every wall must be checked for verticality (deviation
correction allowed for) using a plumb bob for trueness of alignment using a string line.
See “Everyday Survey Check” sketch attached at back of this section.
Optional for this scope of work is the use of a Laser Instrument which is, highly recommended
allowing you to check alignment or verticality of the Formwork at any location with one setting of the
Instrument.
More efficiency and better accuracy is the advantage by using such an instrument.
1.4
Keeping of Survey Records
The survey record for the kicker level, concrete level and deviation report must be kept in the job
file for every single pour. This is a must and the responsible engineer must ensure the record is
kept and maintained.
1.4.1
First Time Setup
It is very beneficial to spend additional time with the setup of the first pour. Even if it takes an extra
day to get the level and alignment correct this will pay big dividends later on in the project by way of
better quality, easier cycle and less remedial works.
Tip: It is always easier to pack than to chip concrete or lower the kickers so set the first time
concrete pour at - 10mm to give yourselves more adjustment to play with.
7
1.5 Miscellaneous
- Simplified Plan of Marking Out Principles
- Control and Adjustment of Vertical Alignment by Packing
- Everyday Survey Check
- Bench Marks
- Plumbing
- Buildings and Tall Structures
8
9
10
11
Bench Marks
Each side should have a primary bench mark which may be :
• A convenient nearby Ordnance Bench Mark
• Referenced to an Ordnance Bench Mark
• Referenced to a given level on existing works
The supervising authority should specify which is to apply. If an Ordnance
Bench Mark is to be used but which one has not been specified, obtain the
current local list of Ordnance Bench Marks (see Appendix C) and agree
which to use with the supervising authority.
In addition to the primary bench mark, it will be necessary to set up
secondary bench marks unless all leveling can conveniently be referred to
the primary bench mark. Secondary bench marks are commonly called
temporary bench marks (TBMs).
To ensure accurate primary and temporary bench marks :
• Establish primary bench mark
*
from the agreed Ordnance
Bench Mark or from existing works and agree level in writing
with the supervising authority.
• Plan positions of TBMs in good time, taking account of
temporary and permanent works (all points of the works
should, where possible be within 40 m of a TBM)
• Verify the levels of previously established TBMs by leveling
from the primary bench mark.
• Establish TBMs not more than 80 m apart. Closing error to
primary bench mark must not exceed 5 mm.
• Use existing permanent features for establishing bench marks
whenever possible (see illustrations)
• Where no permanent feature is available for a bench mark,
establish it in firm ground and mark as shown in the
illustration.
• Protect bench marks from site traffic as necessary
• If assumed datum has been used for schema, as shown on
contract drawings, check with the supervising authority that
this datum may be used.
• Record position, reference number, level and date last
checked of each TBM and the primary bench mark on the site
plan.
• Display copy of site plan or list of bench marks with details in
site offices
• Check levels of TBMs at regular intervals*
• Report any apparent disturbance of TBMs
• Update displayed plan list of TBMs
• Transfer levels from TBMs to permanent works as soon as
practicable
• Remove redundant TBMs
*BRE leveling station can conveniently be used. See Cheney.J.E. in
Bibliography
*Warning: Earthworks and ground settlement, heave, expansion or
contraction can affect TBMs
12
Plumbing
Plumbing of modest accuracy can be achieved with a good quality 1-m spirit
level, but other methods must be used as the height and or need for precision
increases.
Use of plum bob
In the example shown, a freshly concreted wall is checked for verticality. The
plumb bob is suspended from a piece of timber nailed to the top of the
formwork and shielded from the wind or immersed in a pail of oil or water.
Offsets from the back of the form are measured at top and bottom with due
allowance for any steps or tapers in the wall. Any necessary adjustments are
made with a push-pull prop.
Use of theodolite
The formwork for a tall column form is being plumbed in the example. A
theodolite is set up on a plane parallel but offset to one face and sighted on
suitable offset marks at the top. (Observe both edges to check on twist.) Similar
observations are made on the bottom of the form. Any discrepancy in verticality
(mean of observations on left and right face) is read at the bottom for
convenience and the column form adjusted. The whole process is then
repeated for the adjacent face.
Sighting at a steep angle above the horizontal is facilitated by using a diagonal
eyepiece.
Note : The theodolite must be some distance from the column for accuracy
this may be impossible on a cramped site.
Use of optical plumbing instrument
The operation is relatively simple as follows:-
• Set up and level instrument over ground station
• Sight down and center over ground station
• Sight up (through second telescope or by operating prism
mechanism) onto target and mark a defined point
• Turn instrument through 90
0
,180
0
and 270
0
in horizontal plane to
define three further points
• Intersection of diagonals joining four points lies on vertical line
through ground point
Optical plumbing is particularly useful for ensuring the accuracy of lift shafts,
slip formed structures and climbing forms. The example shows the use of an
optical plumbing instrument in a lift shaft using perspex targets fixed at the top
levels. At least three ground stations should be used to check for possible
twisting.
Use of lasers
Lasers can be used to define a vertical line or plane.
13
Buildings: tall structures
Plumbing
The primary instruments for plumbing are:
• Plumb bob
• Theologize
• Optical plumbing instrument
The principles of use are described under Plumbing.
Verticality and twist
Tall structures must be checked for verticality and twist. This is best achieved
by plumbing up or down from four points.
Rectangular structures
The use of an optical plumbing instrument to control the verticality of a multi-
storey building is illustrated.
Within multi-storey buildings, the plumbing of list shafts is particularly critical
operation because the installation tolerances are small. Four setting-out points
should be established at the base of the lift shaft such that the vertical lines
through them will not be obstructed by formwork or scaffolding. Plumbing can
be from top to base using plumb bobs or from base to top using an optical
plumbing instrument. The latter is preferable if a plumb bob would be disturbed
by winds. See illustration under Plumbing.
Tapered structures
To plumb a tapered column or similar structure:
• Set out orthogonal center-lines on the base
• Plumb from top corners (plumb bob or theodolite)
• Check equality of offsets on all four sides
If the structure narrows toward the top, it will be necessary to cantilever out
from the top of the formwork to fix plumb bobs.
Height and level
Floor-to-floor dimensions are controlled by a weighted steel tape measuring
each time from a datum at the base of the structure. Each floor is then provided
with datum marks in key positions from which to transfer levels on each floor.
The base datum level should be set in a location which allows unrestricted
taping to roof level. If a tower crane is used,`` a tape can conveniently be fixed
to the mast (see illustration)
Warning: Errors, apparent or real, can result from differences in
thermal movement of the tape relative to that of the
building particularly if construction spans a number of
seasons.