Pump Commissioning Checklist
Creating a pump commissioning checklist using eAuditor Audits & Inspections can help ensure that all necessary steps are taken to verify the safe and efficient operation of pumps. Below is an example of w...


Slide Content

Pump Commissioning Checklist
A comprehensive guide to ensure safe and efficient pump operation through systematic
verification and testing procedures using eAuditor Audits & Inspections.

Pre-Commissioning: Documentation
Documentation & Physical
Inspection
Documentation Requirements
Before beginning commissioning, ensure all
critical documentation is available and
accessible to the team.
•Installation manual available
•Operation manual available
•Commissioning procedure document
document available
Physical Inspection
Verify proper installation and physical
condition of the pump system.
•Pump correctly installed per
manufacturer's recommendations
•Check alignment of pump and motor
motor
•Proper mounting and leveling verified
•All piping connected properly
•No leaks or visible damages

Electrical & Instrumentation
Verification
1
Electrical Connections
Verify all electrical connections and
ensure motor rating matches power
supply specifications.
2
Control Systems
Check pump control panel wiring and
overload protection settings are
correctly configured.
3
Instrumentation
Confirm pressure gauges, flow meters, and vibration sensors are installed and
functioning properly.

Mechanical Preparation
Lubrication Check
Pump lubricated as per manufacturer
manufacturer specifications with all
mechanical fasteners properly tightened.
tightened.
Coupling Guards
Coupling guards installed securely to
protect moving components during
operation.
Shaft Movement
Pump shaft turns freely without obstructions, ensuring smooth mechanical operation.
operation.

Functional Testing Protocol
01
Priming
Ensure pump is properly primed with suction valve open and air vents clear to
prevent airlock.
02
Start-Up
Test motor starter and verify pump starts without issues. Check initial power
power draw against rated current.
03
Performance Testing
Measure and record flow rate, discharge pressure, vibration levels, and noise
and noise levels. Ensure operation within design parameters.
04
Safety Systems
Verify emergency stop function, test pressure relief valves, check alarm triggers,
alarm triggers, and confirm all interlocks function correctly.

Performance Monitoring
100%
Flow Rate
Design vs actual flow rate measured
measured and documented
PSI
Discharge Pressure
Pressure levels recorded and verified
verified
OK
Vibration Levels
Within acceptable operational limits
limits
dB
Noise Levels
Sound levels meet safety standards
standards

Post-Commissioning & Handover
Final Inspection
•No leaks detected in
in system
•No abnormal
vibrations or sounds
sounds
•All covers and guards
reinstalled
Documentation
•Performance
parameters
documented
•Commissioning report
completed
•Operating manual
provided
•Maintenance schedule
schedule delivered
Training & Handover
Handover
•Operations staff trained
•Maintenance staff
trained
•Emergency procedures
procedures reviewed
reviewed
•Final sign-off obtained

Streamline Your Process with eAuditor
The eAuditor Audits & Inspections platform enables real-time reporting, photo documentation, digital signatures,
and task assignment to streamline the entire commissioning process. Customize this checklist based on your
specific pump type and operational requirements.
Photo Documentation
Capture and attach photos directly to checklist items for comprehensive visual records.
Digital Signatures
Obtain sign-offs electronically from commissioning team and client representatives.
Real-Time Reporting
Generate instant reports and share findings with stakeholders immediately upon completion.