Site Overview Soil testing started on February 18, 2024. 2 Cone Penetration Testing (CPT) equipment units are already on site. 3 Boring equipment already on site BH 4, BH 7, and BH 6 are already done. 3 other borehole is ongoing 7 nos of DCPT already done Topographical survey team already on site WEEK 1 PROGRESS GEOTECHNICAL AND TOPOGRAPHICAL SURVEY
Site Overview DRAINAGE EXISTING AROUND PLAN
Site Overview ORIGINAL GROUND LEVEL NATURAL WATERWAY +37.00 m +37.00 m +40.00 m +25.00 m
Site Overview GRADING CONTOUR
Site Overview DATA COORDINATE AND INVERT LEVEL AROUND PLAN