Strip Raft Foundation Design Issue related to site
Size: 9.34 MB
Language: en
Added: Oct 10, 2024
Slides: 27 pages
Slide Content
Sequence of Work
Case Study – Bukit Raja Phase 13E
Q&A
1)Setting out and leveling.
2)Excavate, install and backfill for underground services.
3)Excavation for strip raft trenches and sand laying.
4)Anti termite treatment.
5)Laying polythene membrane.
6)Reinforcement work and formwork.
7)C.O.W. / Engineer inspection.
8)Concreting.
Next
(Photo)
(Photo)
(Photo)
Problem encounter at site
Strip Raft at drop area
Column position
Reinforcement Lapping
Others
Layout
Photo
Photo
Photo