Turbine Erection Turbine Erection Turbine

gerrard3896 42 views 131 slides Aug 15, 2024
Slide 1
Slide 1 of 131
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66
Slide 67
67
Slide 68
68
Slide 69
69
Slide 70
70
Slide 71
71
Slide 72
72
Slide 73
73
Slide 74
74
Slide 75
75
Slide 76
76
Slide 77
77
Slide 78
78
Slide 79
79
Slide 80
80
Slide 81
81
Slide 82
82
Slide 83
83
Slide 84
84
Slide 85
85
Slide 86
86
Slide 87
87
Slide 88
88
Slide 89
89
Slide 90
90
Slide 91
91
Slide 92
92
Slide 93
93
Slide 94
94
Slide 95
95
Slide 96
96
Slide 97
97
Slide 98
98
Slide 99
99
Slide 100
100
Slide 101
101
Slide 102
102
Slide 103
103
Slide 104
104
Slide 105
105
Slide 106
106
Slide 107
107
Slide 108
108
Slide 109
109
Slide 110
110
Slide 111
111
Slide 112
112
Slide 113
113
Slide 114
114
Slide 115
115
Slide 116
116
Slide 117
117
Slide 118
118
Slide 119
119
Slide 120
120
Slide 121
121
Slide 122
122
Slide 123
123
Slide 124
124
Slide 125
125
Slide 126
126
Slide 127
127
Slide 128
128
Slide 129
129
Slide 130
130
Slide 131
131

About This Presentation

Turbines Erection


Slide Content

26 May 2012 PMI Revision 00 1
TURBINE
ERECTION

26 May 2012 PMI Revision 00 2
HP Turbine
IP Turbine

26 May 2012 PMI Revision 00 3 LP Turbine
Brg

26 May 2012 PMI Revision 00 4
Salient Features Of Turbine Erection
•The fore most activity before taking up the
work is the safe working conditions. Thus
we should first assemble temporary railing
and covers before the start of the job
•Remove construction material & sweep the
foundation well. A proper foundation is of
utmost importance for proper operation of
the machine. A hammer test is to be carried
to detect any flaw / void in the concrete
layer. An ultrasonic testing of the TG deck
should also be carried out if possible. No
looseness below the base plates is
acceptable

26 May 2012 PMI Revision 00 5

26 May 2012 PMI Revision 00 6
Salient Features Of Turbine Erection
(Contd.)
•FOUNDATION CHECK : check accuracy of
size, elevation & axiality of foundation for
conformance the erection drawing
•Check all contact surfaces & openings for
turbine, generator etc., Holes for anchor
bolts. Record final dimensions & make a
protocol
•Check, mark & record main reference point
(absolute floor level) for height against
building wall or foundation pillar

26 May 2012 PMI Revision 00 7

26 May 2012 PMI Revision 00 8

26 May 2012 PMI Revision 00 9

26 May 2012 PMI Revision 00 10
Salient Features Of Turbine Erection
(Contd.)
•BASE PLATES & BEARING PEDESTALS :
LAYING The base plates are designed to transfer
uniformly all forces & vibrations caused by the
operation of the machine.The pedestal are aligned
as the deflection curve of the rotor. The base plates
are leveled with help leveling screws provided below
the base plate

26 May 2012 PMI Revision 00 11

26 May 2012 PMI Revision 00 12

26 May 2012 PMI Revision 00 13
•ANCHOR BOLTS FOR BASE plates :they are long through
bolts for fastening the machine / base plates to the
foundation. They are stretch elongated by specified length
by the help of the bolt tensioning device.Normally diagonally
opposite two bolts are tightened & locked subsequently

Salient Features Of Turbine Erection
(Contd.)

26 May 2012 PMI Revision 00 14

26 May 2012 PMI Revision 00 15

26 May 2012 PMI Revision 00 16
•ANCHOR BOLTS FOR BASE plates :they are long through
bolts for fastening the machine / base plates to the
foundation. They are stretch elongated by specified length
by the help of the bolt tensioning device.Normally diagonally
opposite two bolts are tightened & locked subsequently

Salient Features Of Turbine Erection
(Contd.)

26 May 2012 PMI Revision 00 17

26 May 2012 PMI Revision 00 18

26 May 2012 PMI Revision 00 19

26 May 2012 PMI Revision 00 20

26 May 2012 PMI Revision 00 21

26 May 2012 PMI Revision 00 22

26 May 2012 PMI Revision 00 23

26 May 2012 PMI Revision 00 24

26 May 2012 PMI Revision 00 25

26 May 2012 PMI Revision 00 26

26 May 2012 PMI Revision 00 27
Salient Features Of Turbine Erection
(Contd..)
• ALIGNMENT :align the base plates in zero position
as per the deflection curve. The location is fixed in
longitudinal & transverse axes using plumb & piano
wires.The levels are fixed using the leveling
instrument such as the dumpy level or by scale &
water tubes and final levelling is done by the help of
precision spirit level.Normally bearing pedestal #4
acts as the zero level for the turbine.The base plates
& pedestals are then tightened with spanners for
taking up the grouting

26 May 2012 PMI Revision 00 28

26 May 2012 PMI Revision 00 29
Salient Features Of Turbine Erection
(Contd..)
•Grouting: The grouting of the base plates &
pedestals is carried using shrink free
grouting cement which is intended to ensure
uniform transmission of mass and vibration
of the machine on the foundation.The
activity is carried with great care as the
operation behavior of the machine depends
largely on workmanship while carrying out
the assembly of the load bearing
components
• Bolt tensioning:

26 May 2012 PMI Revision 00 30

26 May 2012 PMI Revision 00 31
Salient Features Of Turbine Erection
(Contd..)

•COUPLINGS: coupling on turbine shaft are generally rigid couplings.
The couplings are used to connect two shafts to form a shaft
assembly. The couplings are so designed so as to perform the
following two functions:
•a)the dimensions & design is such that it is capable of transmission of
all torque encountered during its service.
• b) The coupling must not influence the smooth running of the shaft
assembly

26 May 2012 PMI Revision 00 32

26 May 2012 PMI Revision 00 33

26 May 2012 PMI Revision 00 34

26 May 2012 PMI Revision 00 35

26 May 2012 PMI Revision 00 36

26 May 2012 PMI Revision 00 37
SALIENT FEATURES OF TURBINE ERECTION
(CONT)
•After carrying out the coupling check and
performing the adjustments necessary in the shaft
position, the coupling of the shafts is carried out.
Check for concentricity / radial alignment before
carrying out the the coupling. Also measure the
clearance between the spigot & recess. This
should be well within the specified limit s of
0.08mm or else it shall give a lot of problem while
doing the alignment of the rotors. There after
carry out the axial alignment of the rotors

26 May 2012 PMI Revision 00 38
SALIENT FEATURES OF TURBINE ERECTION
(CONT)
•While coupling ensure the concentricity of the coupling
holes of the two coupling. This shall minimize the
requirement of reaming & honing. A run out check at the
shaft journal is necessary to ensure a good coupling. It
may be noted that even a run out of 0.03mm at journal
area will eventually lead to vibrations of 30 microns.A
higher run out is an indication of improperly connected
coupling. It is imperative to locate the cause of the
improper connection& to eliminate them by appropriate
measures

26 May 2012 PMI Revision 00 39
SALIENT FEATURES OF TURBINE ERECTION
(CONTD..)
•CASING GUIDES: The casing guides are used to link
the turbines & bearing casing together in such away
that turbine casing can expand freely in desired
direction when heated. Prior to installation of the
turbine casing, check their mating surfaces& t6hose of
bearing casing for perfect condition. Permanent casing
guide keys are fixed with required clearance after the
final alignment of rotor and casings. Ensure a thin layer
of molykote on keys while installing. The thickness of
keys& the clearances are to be recorded in the log-
sheets

26 May 2012 PMI Revision 00 40

26 May 2012 PMI Revision 00 41
SALIENT FEATURES OF TURBINE ERECTION
(CONTD..)

•CASING SUPPORTS :The position of all outer casing &
that of inner casing of LP turbine are fixed horizontally
by casing supports. When the turbine casing rests on
the bracket supports the casing is at proper elevation
wrt turbine shaft
•The HP &IP turbine casing are supported in the turbine
axis by two front & two rear bracket supports standing
on the support blocks of the pedestals.The support are
free to slide during the thermal expansion

26 May 2012 PMI Revision 00 42

26 May 2012 PMI Revision 00 43
•BEARING PEDESTALS
The Function of the Bearing Pedestal Is To:
-Support the Rotors
-Connect HP & IP to Form One Unit
-Support HP & IP Turbine Sections
-Center the Turbine Sections
•THRUST BEARING takes care of the uncompensated residual thrust
•FRONT BEARING PEDESTAL houses the main oil pump for lube oil
& control oil. The over speed trip device is also installed in this
pedestal
•AXIAL MOVEMENT : those pedestals which are not fixed point are
designed to take care of thermal expansion. The movement is based
in the length of the turbine section and the casing temperatures
• Setting of spacer bolt clearance
•Checking of radial & axial clearance on the right & left hand sides

26 May 2012 PMI Revision 00 44
The Erection any equipment is a complete & systematic
process which is well conceived before start of the job.
It involves detailed planning about the content and the
scope of work that needs to done. The complete
technical specification of the equipment, its Layout, the
foundations, and the Terminal points have to be defined
before the start of the work. It is well said, that a work
well planned is half done.
Thus while award of the work the complete technical
specifications are frozen in detail during pre award
discussions with the Engineering and the Contract
services.

26 May 2012 PMI Revision 00 45
-The complete erection of a TG is a long drawn process
requiring more that 30 months of work.
-Thus the sequence of supplies and their dates of
dispatches are decided before hand.
-Similarly the dates of readiness of the Foundations is also
decided before hand.
-The Terminal points are also decided before the Final
award of the contract i.e. NTPC scope(Customer Scope)
which generally are free construction power supply, water
supply, Civil foundations, EOT Crane (optional) with
operators, Compressed air, Area lighting, accommodation
land, storage area, DM water etc.
-The rest of the work is in the scope of the equipment
supplier.
- This includes Supply, Storage, Erection, Testing &
Commissioning and Trial operation of the equipment.

26 May 2012 PMI Revision 00 46
Pert Networks
•The contractor is required to submit a PERT
network indication the major mile stone dates
•The three types viz. L1, L2 & L3 networks are
submitted by the contractor which is
reviewed & finalized after incorporating the
comments of the owner. L3 is the complete
detailed network which is normally used at
site for each commitment
•Similarly the supplies are also decided as per
the milestone dates and any slippage from
the committed date is subject to LD to be
levied by the owner. This is levied @ 1/2 %
per week’s delay subject a maximum ceiling
of 5 %

26 May 2012 PMI Revision 00 47
Handing Over Of Fronts
• The fronts are handed over to the contractor after due
checking of the soundness & dimensional check of the elevation
& pocket, insert sizes and their location after a joint protocol
•It is essential to provide weather proof TG hall along with crane
girder which includes side wall cladding, railway siding,
approach ladders / staircase, adjoining floors etc

26 May 2012 PMI Revision 00 48
CONSTRUCTION OF TG DECK
•The TG deck is supported on steel / RCC
columns. A vibration isolation system is
provided on the column to isolate the deck
vibrations from the columns
•After the layout of steel inserts on the form
work/ shuttering, the TG deck is constructed
by a process of non stop casting in order to
provide monolithic structure. The cement
setting is delayed by adding certain additives
to the concrete mixture. The curing is carried
out for a period of 28 days after which it is
released for erection of the equipments

26 May 2012 PMI Revision 00 49

26 May 2012 PMI Revision 00 50

26 May 2012 PMI Revision 00 51

26 May 2012 PMI Revision 00 52

26 May 2012 PMI Revision 00 53

26 May 2012 PMI Revision 00 54

26 May 2012 PMI Revision 00 55

26 May 2012 PMI Revision 00 56

26 May 2012 PMI Revision 00 57

26 May 2012 PMI Revision 00 58

26 May 2012 PMI Revision 00 59

26 May 2012 PMI Revision 00 60

26 May 2012 PMI Revision 00 61

26 May 2012 PMI Revision 00 62

26 May 2012 PMI Revision 00 63

26 May 2012 PMI Revision 00 64

26 May 2012 PMI Revision 00 65

26 May 2012 PMI Revision 00 66

26 May 2012 PMI Revision 00 67

26 May 2012 PMI Revision 00 68

26 May 2012 PMI Revision 00 69

26 May 2012 PMI Revision 00 70

26 May 2012 PMI Revision 00 71

26 May 2012 PMI Revision 00 72

26 May 2012 PMI Revision 00 73

26 May 2012 PMI Revision 00 74

26 May 2012 PMI Revision 00 75

26 May 2012 PMI Revision 00 76

26 May 2012 PMI Revision 00 77

26 May 2012 PMI Revision 00 78

26 May 2012 PMI Revision 00 79

26 May 2012 PMI Revision 00 80

26 May 2012 PMI Revision 00 81

26 May 2012 PMI Revision 00 82

26 May 2012 PMI Revision 00 83

26 May 2012 PMI Revision 00 84

26 May 2012 PMI Revision 00 85

26 May 2012 PMI Revision 00 86

26 May 2012 PMI Revision 00 87

26 May 2012 PMI Revision 00 88

26 May 2012 PMI Revision 00 89

26 May 2012 PMI Revision 00 90

26 May 2012 PMI Revision 00 91

26 May 2012 PMI Revision 00 92

26 May 2012 PMI Revision 00 93

26 May 2012 PMI Revision 00 94

26 May 2012 PMI Revision 00 95

26 May 2012 PMI Revision 00 96

26 May 2012 PMI Revision 00 97

26 May 2012 PMI Revision 00 98

26 May 2012 PMI Revision 00 99

26 May 2012 PMI Revision 00 100

26 May 2012 PMI Revision 00 101

26 May 2012 PMI Revision 00 102

26 May 2012 PMI Revision 00 103

26 May 2012 PMI Revision 00 104

26 May 2012 PMI Revision 00 105

26 May 2012 PMI Revision 00 106

26 May 2012 PMI Revision 00 107

26 May 2012 PMI Revision 00 108

26 May 2012 PMI Revision 00 109

26 May 2012 PMI Revision 00 110

26 May 2012 PMI Revision 00 111

26 May 2012 PMI Revision 00 112

26 May 2012 PMI Revision 00 113

26 May 2012 PMI Revision 00 114

26 May 2012 PMI Revision 00 115

26 May 2012 PMI Revision 00 116

26 May 2012 PMI Revision 00 117

26 May 2012 PMI Revision 00 118

26 May 2012 PMI Revision 00 119

26 May 2012 PMI Revision 00 120

26 May 2012 PMI Revision 00 121

26 May 2012 PMI Revision 00 122

26 May 2012 PMI Revision 00 123

26 May 2012 PMI Revision 00 124

26 May 2012 PMI Revision 00 125

26 May 2012 PMI Revision 00 126

26 May 2012 PMI Revision 00 127

26 May 2012 PMI Revision 00 128

26 May 2012 PMI Revision 00 129

26 May 2012 PMI Revision 00 130

26 May 2012 PMI Revision 00 131
THANK YOU
Tags