Breslow Ice Center Program Statement
8
Probable Project Costs
CONSTRUCTION COSTS
External ServicesGeneral Construction Contractor $8,118,000
Fixed Equipment (Installed by GC) $0
Sitework/Demolition* $0
Utilities Contractor(s) and/or Services $0
Environmental Issues (i.e., asbestos abatement, etc.) $0
Parking/Drives , Roads, & Walks $0
Signage $36,000
Audio Visual Telecommunication $0
Internal Services
Energy Management Control System $370,000
Card Access System $58,000
Fire Alarm System $134,000
Security System $114,000
Other UNL Services $0
Utilities $0
Keying of Doors $2,000
Landscaping $0
Telecommunications $93,000
Fixed Equipment (Purchased/Installed by UNL) $0
Construction Contingency $575,000
Subtotal - Construction Costs $9,500,000
NON-CONSTRUCTION COSTS
Design and
Planning & Program Statement $0
Project Management A/E Basic Services $700,000
A/E Additional Services $0
A/E Reimbursable Expenses $0
Project Management/Construction Inspection (UNL) $204,000
Other Specialty Consultants $0
Equipment
Movable Equipment $479,000
Non Capital Equipment/Supplies $0
Special & Technical Equipment $0
Other
Land Acquisition $0
Artwork $0
Builder's Risk Insurance $0
Moving & Relocation Costs $0
Other Non-construction Costs $42,000
Code Review and Inspection $1,000
Non-construction Contingency $74,000
Subtotal - Non-construction Costs $1,500,000
TOTAL PROBABLE PROJECT COSTS $11,000,000