Which of the following is a basic assumption of PERT? A. Activity completion times are known
with certainty. B. No activity in the network must be repeated. C. There is only one complete
route from the start of a project to the end of a project. D. Only critical path activities in the
network must b...


Slide Content

Which of the following is a basic assumption of PERT? A. Activity completion times are known
with certainty. B. No activity in the network must be repeated. C. There is only one complete
route from the start of a project to the end of a project. D. Only critical path activities in the
network must be performed.