TENDER – PROCEDURE TO BE FOLLOWED TENDER – PROCEDURE TO BE FOLLOWED
ACCORDING TO GFR 2017ACCORDING TO GFR 2017
Tender work flow 1
Tender ProceduresTender Procedures
Tender work flow 2
•(i) Upto Rs. 25,000/-
•Through any of the available suppliers on the meeting the
requisite quality, specifications and delivery period of the
internal committee
Tender work flow 3
(ii) Above Rs.25, 000 and upto Rs. 5,00,000/-
•Through the available sellers having lowest price.
•Choose from three different suppliers and least bidder may be
considered.(i.e. L1)
Tender work flow 4
(iii) Above Rs.5, 00,000/-
•Through the suppliers having lowest price, meeting the requisite
quality, specifications and delivery period after mandatorily
obtaining bids.
•Rule 155 - Purchase of goods by Purchase Committee
Procurement ProcedureProcurement Procedure
As per GFR, the procurement should be made (Rule 144 & 155)
I
II
III
IV
Detailed Work flow of the Tender PurchasingDetailed Work flow of the Tender Purchasing
Tender work flow 6
Tender work flow 7
Tender work flow 8
Tender work flow 9
Framing of Local purchase committeeFraming of Local purchase committee
•Framing Local Purchase Committee consisting of three
members of an appropriate level as decided by the Head of
the Department (Rule No: 155 )
Tender work flow 10
Important Points toTenderImportant Points toTender
•Preparing technical specification for approved items.
•Preparing document as per GFR 2017
(See Rule 136,139,144, 149,154, 155,158,159,160 and 161,162,163,164 respectively which are related
to tender and procurements)
•Adding condition relevant to purchase.
•Security deposits will be as per GFR. (See Rule 170 and 171 respectively)
•Advance Payment to Supplier, if any (See Rule 172)
•All procurement should be in compliance of Rule 173 of GFR
Tender work flow 11