NIGEL A. JOHN Project Coordinator, NAWASA PRESENTATION PROCUREMENT FAIR SOUTHERN ST. GEORGE WATER SUPPLY EXPANSION PROJECT GRENADA
What We Do Overview of the Project(s) Procurement Activities Works Goods Consultancy Services PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024 TABLE OF CONTENTS
WHAT WE DO... PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024 Increase availability of a safely managed drinking water service, and increase the capacity for integrated waste resources management, within NAWASA’s Southern Water Supply Network in Grenada.
OVERVIEW OF THE PROJECT(S) Executing Unit: National Water and Sewerage Authority (NAWASA) Grant Amount: US$20,772,700 Sector: Water and Sanitation Components: Project preparation (feasibility study and detailed designs) Infrastructure Works (Lots 1 and 2) Capacity building Training farmers in climate smart agriculture techniques Training communities in communications and water conservation Institutional strengthening Development of an IT plan for NAWASA PRESENTATION TITLE & DATE PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024
PROCUREMENT ACTIVITIES PRESENTATION TITLE & DATE Infrastructure Works: Lot 1 – Concord to St. George’s: Repair of existing dam (weir) on the Black Bay River Upgrade to the Concord water treatment plant, increasing daily output from about 600,000 gallons to about 1,000,000 gallons Construction of two new potable water storage tanks (total 500,000 gals) Upgrade/repair of almost 2 miles of water mains Installation of measurement and control devices (meteorological and hydraulic) WORKS PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024
PROCUREMENT ACTIVITIES PRESENTATION TITLE & DATE Infrastructure Works: Lot 2 – St. George’s to Point Saline: Upgrade/repair of about 7 miles of water mains Upgrade/repair of about 1.25 miles of sewer mains Upgrade of 3 sewer lift stations WORKS PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024
PROCUREMENT ACTIVITIES PRESENTATION TITLE & DATE For Water Supply: Water treatment plant components 4,865 lengths of ductile iron pipes 270 lengths of high density polyethylene (HDPE) pipes 105 lengths of galvanized iron pipes Pipe fittings and connectors Fire hydrants Valves and meters For Sewerage: 705 lengths of PVC pipes for gravity mains 40 lengths of ductile iron pipes for force mains GOODS PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024
PROCUREMENT ACTIVITIES PRESENTATION TITLE & DATE Consultancy services for the development and implementation of gender responsive and socially inclusive communications and water conservation training Consultancy services for the development of an information technology (IT) plan for NAWASA CONSULTANCY SERVICES PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024
The General Procurement Notice is at https://www.caribank.org/work-with-us/procurement/procurement-notices/southern-st-georges-water-supply-expansion-project The extant Procurement Plan is at https://drive.google.com/file/d/1oheaVvaNjBiBj7nyOoVoonWG_QbvfyC0/view?usp=drive_link PRESENTATION TITLE & DATE PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024
POINT OF CONTACT PROCUREMENT FAIR | SAINT LUCIA | SEPTEMBER 4 & 5, 2024 NAME: Nigel A. John POSITION: Project Coordinator EMAIL: [email protected] TELEPHONE: (473) 458-8306