3249_Rws & s Kalahandi-3_MRM_May'24.pptx

abhisheksharma120000 16 views 26 slides Jul 03, 2024
Slide 1
Slide 1 of 26
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26

About This Presentation

Monthly review meeting of rwss kalahandi 3 project.


Slide Content

Execution of Individual Rural Piped Water Supply Projects pertaining to Koksara & Th Rampur Block of Kalahandi District including “five years Operation & Maintenance” on EPC Mode M/s Megha Engineering and Infrastructures Limited 3249 – RWS&S Kalahandi-3, Odisha

Agreement Value : 248.91 Crores (Execution –215.66, O&M – 33.26) Blocks Covered : Koksara & Th Rampur Block Project Start Date : 04.11.2022 Project End Date : 05.11.2024 Operation & Maintenance : 05 Years 3249 – RWS&S Kalahandi-3, Odisha

Design & Drawings Description Koksara Th Rampur Intake well cum Pump house Submitted   Submitted GAD Compliance submitted RWS EIC Compliance submitted RWS EIC Structural Design Vetted Drawing Submitted to ACE office Observation to be submitted WaterTreatment Plant 15.70 MLD 7.30 MLD Process Design & Layout Approved Approved Structural Designs of WTP 16/22 recieved 12/22 received

Design & Drawings of Koksara & Thuamul Rampur Pipe Line Description Koksara Block Remarks Th Rampur Block Remarks PSR Approved   Approved   Raw Water Main 5.17/15.60 Kms 35% Completed 0.060/7.5 Kms 0.8 % Completed Approved Approved

BLOCK MAY-24 JUNE-24 Target Achievement Target KOKSARA Excavation & Pcc Completed Raft & First Lift wall TH.RAMPUR To be Approved from EIC INTAKE WELL

Structure MAY-24 JUNE-24 Target Achievement Target Guard Room Brick work & Plastering Completed Paintings & Finishing Works Staff Quarters Brick work & Plastering, Completed Paintings & Finishing Works Adminstrative Building Brick work & Plastering. Completed Paintings & Finishing Works Office cum lab buildings Brick work & Plastering. Completed Plastering & Finishing Works AERATOR Up to tie Beam Completed Column & Shaft Up to bottom slab CLF-1 O uter ring Wall Raft Wall Second Lift & central shaft second lift Completed Up to Lcb bottom CLF-2 Outer ring Wall Raft Wall Second Lift & central shaft second lift Completed Up to Lcb bottom Wash water Tank Up to FRB Bottom level Completed Bottom Dome Water Treatment Plant-Koksara

Water Treatment Plant- Koksara Structure MAY-24 JUNE-24 Target Achievement Target Wash Water Recycling Tank Up to head roof slab. Completed Bricks works & plastering. Chemical House Excavation Completed Pcc & Raft Centrifuge Building Up to Plinth Beam Completed Floor Slab Thickned Sludge Sump Roof beam & Slab Completed Bricks works & Plastering Chlorine House Excavation to be started Sludge Thickner-1 Top slab Tank completed Completed Launder Beam & Walk way Sludge Thickner-2 Top slab Tank completed Completed Launder Beam & Walk way Flash Mixer-1&2 Excavation to be Started CWR To be Vetted Filter House To be Vetted CWPH To be Vetted

ESR’S-36 nos Description MAY - 2024 Cumulative Completed up to MAY 24 Balance up to JUNE - 24 JUNE 2024 Target Achieved Target Excavation 1 no 2 nos 6 n os 30 nos 5 nos PCC 2 nos 2 nos 4 nos 32 nos 3 nos Raft 1 no 1 no 4 nos 32 nos 3 nos Completion of 50% Staging Height - - - 36 nos 3 nos Completion of 100% Staging Height - - - 36 nos 2 nos Bottom Dome - - - 36 nos - Container Wall - - - 36 nos - Top Dome - - - 36 nos -

Structure MAY-24 JUNE -24 Target Achievement Target Guard Room Column, Roof Beam Completed Up to Slab & Roof Beam Staff Quarters Column, Roof Beam Completed Adminstrative Building Column ,Roof Beam Completed Office cum lab buildings Column, Roof Beam Completed Compound wall 200 m bricks wall completed& 100 m plastering Completed 50 m bricks work & 100 m plastering ,copping Aerator Excavation Completed Pcc & Raft CLF-1 Pcc & Raft Completed Outer ring wall Pcc & Raft CLF-2 Pcc & Raft Completed Outer ring wall Pcc & Raft Water Treatment Plant- Thuamul Rampur

Structure MAY-24 JUNE-24 Target Achievement Target Wash water Recycling Excavation Completed Pcc & Raft Centrifuge Building Excavation Chemical House Excavation Chlorine House Excavation Sludge Well Excavation Completed Pcc & Raft Flash Mixer-1&2 To be Approved from EIC CWR To be Approved from EIC Wash Water Tank To be Approved from EIC Filter House To be Approved from EIC CWPH To be Vetted Water Treatment Plant- Thuamul Rampur

DI 355.93 34.40 2.00 - 6.33 28.07 5.00 HDPE 894.24 784.39 15.00 21.21 78.70 705.69 15.00 Total 1250.17 818.79 17.00 21.21 85.03 733.76 20.00 Pipeline Laying Description Scope (A) Pipes Received (B) May-2024 Cumulative Laid (C) Balance to be laid (B-C) JUNE ’24 Target Achieved Target In Kms

S.No Machinery Type No Percentage of utilization Remarks 1 TRAILER 1 80.83% 2 BOLERO 1 56.10% 3 EXCAVATOR -140 1 72.54% 4 EXCAVATOR -200 1 75.54% 5 JCB 1 85% UTILIZATION REPORT –MAJOR HIRE MACHINERY

S.No Machinery Type No Percentage of utilization Remarks 1 MAHINDRA BOLERO 1 124.26% 2 TATA AJAX FIORI 1 12.83 % 3 SCHWING STETTER 1 50.5% 4 MAHINDRA BOLERO 1 163.28% UTILIZATION REPORT –MAJOR OWN MACHINERY

INTAKE WELL KOKSARA BLOCK

15.70 MLD KOKSARA WATER TREATMENT PLANT GUARD ROOM ADMIN BUILDING STAFF QUARTERS OFFICE CUM LAB BUILDING

15.70 MLD KOKSARA WATER TREATMENT PLANT WASH WATER RECYCLING TANK THICKNED SLUDGE SUMP

15.70 MLD KOKSARA WATER TREATMENT PLANT WASH WATER TANK SLUDGE THICKNER

15.70 MLD KOKSARA WATER TREATMENT PLANT CENTRIFUDGE BUILDING SLUDGE THICKNER

KOKSARA ESLR : PHUFGAON OHT LADUGAON OHT

CLEAR WATER RISING MAIN – PIPE LINE KOKSARA BLOCK

DISTRIBUTION– PIPE LINE KOKSARA BLOCK

7.30 MLD THUAMUL RAMPUR WATER TREATMENT PLANT ADMIN BUILDING STAFF QUATERS OFFICE CUM LAB BUILDING

7.30 MLD THUAMUL RAMPUR WATER TREATMENT PLANT CLF-1 CLF-2

7.30 MLD THUAMUL RAMPUR WATER TREATMENT PLANT WASH WATER RECYCLING TANK COMPOUND WALL

DISTRIBUTION– PIPE LINE TH.RAMPUR BLOCK