Monthly review meeting of rwss kalahandi 3 project.
Size: 35.41 MB
Language: en
Added: Jul 03, 2024
Slides: 26 pages
Slide Content
Execution of Individual Rural Piped Water Supply Projects pertaining to Koksara & Th Rampur Block of Kalahandi District including “five years Operation & Maintenance” on EPC Mode M/s Megha Engineering and Infrastructures Limited 3249 – RWS&S Kalahandi-3, Odisha
Agreement Value : 248.91 Crores (Execution –215.66, O&M – 33.26) Blocks Covered : Koksara & Th Rampur Block Project Start Date : 04.11.2022 Project End Date : 05.11.2024 Operation & Maintenance : 05 Years 3249 – RWS&S Kalahandi-3, Odisha
Design & Drawings Description Koksara Th Rampur Intake well cum Pump house Submitted Submitted GAD Compliance submitted RWS EIC Compliance submitted RWS EIC Structural Design Vetted Drawing Submitted to ACE office Observation to be submitted WaterTreatment Plant 15.70 MLD 7.30 MLD Process Design & Layout Approved Approved Structural Designs of WTP 16/22 recieved 12/22 received
Design & Drawings of Koksara & Thuamul Rampur Pipe Line Description Koksara Block Remarks Th Rampur Block Remarks PSR Approved Approved Raw Water Main 5.17/15.60 Kms 35% Completed 0.060/7.5 Kms 0.8 % Completed Approved Approved
BLOCK MAY-24 JUNE-24 Target Achievement Target KOKSARA Excavation & Pcc Completed Raft & First Lift wall TH.RAMPUR To be Approved from EIC INTAKE WELL
Structure MAY-24 JUNE-24 Target Achievement Target Guard Room Brick work & Plastering Completed Paintings & Finishing Works Staff Quarters Brick work & Plastering, Completed Paintings & Finishing Works Adminstrative Building Brick work & Plastering. Completed Paintings & Finishing Works Office cum lab buildings Brick work & Plastering. Completed Plastering & Finishing Works AERATOR Up to tie Beam Completed Column & Shaft Up to bottom slab CLF-1 O uter ring Wall Raft Wall Second Lift & central shaft second lift Completed Up to Lcb bottom CLF-2 Outer ring Wall Raft Wall Second Lift & central shaft second lift Completed Up to Lcb bottom Wash water Tank Up to FRB Bottom level Completed Bottom Dome Water Treatment Plant-Koksara
Water Treatment Plant- Koksara Structure MAY-24 JUNE-24 Target Achievement Target Wash Water Recycling Tank Up to head roof slab. Completed Bricks works & plastering. Chemical House Excavation Completed Pcc & Raft Centrifuge Building Up to Plinth Beam Completed Floor Slab Thickned Sludge Sump Roof beam & Slab Completed Bricks works & Plastering Chlorine House Excavation to be started Sludge Thickner-1 Top slab Tank completed Completed Launder Beam & Walk way Sludge Thickner-2 Top slab Tank completed Completed Launder Beam & Walk way Flash Mixer-1&2 Excavation to be Started CWR To be Vetted Filter House To be Vetted CWPH To be Vetted
ESR’S-36 nos Description MAY - 2024 Cumulative Completed up to MAY 24 Balance up to JUNE - 24 JUNE 2024 Target Achieved Target Excavation 1 no 2 nos 6 n os 30 nos 5 nos PCC 2 nos 2 nos 4 nos 32 nos 3 nos Raft 1 no 1 no 4 nos 32 nos 3 nos Completion of 50% Staging Height - - - 36 nos 3 nos Completion of 100% Staging Height - - - 36 nos 2 nos Bottom Dome - - - 36 nos - Container Wall - - - 36 nos - Top Dome - - - 36 nos -
Structure MAY-24 JUNE -24 Target Achievement Target Guard Room Column, Roof Beam Completed Up to Slab & Roof Beam Staff Quarters Column, Roof Beam Completed Adminstrative Building Column ,Roof Beam Completed Office cum lab buildings Column, Roof Beam Completed Compound wall 200 m bricks wall completed& 100 m plastering Completed 50 m bricks work & 100 m plastering ,copping Aerator Excavation Completed Pcc & Raft CLF-1 Pcc & Raft Completed Outer ring wall Pcc & Raft CLF-2 Pcc & Raft Completed Outer ring wall Pcc & Raft Water Treatment Plant- Thuamul Rampur
Structure MAY-24 JUNE-24 Target Achievement Target Wash water Recycling Excavation Completed Pcc & Raft Centrifuge Building Excavation Chemical House Excavation Chlorine House Excavation Sludge Well Excavation Completed Pcc & Raft Flash Mixer-1&2 To be Approved from EIC CWR To be Approved from EIC Wash Water Tank To be Approved from EIC Filter House To be Approved from EIC CWPH To be Vetted Water Treatment Plant- Thuamul Rampur
DI 355.93 34.40 2.00 - 6.33 28.07 5.00 HDPE 894.24 784.39 15.00 21.21 78.70 705.69 15.00 Total 1250.17 818.79 17.00 21.21 85.03 733.76 20.00 Pipeline Laying Description Scope (A) Pipes Received (B) May-2024 Cumulative Laid (C) Balance to be laid (B-C) JUNE ’24 Target Achieved Target In Kms
S.No Machinery Type No Percentage of utilization Remarks 1 TRAILER 1 80.83% 2 BOLERO 1 56.10% 3 EXCAVATOR -140 1 72.54% 4 EXCAVATOR -200 1 75.54% 5 JCB 1 85% UTILIZATION REPORT –MAJOR HIRE MACHINERY
S.No Machinery Type No Percentage of utilization Remarks 1 MAHINDRA BOLERO 1 124.26% 2 TATA AJAX FIORI 1 12.83 % 3 SCHWING STETTER 1 50.5% 4 MAHINDRA BOLERO 1 163.28% UTILIZATION REPORT –MAJOR OWN MACHINERY
INTAKE WELL KOKSARA BLOCK
15.70 MLD KOKSARA WATER TREATMENT PLANT GUARD ROOM ADMIN BUILDING STAFF QUARTERS OFFICE CUM LAB BUILDING
15.70 MLD KOKSARA WATER TREATMENT PLANT WASH WATER RECYCLING TANK THICKNED SLUDGE SUMP
15.70 MLD KOKSARA WATER TREATMENT PLANT WASH WATER TANK SLUDGE THICKNER
15.70 MLD KOKSARA WATER TREATMENT PLANT CENTRIFUDGE BUILDING SLUDGE THICKNER
KOKSARA ESLR : PHUFGAON OHT LADUGAON OHT
CLEAR WATER RISING MAIN – PIPE LINE KOKSARA BLOCK
DISTRIBUTION– PIPE LINE KOKSARA BLOCK
7.30 MLD THUAMUL RAMPUR WATER TREATMENT PLANT ADMIN BUILDING STAFF QUATERS OFFICE CUM LAB BUILDING
7.30 MLD THUAMUL RAMPUR WATER TREATMENT PLANT CLF-1 CLF-2
7.30 MLD THUAMUL RAMPUR WATER TREATMENT PLANT WASH WATER RECYCLING TANK COMPOUND WALL