5.Foamed-Bitumen-Stabilised-Pavements.ppt

TevitaToloi3 17 views 36 slides Aug 31, 2025
Slide 1
Slide 1 of 36
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36

About This Presentation

Mix Design and field svaluation of FBSP


Slide Content

research | consulting | technology
www.arrb.com.au Advancing safety and efficiency in transport through knowledge
TT1825 Mix design and field evaluation of foamed
bitumen stabilised pavements
December 2014

Need for cost-effective pavement
rehabilitation treatments
2

Increasing use of foamed bitumen to stabilise
unbound granular bases of rural highways
3
Commonly use
about 3% bitumen
and 1.5% quicklime

National procedures for design of FBS
treatments
•project commenced in July 2012
•two progress reports published
•completion June 2016
4
•mix design
•distress modes
•improved Austroads
thickness design procedures

Collaboration is maximising research
outcomes
•research being guided by a Working Group comprising road
agencies and industry
•extensive collaborative of road agencies, industry and
ARRB
•laboratory testing by two experienced labs, Downer and
TMR
•road agencies and industries are contributing through the
construction of under-designed pavts
5

Foamed bitumen (FB) mix design
•Existing mix design process in need of improvement
6

Requirements for untreated material
•requirements for grading and plasticity of the untreated
material, generally accepted
•not the focus of research
7

Amount of bitumen and lime determined from
indirect tensile modulus testing
8

Department of Transport and Main Roads
(TMR) Queensland modulus requirements
•Austroads building on TMR experience over the last 15
years
•TMR lab mixes are compacted into 150 mm diameter
moulds and 10 kg Marshall hammer
9

TMR mix requirements
•initial modulus 3 hours after lab compaction used as a
indicator of early-life rut resistance
•also undertake wheel tracking
10

TMR mix requirements
•bitumen and lime content adjusted to satisfy requirements
for cured dry and wet modulus
11

Issues being addressed in the research project
Need to harmonise test methods throughout Australia
•various compaction methods in use (e.g. gyratory, standard
Marshall, large Marshall)
•recently agreed that the interim Austroads method would be
large Marshall based on TMR experience
•various mixing and compacting moisture contents being
used
–70% standard Proctor OMC untreated material
–85% modified Proctor OMC untreated material
•some labs using quicklime other hydrated lime
12

Effect of mixing moisture
13

Research will lead to Austroads test method
and mix design procedure
14

Issues being addressed in the research project
The most challenging issue is validation of usefulness of lab
moduli in materials characterisation/mix design.
Need to link lab moduli to field performance
•usefulness of initial moduli in evaluating early-life rut
resistance
•usefulness in cured dry and wet moduli in predicting long
term field performance
15

16
The purpose of this project is:
•to improve and harmonise national mix design procedures
for bituminous stabilised materials
•to identify distress modes of bituminous stabilised
pavements from the trial sites.
•to improve the Austroads thickness procedures.
Purpose

Field performance
•to address the project objectives data on the field
performance of FBS pavement is required
•to obtain performance data during the research project (4
years), a number of under-designed pavements have been
constructed and are being monitored
•to date we have five trials
–Kwinana Freeway Perth (2010)
–Port Wakefield Road South Australia (2011)
–Kewdale Road, Welshpool Perth (2011)
–Calder Freeway, Woodend Victoria (early 2013)
–Newell Highway Bellata, NSW (late 2013)
17

Summary of trials
Site Surface FBS
thickness
(mm)
Nominal
bitumen
content
(%)
Nominal
lime content
(%)
Kwinana FreewayOGA on
DGA
150 mm 3.5% 0.8%
hydrated lime
Port Wakefield
road
seal 150 mm and
200 mm
3% 1%
hydrated lime
Kewdale road DGA 100 mm and
150 mm
3% 0.8%
quicklime
Calder Freeway seal 150 mm 3.5% 1.5%
quicklime
Newell Highway seal 175 mm 3.5% 1.5%
quicklime
18

Kwinana Freeway after FBS placement before
asphalt and GRS placed, 2010
19

Port Wakefield Road 2011
20

Calder Freeway Victoria under construction
March 2013
21

Newell Highway 2013
22

Sites tested during construction and
monitored for performance
23

Proposed trial on Western Highway Victoria
Heavily trafficked road about 1-2 million ESA per year
200 mm depth FBS, anticipate fatigue after 2-3 years
Two binder contents 2.7% and 3.5%
24

25

FINDINGS TO DATE
26

Ravelling of Calder Freeway when pavement
was opened to traffic the day of construction
•ravelling next day
•may have been
affected by adding
additional material
late in construction to
adjust level to match
adjacent lane
27

Cracking has been observed
•at commencement of trial doubts whether fatigue cracking
was a distress mode for FBS
•to date observed cracking at 2 of the 3 trial sites with seal
surfaces
28
Port Wakefield Road, 18 months Calder Freeway, 18 months

Only one instance of rutting, when an old
asphalt patch was inadvertently stabilised
29

Foamed bitumen and lime stabilisation
produces high modulus in situ
With high temp in
summer construction
enabled rapid water
loss, FBS cores can
be taken 7 days after
construction
30

Modulus varies with markedly depth/density
•in situ modulus can decrease significantly with depth due to
lower densities
31

Back-calculated moduli being monitored to
predict time to fatigue damage
32

Issues being addressed to improve thickness
design
FBS design modulus
•currently values of 2000 – 3000 MPa are commonly used
•need improve process to determine the flexural design
modulus from the lab IDT moduli
33

Data being obtained to improve determination of
design modulus
•relationship between moduli of lab specimens and moduli of
early-life field cores
•relationship to correct the lab moduli to the field densities
•relationship to adjust IDT modulus to a flexural modulus
34

Issues being addressed to improve thickness
design
•currently fatigue relationship used is that for asphalt with a
reduced volume of binder
•given material contains 1-2% lime and the bitumen
distribution is different from asphalt this relationships needs
to be validated
35

Summary
•research is being undertaken to improve Austroads
procedures for foamed bitumen stabilisaton:
–mix design
–thickness
•strong collaboration and involvement of road agencies and
industry will maximise research outcomes
•progress report published in 2014
•project is due for completion in June 2016
36
Tags