It's an analysis of building project management
Size: 972.56 KB
Language: en
Added: Sep 16, 2025
Slides: 53 pages
Slide Content
Civil and Environmental Engineering CE 660 1 Advanced Project Planning and Management CASE STUDY: PROJECT PLANNING AND SCHEDULING OF A TWO-STORIED RCC RESIDENTIAL BUILDING PRESENTED TO Professor Md Shoaib Chowdhury Ph.D., P.E., Fellow ASCE, Member Sigma Xi DATE OF PRESENTATION 15 AUGUST, 2025
LIST OF CONTENTS SL Description 1 INTRODUCTION (PROJECT DESCRIPTION, OBJECTIVES AND SCOPE) 2 WORK BREAKDOWN STRUCTURE (WBS) 3 ACTIVITY DEFINITION AND SEQUENCING 4 DURATION AND COST ESTIMATION 5 PROJECT SCHEDULING USING MS PROJECT 6 CONCLUSION
NAME OF THE STUDENTS AND ID nAME id SAMIHA HASAN ID# 2517317065 NAWSHAD ASEF ID#2517034065 TANIMA BINTE IQBAL ID# 2517266665 MOHAMMAD MAIDUR RAHMAN ID# 2517029065 MOHAMMAD MURAD HOSSAIN ID# 2517157665 PRODIP KUMAR SORKER ID# 2517389065
INTRODUCTION (PROJECT DESCRIPTION,OBJECTIVES AND SCOPE)
PROJECT OBJECTIVES The main objective of this project is to successfully plan, design, and construct a two-storied reinforced cement concrete (RCC) residential building in Dhaka, Bangladesh. The project aims to deliver a safe, durable, cost-effective, and aesthetically pleasing residential structure that meets the modern housing needs of an urban family. Key goals include: Ensuring timely completion of construction activities within a span of 10 months (approximately 300 days). Maintaining the total project cost within the allocated budget of BDT 36 million. Achieving quality construction outcomes by using best practices in materials, workmanship, and planning.
PROJECT OBJECTIVES(Cont’d) Ensuring full compliance with relevant regulatory authorities, specifically adhering to RAJUK (Rajdhani Unnayan Kartripakkha) and BNBC (Bangladesh National Building Code) standards. Incorporating sustainable construction methods and the use of locally available materials to promote environmental responsibility.
SCOPE OF THE PROJECT The scope of the project encompasses the complete development of a two-storied residential structure including civil, structural, electrical, plumbing, and finishing works. Key inclusions: Total construction area of approximately 7,600 square feet, split into two floors (~3,663 sq. ft. each). Layout and provision for all essential household spaces: multiple bedrooms, bathrooms, a kitchen, living room, dining space, and service areas. Execution of civil and structural works, including foundations, superstructure (RCC frame), and masonry.
SCOPE OF THE PROJECT(Cont’d) Installation of MEP (Mechanical, Electrical, and Plumbing) services, including modern wiring, plumbing lines, water supply, and sanitary fittings. Full interior and exterior finishing, including tiling, flooring, painting, door/window fittings, and false ceiling (if required). External development, such as boundary walls, main gate, landscaping, and driveway construction. Preparation of planning documents, including a Work Breakdown Structure (WBS), Gantt chart, bar chart, and cost estimation plan. Ensuring the handover process, which includes final inspection and client approval.
MAJOR COMPONENTS OF THE PROJECT The project has been broken down into the following major components to ensure systematic implementation: Site Preparation Substructure (Foundation Works) Superstructure (RCC Frame) Masonry and Plastering Flooring and Tiling Doors and Windows Plumbing and Sanitary Installations Electrical Wiring and Fixtures
MAJOR COMPONENTS OF THE PROJECT (Cont’d) Painting and Finishing Works External Development
ASSUMPTION To ensure smooth project execution, the following assumptions have been made: The project site has been legally acquired, and there are no land disputes or legal hindrances. Soil conditions are stable and verified through geotechnical testing, ensuring foundation design safety. Necessary approvals and permits (RAJUK, BNBC, utility services) will be obtained without significant delay. Labor availability is consistent throughout the project period, and required skill levels are accessible.
ASSUMPTION (Cont’d) All construction materials (cement, steel, bricks, tiles, etc.) will be locally available and delivered on time. No major design modifications will be requested after construction begins, helping avoid scope creep. Adequate financial resources will be available throughout the project to avoid funding delays. Weather conditions will permit uninterrupted outdoor construction work for most of the year.
CONSTRAINTS While planning and executing the project, several limitations must be acknowledged: Time Constraint: The construction must be completed within a strict 10-month timeline, including planning, approvals, and execution. Budget Constraint: The total cost is capped at BDT 36 million, requiring tight cost monitoring and budget control throughout the project. Regulatory Compliance: Adherence to RAJUK guidelines and BNBC codes is mandatory, limiting flexibility in design or materials. Urban Site Challenges: Limited space for material storage, machinery movement, and waste management due to the congested Dhaka location.
CONSTRAINTS (Cont’d) Weather Dependence: Monsoon season in Bangladesh may cause work delays, especially during excavation, concreting, or external development. Labor and Resource Risk: Potential risks of labor strikes, shortage of skilled workforce, or material price fluctuations. Client Change Requests: Any late-stage design or material change requests can disrupt the construction schedule and increase costs. Safety Regulations: All work must comply with worker safety norms and on-site accident prevention protocols.
WORK BREAKDOWN STRUCTURE (WBS)
The Work Breakdown Structure (WBS) is developed by systematically breaking down the overall project scope into smaller, manageable components. It starts with a clear understanding of the scope, as defined in the project scope statement. Major deliverables or phases are first identified, forming the top level of the WBS. It is typically presented in a hierarchical format, such as an indented list or tree diagram.
BENEFITS OF WBS Breaks down the overall project scope into smaller, manageable components. Begins with a clear understanding of the project scope statement. Identifies major deliverables or phases at the top level. Presented in hierarchical format (indented list or tree diagram). Clarifies what needs to be done by an organization or subcontractor. Facilitates responsibility assignment. Enables effective progress tracking
Drawbacks OF WBS Requires significant effort to create for complex project. Too many small tasks can make management cumbersome. . Difficult to adjust when project scope changes. . Poorly defined tasks can cause confusion and rework . May overlook process-oriented activities . Inaccurate scope leads to flawed WBS . Lacks timelines, dependencies, and resources without other tools.
ACTIVITY DEFINITION AND SEQUENCING
INTRODUCTION A project activity is a distinct task or work function where a particular worker or crew of workers completes a specific item of work within a prescribed time frame. The “job” must be measurable for each project activity. The Work Breakdown Structure (WBS) for the two-storied RCC residential building is divided into four major components—Substructure, Superstructure, MEP (Mechanical, Electrical, Plumbing), and Finishing Work —each of which can be further broken down into progressively detailed levels.
Level 1: Project Level 2: Major Component Level 3: Work Package Level 4: Detailed Activities Two-Storied RCC Residential Building 1. Substructure Clearing & Layout Site cleaning Boundary marking Grid layout Earth Excavation Mobilize equipment Mark excavation zones Excavate to required depth Dispose of soil Footing Prepare base Place reinforcement Pour concrete Curing Short Column Formwork Reinforcement Concrete casting Grade Beam Shuttering Reinforcement Pouring and curing
Level 1: Project Level 2: Major Component Level 3: Work Package Level 4: Detailed Activities Two-Storied RCC Residential Building 3. MEP Electrical Conduits Conduit Layout Conduit Installation Cable Pulling Switchboard Installation Lighting Fixture Installation Testing and Commissioning Plumbing Pipe Layout Pipe Installation Fixture Installation Pressure Testing Final Commissioning HVAC Installation of grills Installation of aluminium frame Exhaust fan installation
Level 1: Project Level 2: Major Component Level 3: Work Package Level 4: Detailed Activities Two-Storied RCC Residential Building 4. Finishing Work Masonry & Plaster Brickwork Internal and external plaster Door & Window Frame installation Panel fitting Painting Surface preparation Primer and coats Exterior Concrete Driveways and walkways Floor Finish Tiling or marble work
LOGICAL DEPENDENCIES Finish to Start (FS) – Task B cannot start until Task A finishes.One task must finish before the next starts. (Most common) Start to Start (SS) – Task B cannot start until Task A starts. One task must finish before the next starts. Finish to Finish (FF) – Task B cannot finish until Task A finishes. Start to Finish (SF) – Task B cannot finish until Task A starts (rare)
LOGICAL DEPENDENCIES
LOGICAL DEPENDENCIES Predecessor Activity Successor Activity Dependency Type Explanation Site Cleaning Boundary Marking FS Boundary marking starts after site is cleaned Boundary Marking Grid Layout FS Grid layout begins after boundary is marked Grid Layout Earth Excavation FS Excavation zones are defined by grid Earth Excavation Footing FS Footing starts after excavation is complete Footing Short Column FS Columns cast after footing Short Column Grade Beam FS Grade beam connects short columns Grade Beam 1st Floor Column FS Superstructure begins after substructure 1st Floor Column Slab (1st Floor) FS Slab requires column support
LOGICAL DEPENDENCIES Predecessor Activity Successor Activity Dependency Type Explanation Slab (1st Floor) Brickwork (Ground Floor) FS Slab provides stability for masonry scaffolding Slab (1st Floor) 2nd Floor Column FS Next level columns depend on slab 2nd Floor Column Slab (2nd Floor) FS Slab cast after column Slab (2nd Floor) Brickwork (1st Floor) FS Same logic as ground floor masonry Brickwork (each floor) Electrical Conduits SS Conduits can start as brickwork progresses Brickwork (each floor) Plumbing SS Plumbing layout follows wall construction Slab (2nd Floor) & Brickwork HVAC FS HVAC needs structural and wall completion
LOGICAL DEPENDENCIES Predecessor Activity Successor Activity Dependency Type Explanation Electrical & Plumbing Internal Plaster FS Plastering starts after MEP rough-ins Brickwork (all floors) External Plaster FS External plaster follows masonry Internal Plaster Door & Window Installation FS Frames installed after wall finishing Door & Window + Plaster Painting FS Surface prep and painting follow finishing Internal Plaster Floor Finish FS Tiling after plastering Grade Beam & Site Clearance Exterior Concrete FS Driveways done near project completion
DURATION AND COST ESTIMATION
ACTIVITY DURATION TABLE Sl. No. Activity Description Duration Start Time End Time Dependencies 1 Excavation for Foundation 7 days Day 01 Day 17 None 2 PCC and Footing Reinforcement + Casting 10 days Day 18 Day 27 Activity 1 3 4 Column up to Plinth Level 7 days Day 28 Day 34 Activity 2 Plinth Beam & Backfilling 7 days Day 35 Day 41 Activity 3 5 Ground Floor Slab Shuttering, Reinforcement & Casting 15 days Day 42 Day 56 Activity 4 6 7 Column up to First Floor 10 days Day 57 Day 66 Activity 5 First Floor Slab Work 15 days Day 67 Day 81 Activity 6 8 Second Floor Column & Roof Beam 10 days Day 82 Day 91 Activity 7 9 Roof Slab + Parapet Wall 10 days Day 92 Day 101 Activity 8 10 Brickwork (All Floors) 20 days Day 85 Day 104 Can run in parallel with 6, 7, 8 11 Internal Plastering 15 days Day 105 Day 119 Activity 10 After major brickwork 12 External Plastering 10 days Day 120 Day 129 Activity 11: After internal plastering starts
ACTIVITY DURATION TABLE Sl. No. Activity Description Duration Start Time End Time Dependencies 13 Floor Tiling (All floors) 15 days Day 130 Day 144 Activity 11 After Internal plastering 14 Door & Window Frame Fixing 10 days Day 130 Day 139 Activity 12 can run in parallel with tiling, i.e., Activity 13 15 Electrical Wiring (Concealed) 10 days Day 105 Day 114 With plastering, i.e., Activity 11, 12 16 Plumbing (Concealed) 10 days Day 115 Day 124 With wiring, i.e., Activity 15 17 Painting (Internal and External) 15 days Day 145 Day 159 Activity 13 After plastering & tiling 18 Door Shutter, Window Glass Fixing 7 days Day 160 Day 166 Activity 17: After painting the base coat 19 Electrical Fixtures Installation 5 days Day 167 Day 171 After painting, i.e., Activity 17 20 Plumbing Fixtures Installation 5 days Day 172 Day 176 After tiling, i.e., Activity 13 21 Sanitary & Bathroom Fixtures 7 days Day 184 Day 190 After floor tiles + plumbing, i.e., Activity 13, 16 22 Final Paint Touch‐up 5 days Day 191 Day 195 After all internal work, i.e., Activity 13 to 21 23 Site Cleaning & Handover 5 days Day 196 Day 200 Activity 21, All works completed
COST ESTIMATE TABLE
PROJECT SCHEDULING USING MS PROJECT/EXCEL SPREADSHEET
PROJECT BAR CHART
PROJECT GANTT CHART
CPM NETWORK WITH FLOAT
NETWORK DIAGRAM
CONCLUSION
PROJECT RISKS Weather delays: Heavy monsoon rains in Dhaka can significantly delay excavation and concreting. Material price fluctuation: Unforeseen increases in the cost of steel, cement, or bricks can impact the budget. Labor shortages: A lack of skilled workers or strikes can cause project delays. Design changes : Changes requested by the client during construction can disrupt the schedule and increase costs.
CONCLUSION This project report outlines a comprehensive plan for the construction of a two-storied RCC residential building. By adhering to the proposed schedule, managing the budget, and proactively mitigating identified risks, the project can be completed within the 10-month timeframe and the ৳36 million budget, delivering a quality residential building in Dhaka, Bangladesh. We converted this plan into contract documents, and we prepared a detailed BOQ, obtained vendor quotes, performed geotechnical investigation, and finalize the structural and MEP designs (to align quantities with cost and schedule precisely. The attached schedule, Gantt chart, and bar chart provide concrete tools for daily/weekly tracking and risk monitoring.
APPENDICES
LIST OF APPENDICES APPENDIX A: WBS (Image/Diagram) APPENDIX B: Bar chart, CPM Network Diagram (Showing floats, critical activities, critical paths etc.) APPENDIX C: MS Project Gantt Chart Screenshot