HIRA AMBREEN & SEERAT MUSKAN EE-2030-0126 ; EE-2030-0134 Community Park Renovation Project Presented By Department of Electrical & Computer Engineering

Project Charter

Project Title: Community Park Renovation Project Authorization Date: 26th-March-2024 Start Date: 01-April-2024 End Date: 17-March-2025 Key Milestones Kickoff Meeting and Planning Playground Renovation Seating Area Enhancement Pathway and Walkway Repair Landscaping Lighting Installation Final Inspection and Handover Budget Information: Step into a realm of transformation guided by key milestones and a 1 million budget. Project Manager: Success Criteria : Completing tasks within budget, enhancing park aesthetics, and fostering positive community feedback, ensuring our efforts leave a lasting impact on all who enjoy the park.

Duration Tasks 3 Weeks Gather stakeholders for a kickoff meeting to discuss project objectives, scope, and expectations. 2 Weeks Develop a detailed project plan including tasks, timeline, and budget allocation. 6 Weeks Assess current playground equipment and determine replacement needs. 3 Weeks Procure new playground equipment and schedule installation. 4 Weeks Design benches and picnic tables for the seating area. 3 Weeks Procure materials and install benches and picnic tables.

5 Weeks Survey existing pathways and identify repair needs. 4 Weeks Schedule repair activities and ensure safe access throughout the park. 4 Weeks Design a landscaping plan to improve greenery and aesthetics. 2 Weeks Procure plant materials and plant greenery according to the plan. 4 Weeks Design lighting layout for safety and ambiance. 4 Weeks Procure lighting fixtures and install them strategically throughout the park. 1 Week Conduct a final inspection of all renovated areas to ensure quality and compliance.

Conti… Roles & Responsibilities Name Roles Position Contact Information Project Manager Stakeholder Contractor

Work Breakdown Structure

Activity-On-Node AON Diagram

Slack Time Analysis

Gantt Chart

Conclusion & Next steps Conclusion: Aimed at revitalizing the park and enhancing its functionality and aesthetics. Meticulous planning and execution have laid a solid foundation. Collaborative efforts of stakeholders have been instrumental. Next Steps: Continue project execution according to established timeline and milestones. Monitor progress and address any challenges promptly. Maintain open communication with stakeholders. Conduct periodic reviews to evaluate progress. Prepare for final inspection and handover of the renovated park.