Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity

akhileshshukla963 17,496 views 121 slides Jun 28, 2018
Slide 1
Slide 1 of 121
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66
Slide 67
67
Slide 68
68
Slide 69
69
Slide 70
70
Slide 71
71
Slide 72
72
Slide 73
73
Slide 74
74
Slide 75
75
Slide 76
76
Slide 77
77
Slide 78
78
Slide 79
79
Slide 80
80
Slide 81
81
Slide 82
82
Slide 83
83
Slide 84
84
Slide 85
85
Slide 86
86
Slide 87
87
Slide 88
88
Slide 89
89
Slide 90
90
Slide 91
91
Slide 92
92
Slide 93
93
Slide 94
94
Slide 95
95
Slide 96
96
Slide 97
97
Slide 98
98
Slide 99
99
Slide 100
100
Slide 101
101
Slide 102
102
Slide 103
103
Slide 104
104
Slide 105
105
Slide 106
106
Slide 107
107
Slide 108
108
Slide 109
109
Slide 110
110
Slide 111
111
Slide 112
112
Slide 113
113
Slide 114
114
Slide 115
115
Slide 116
116
Slide 117
117
Slide 118
118
Slide 119
119
Slide 120
120
Slide 121
121

About This Presentation

Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id [email protected]


Slide Content

Introduction of METRO RAIL in INDIA Rapid transits in India consist of Metro, Monorails and light rail system How it Began India’s 1 st and Asia’s 5 th Metro rail was introduced in Kolkata in 1984 Delhi Metro was India's first modern metro which began its operation in 2002. Rapid Metro Rail Gurgaon, which started operations in November 2013, is India's first privately owned & operated metro.

Why is it Needed ? Unprecedented growth of personal Vehicle Growing Traffic Congestion Air pollution and traffic accidents has become a major concern To avoid congestion at Peak hour Time saving and Reduced fuel consumption

METRO RAIL in INDIA Unprecedented growth of personal Vehicle Growing Traffic Congestion Air pollution and traffic accidents has become a major concern To avoid congestion at Peak hour Time saving and Reduced fuel consumption

METRO RAIL in INDIA Existing Metro Rail in INDIA Delhi Metro Kolkata Metro Mumbai Metro Chennai Metro Bangalore Metro Jaipur Metro Lucknow Metro Hyderabad Metro Kochi Metro Noida Metro Under construction and proposed Metro Rail in India Ahmedabad Metro Pune Metro Nagpur Metro Indore Metro Bhopal Metro 5) Kanpur Metro

Type of metro Type of Metro Elevated Metro Underground Metro On Grade

ELEVATED METRO

Basic Sequence of Activities For Elevated Metro (Viaduct) Casting of superstructure Segments & parapet Stacking and Transportation of segments Casting Yard Set Up

Basic Sequence of Activities For Elevated Metro (Station) Casting of superstructure I -Girder Stacking and Transportation of segments Casting Yard Set Up

P n P n+1 Span Length Number of Segments 37 m 13 34 m 12 31 m 11 28 m 10 25 m 9 22 m 8 S7C 3000 S6D 3000 S6U 3000 S5D 3000 S4D 3000 S3D 3000 S2D 3000 S5U 3000 S4U 3000 S3U 3000 S2U 3000 S1U 1975 S1D 1975 Segment Codes Standard Span Length S1U S2U S3U S4U S5U S6U S7C S6D S5D S4D S3D S2D S1D 37 √ √ √ √ √ √ √ √ √ √ √ √ √ 34 √ √ √ √ √ √ x √ √ √ √ √ √ 31 √ √ √ √ √ x √ x √ √ √ √ √ 28 √ √ √ √ √ x x x √ √ √ √ √ 25 √ √ √ √ x x √ x x √ √ √ √ 22 √ √ √ √ x x x x x √ √ √ √ Casting Yard – Segment Details Average 15 Days will be required to cast segments for 37m span.

Casting Sequence Segment Id Average Cummulative days 1 S7C 1 2 S1U 2 3 S6U 4 4 S6D 5 5 S2U 6 6 S5U 7 7 S5D 8 8 S4U 9 9 S1D 10 10 S4D 11 11 S2D 12 12 S3U 14 13 S3D 15 Match Casting Activity Short bed Long bed

Pier Pile Pile Cap Crash Barrier Pier Cap Upstand/Pedestal Segments (Span) Sub Structure Super Structure Seismic arrester of span Details of Structure

Pile 3 4 1 2 Average Time Required for Casting of one Pile will be 12hrs . Average Time take to cast pile group will be 5 Days. Piling Sequence Piling Activity

P - 1 P – 2 P -3 P -4 Pile cap shutter 1 Pile cap shutter 2 Pile Cap Reinforcement (3 Days) Average Time take to cast pile cap will be 12 Days. After 1 day Resources movement Pile Cap Pile Pile cap Activity

P -1 P -2 P -3 P -4 Pier shutter 1 Pier shutter 1 Pier shutter 2 Pier shutter 3 Pier shutter 1 Pier shutter 2 Pier shutter 3 Pier shutter 2 Pier shutter 3 Pier Pile Cap Pile After 24 Hrs. After 1 day Pier Activity Resources movement Average Time Cycle for Pier 5 days Pier P -5 P -6

Pier Cap Preparation of reinforcement Cage (3 Days) Pedestal And shear key Casting (18 Hrs ) After 21 day Average Time cycle for pier cap is 8 days Pier Cap Activity

dry matching (8 hrs ) and wet matching (10 hrs ) including cutting and treading and lowering of span. Launching Sequence Activity

DETAILS OF LAUNCHING GIRDER

COMPONENTS OF LAUNCHING GIRDER MAIN BOX GIRDER FRONT SUPOORT MIDDLE SUPPORT REAR SUPPORT REAR TROLLEY SLIDER BEAM COUNTER WEIGHT FIXED MOUNTED HOIST PLATFORM/ WALK WAYS

Maximum height of Front support : 6220mm Minimum height of Front support : 4230mm FRONT SUPPORT TOP BEAM TOP VERTICAL LEG BOTTOM BEAM TELESCOPIC LEG GENERAL ARRANGEMENT OF FRONT SUPPORT

TYPICAL ISOMETRIC VIEW OF FRONT SUPPORT

MIDDLE SUPPORT Main beam Bracket of main beam Launching bearing Longitudinal side bearing Knuckle bearing Cradle TYPICAL ISOMETRIC VIEW OF MIDDLE SUPPORT

Rear support is more or less same replica of middle support accept longitudinal pushing assembly is not provided in this support. REAR SUPPORT TYPICAL ISOMETRIC VIEW OF REAR SUPPORT

REAR TROLLEY TYPICAL ISOMETRIC VIEW OF REAR TROLLEY REAR TROLLEY IS POSITIONED AT 4500MM FROM THE REAR END OF THE MAIN GIRDER S8 AND PROVIDES SUPPORTS DURING LONGITUDINAL AUTO LAUNCHING .

SLIDER BEAMS TYPICAL FRONT VIEW OF SLIDER BEAM TYPICAL ISOMETRIC VIEW OF SLIDER BEAM Slider beams are independent assembly of two built up I sections connected together with steel diaphragms

SCHEME FOR AUTO-LAUNCHING FOR SPANs UPTO 37m Span

Step:1 Erect all the segments of the span and do final pre-stressing as per specification in drawing.

Step:2 Ensure that erection of all span is completed in all aspects . Release all suspenders from erected span and lower the span on temporary bearing placed on pier cap.

Step:3 Bring all the sliders to the rear end.

Step:4 Release the middle support from the span and w ith the help of slider beam shift the middle support nearer to the front support on segment S1 as shown in drawing.

Step:5 Activate the jacks of middle support on segment S1 and anchor with the span .

Step:6 Release the Rear support from the span and with the help of slider beam shift the rear support to the erected span of segment S1.

Step:7 Activate the jacks of rear support on segment S1 and anchor with the span .

Step:8 Now move both the sliders back to the rear trolley .

Step:9 Ensure that middle and rear support are firmly anchored with the span. Now close the telescopic leg of front support so that all load transferred to the middle and rear support.

Step:10 Ensure all the supports firmly anchored with the span and make sure that rear trolley free from anchorage from the span.

Step:11 Ensure that all supports firmly anchored with super structure. Start Auto-launching and auto launch the launching girder by 1200mm. Check that all supports are firmly anchored or not.

Step:12 Now again start auto launching until rear trolley come nearer to the rear support.

Step:13 With the help of slider beam move rear support near to the middle support and anchored it with the span.

Step:14 Continue auto-launching till front support reaches next pier cap location..

Step:15 Open the telescopic leg of front support and activate it. Anchor firmly with pier cap.

ERECTION SCHEME FOR 37M SPAN

Step: 1 Make sure that launching Girder is ready for erection of new span and lifting of segments. Now move the sliding towards the next span to be erected near front support as shown.

Step:2 Move the trailer below the lifting hoist.

Step:3 Pull down the lifting beam.

Step:4 Fix the lifting beam and temporary pre-stressing beam on segment S1. Now lift the pier segment S1 with the help of lifting hoist. Now move the slider in position to lift the S1 segment.

Step:5 Connect the S1 with the slider beam and move it nearer to the middle support .

Step:7 Move S2 nearer to the segment S1.

Step:8 Move S3 nearer to the segment S2.

Step:9 Move S4 nearer to the segment S3 .

Step:10 Move S5 nearer to the segment S4.

Step:11 Move S6 nearer to the segment S5.

Step:11 Move S7 nearer to the segment S6.

Step:11 Move all the sliders towards Segment S7.

Step:11 Move all the sliders towards Segment S7.

Step:11 Now lift the segment S3 upwards then other segments for adjustment of all the segments in fixed length.

Step:11 Now lift the segment S3 upwards then other segments for adjustment of all the segments for dry matching.

Step:11 Now move remaining sliders towards segment S3.

Step:11 Now move remaining sliders towards segment S3.

Step: Lift the segment S5 and move it near the segment S6.Now same do same procedure for segment S4.

Step:17 Now do dry/wet matching and temporary pre-stressing and follow the procedure for final pre-stressing as per specification given in drawing.

Concourse Level Track Level Platform Level Road Level CANTILEVER TYPE STATION Bored Cast-in situ Piles Pile Cap Pier Crash Barrier Pier Head at CL Staircase Precast I-girders Deck slab at CL Pier Heads at PL & TL Pre-cast I-girders PEB Roofing Deck Slab at PL & TL 61

Concourse Level Track Level Platform Level Road Level PORTAL TYPE STATION Bored Cast-in situ Piles Pile Cap Pier Crash Barrier Portal Beam at CL Staircase Precast I-girders Deck slab at CL Pier Heads at PL & TL Pre-cast I-girders PEB Roofing Deck Slab at PL & TL 62

Underground Metro Tunnel Cut and Cover Bored Tunnel Station Top –Down Bottom-up

Stage – 03. Stop End inserted in both end of the trench. Stop End Stop End Installation Stage – 05. Concrete placing through tremie pipe as polymer slurry is displaced. Panel Concreting ` DIAPHRAGM WALL CONSTRUCTION METHODOLOGY.

Excavation Methods Bottom Up Method: Slabs will be laid from Bottom to Top such that Base slab will be constructed first Base slab Concourse Slab Roof Slab GL GL D-wall Top Down Method: Slabs will be laid from Top to Bottom such that Top slab will be constructed first Top slab Concourse Slab Base Slab GL GL D-wall 65

Completion of all D wall Works Start excavation for 1 st layer D wall King Post Bottom Up Method : Launching shaft Construction (Stage 1)

Excavation upto 1 m Below Temporary Sturt -1 From one side D wall King Post Bottom Up Method : Launching shaft Construction (Stage 1)

50 T Gantry D Wall Road Waler Start Fixing brackets form one side Start Fixing of Waler form one side Bottom Up Method : Launching shaft Construction (Stage 2)

50 T Gantry D Wall Waler Road Erection of Diagonal Strut Start Fixing Diagonal Strut Start Fixing of Waler for Straight Strut Bottom Up Method : Launching shaft Construction (Stage 2)

Start Fixing Straight Strut Start Fixing of Waler for Diagonal Strut 50 T Gantry D Wall Diagonal Strut Road Erection of Straight Strut Erection of Waler for Diagonal strut Bottom Up Method : Launching shaft Construction (Stage 2)

Completion of Strut erection Start on 1 st Layer Excavation for 2 nd layer Diagonal Strut Road Straight Strut Erection of Diagonal strut D Wall 50 T Gantry Bottom Up Method : Launching shaft Construction (Stage 2)

Erection of 2 nd Strut Layer Excavation upto 1 m Below Temporary Sturt -2 From one side D wall King Post Bottom Up Method : Launching shaft Construction (Stage 3 )

Start Fixing of Brackets from One side Start Fixing of Waler from One side Erection of 2 nd Strut Layer Excavation upto 1 m Below Temporary Sturt – 3 From one side King Post D wall Bottom Up Method : Launching shaft Construction (Stage 4)

Start Fixing of Brackets from One side Start Fixing of Waler from One side Erection of 3 rd Strut Layer Excavation upto 1 m Below Temporary Sturt – 4 From one side King Post D wall Bottom Up Method : Launching shaft Construction (Stage 5)

Start Fixing of Brackets from One side Start Fixing of Waler from One side Erection of 4 th Strut Layer Excavation upto Base Slab Level From one side King Post D wall Bottom Up Method : Launching shaft Construction (Stage 6)

Excavation upto Base Slab Level Levelling Surface for Base slab construction King Post D wall Bottom Up Method : Launching shaft Construction (Stage 7)

Casting of Base Slab Attain required strength for Base slab Removal of 4 th Level strut Cast reaction Frame support for Pedestal Handover the shaft to TBM operations Base Slab King Post D wall Bottom Up Method : Launching shaft Construction (Stage 8)

Station Construction Top – Down Method

Top Down Method : Station Construction (Stage 1 )- Excavation still Roof Slab

Top Down Method : Station Construction (Stage 2)- Casting of Roof Slab and Excavation till Roof Slab

Top Down Method : Station Construction (Stage 3 )-Excavation for Concourse Slab

Top Down Method : Station Construction (Stage 4)-Excavation for Concourse Slab and Completion of Roof Slab

Top Down Method : Station Construction (Stage 5 )- Casting Concourse Slab

Top Down Method : Station Construction (Stage 6)- Excavation of Base slab and Casting of Concourse Slab

Top Down Method : Station Construction (Stage 7 )- Completion of concourse and Casting of Base Slab

Top Down Method : Station Construction (Stage 8)- Casting of Base Slab

Station Construction Bottom – Up Method

Bottom UP Method : Station Construction (Stage 1 )- Excavation still Roof Slab and Fixing of Strut

Bottom UP Method : Station Construction (Stage 2)- Excavation still Concourse Slab and Fixing of Strut

Bottom UP Method : Station Construction (Stage 3 )- Excavation still Base Slab and Casting of Base Slab

Bottom UP Method : Station Construction (Stage 4 )- Casting of Concousre Slab

Bottom UP Method : Station Construction (Stage 5 )- Casting of Roof Slab

Bottom UP Method : Station Construction (Stage 6)- Backfill

Cut and Cover Method

Tunnel Segment

TUNNEL SEGMENT CYCLE TIME Sr.No Activity Duration In Minutes Start Finish 1 Mould Opening 30 30 2 Cleaning of Mould 40 30 70 3 Placing of reinforcement 20 70 90 4 Insert Fixing 10 90 100 5 Checking of reinforcement 20 100 120 6 Concrete Pouring 20 120 140 7 Steam Curing 420 140 560 8 Removal of Segment 40 560 600   In Minutes 600       In Hours 10     Average Time take for 1 Tunnel Segment will be 10 Hrs

TUNNEL SEGMENT CYCLE TIME (6 Nos of Mould) Sr.No Activity Mould 1 Mould 2 Mould3 Mould 4 Mould 5 Mould 6 1 Mould Opening 30 30 30 30 30 30   Duration ( In Minutes) 0-30 30-60 60-90 0-30 30-60 60-90 2 Cleaning of Mould 40 40 40 40 40 40   Duration ( In Minutes) 30-70 70-110 110-150 30-70 70-110 110-150 3 Placing of reinforcement 20 20 20 20 20 20   Duration ( In Minutes) 70-90 110-130 150-170 70-90 110-130 150-170 4 Insert Fixing 10 10 10 10 10 10   Duration ( In Minutes) 90-100 130-140 170-180 90-100 130-140 170-180 5 Checking of reinforcement 20 20 20 20 20 20   Duration ( In Minutes) 100-120 140-160 180-200 100-120 140-160 180-200 6 Concrete Pouring 20 20 20 20 20 20   Duration ( In Minutes) 120-140 160-180 200-220 120-140 160-180 200-220 7 Steam Curing 420 420 420 420 420 420   Duration ( In Minutes) 140-560 180-600 240-640 140-560 180-600 240-640 8 Removal of Segment 40 40 40 40 40 40   Duration ( In Minutes) 560-600 600-640 640-680 560-600 600-640 640-680 Total Time for Casting ( For each Mould) 600 Min 10 Hours Total Time for casting (For 6 Mould) 680 Min 11.33 Hours Total Repeatative Ring casting in 22 hours 22/11.33 1.94 Repition No.Of working Days 26   Total no of casting by each mould each month 50 Rings   Total Number of Casting 302 Rings   Average.Casting Per Day 12 Rings 10 Rings Consider in DWP

8 hr for Concreting to Harden Lift Precast segment out of Mould After 8 hours

Type of Tunnel Boring Machine EPB Machine Slurry Machine EPB and Slurry Machine

Parts of TBM machine

Working of TBM

Ahmedabad Metro

PROJECT ALIGNMENT (UG2)

Package: UG2 – 4.102 Km (11620.302m  7518.161 m) Shafts Launching Shaft - Top Down (40 m length) Stations Ghee Kanta - Top Down (170 m length) Shahpur - Top Down (260 m length) Tunnel & Cross Passage TBM Tunnel - 3300 m length × 2 Cross Passage - 13 Nos. Ramp West Ramp - Bottom Up (286 m length) Entry & Exit Entry / Exits - 07 Nos. (3 nos. – Ghee Kanta, 4 nos. – Shahpur) SCOPE OF WORKS (UG2) 116

Description Launching Shaft Intermediate Shaft Ghee Kanta Shahpur Arrival Shaft Construction Method Bottom Up Bottom Up Top Down Top Down Bottom Up Length (Outer Length) 40 30 170 260 25 Width (C/C) 25 25 22 22 22 Depth (Base Slab) 20 21 19.5 18.5 18.5 No of Entrances -- -- 3 4 -- Ancillary Building -- -- 1 1 -- SCOPE OF WORKS (UG2) : GENERAL DETAIL

TBM PATH ( UG2) TBM 2 TBM 1 TBM 3 Tunneling Configuration

Completion of all D wall Works Start excavation for 1 st layer Excavation upto 1 m Below Temporary Sturt -1 From one side Start Fixing brackets form one side Start Fixing of Waler form one side THALTEJ GAM (WEST) VASTRAL GAM (EAST) LAUNCHING SHAFT SEQUENCE

CONSTRUCTION SEQUENCE OF GHEEKANTA