Ser Description Status Remarks 1 Proc of Hydraulic & Disc Cutter for Salt Rg Completed 2 Hiring of Hy Crane for Salt Rg ‘’ 3 Proc of used tyres for Salt Rg ‘’ 4 Repair of Steel Pedestrian Br (Br 5 & 9) ‘’ 5 Pasting of reflective sheets on ambs ‘’ 6 Instl of trackers on ambs ‘’ 7 Retrofitting of damaged pier RCC Br at RD 344 ‘’ 8 Repositioning of anti glare sheets ‘’ 9 Winter Uniforms for Staff (Jackets, gloves, headgear etc ) ‘’ 10 Svy of Asphalt plts ex 763 CTE and 21 EB ‘’ 11 Svy of Layby areas by team ex 101 EB ‘’ 12 Proc of chairs for TPs ‘’ 13 Svy of Extn at MTP KSK by Contr ‘’ 14 JMF ( Revalidation of prev JMF and new JMF for sec-1) ‘’ 15 Renov work (Play area) at FMHS ‘’ 16 Svy of Motorway MCW by ZEERUK ‘’ 17 Instl of RD markers ‘’ 18 Uplift of Balkasar Camp ‘’ 19 Uplift of ITP Kalar Kahar ‘’ UPDATE – PRI TASKS (COMPLETED)
Ser Description Status Remarks 20 Instl of Asphalt Plt ‘’ • Instl of asphalt plt completed, minor maint in progress 21 Instl / repair of Concrete plt at Sumbal ‘’ 22 Lane Mk and Kerb Stone paint at Police Trg School Lhr ‘’ Lane Mk with CR Paint (2km) and Kerb Stone Paint completed 23 Sign Bds for M Tag / Non M Tag lanes (MTPs/ ITPs) ‘’ FA accorded, CA under process • 30 x Sign Bds instl at ITPs in Sec -3 • 40 x sign bds instl at ITPs in Sec – 2 • 31 x sign bds Instl at ITPs sec – I 24 Const of Precast Bdry wall at RD 349 ‘’ 100 % completed UPDATE – PRI TASKS (COMPLETED)
Ser Description Status Remarks 1 Proc of Tfc Diversion set Pended Min sheet fwd to HQ 498 GP for rel of funds (Rs 76 Mn) from HQ FWO Diversion Sign Bds 77 x Sign Bds del Remaining under prep 28 x Info Sign Bds del Diversion Items Del 140 x Plastic Barriers 300 x safety Cones 30 x Safety reflective wests 12 x tires 6 x Barrels 30 x Safety helmets Aluminum Plates for 200 x diversion ladder (45 x Plastic NJBs and 100 x Cones Placed at MTP Ravi) 2 Proc of Crush for asphalt ‘’ 2 x Dump trks del at Balkasar plt 3 Rehab Proj ( Tfr of plt / eqpt to 101 EB ) Under Progress 2 x PTRs, 1 x Tandem Roller, 1 x Bitumen distributer and 1 x Asphalt Paver (755 CTE) received at Thallian Camp Plt pieces received are under repair 1 x Asphalt paver tfr to 765 CTE 2 x TMs under repair at Base Wksp being made aval for Rehab 4 Uplift of KQD Camp ‘’ • 98 % completed UPDATE – PRI TASKS (REHAB)
Ser Description Status Remarks 1 Uplift of Layby Areas Under Progress Work in Progress at 9 x Layby areas RD 349 North Paint of lintel Louvers - 100% Brickwork parapet wall – 100% Brickwork of bdry wall– 100% Plaster work – 100% Grill instl – 100% Aluminum Cladding – 100% Curb Stone – 100% Repair work pub facilities – 40% Masjid fiber shed – 100% Graffito work - 100% Tuff Paver Repair – 20 % RD 349 South lintel Leveling - 100% Plaster work – 100% Aluminum Cladding – 100% Repair work pub facilities – 70% Masjid fiber shed – 100% Graffito work - 100% Brickwork of parapet wall- 100% Plaster work parapet wall- 100 % RD 274 North Brickwork parapet wall – 100% Brickwork of bdry wall– 100% Plaster work – 100% Grill instl – 100% Aluminum Cladding – 100% Masjid fiber shed – 40% Horticulture – 100% Lintel Louvers - Pending UPDATE – PRI TASKS
Ser Description Status Remarks 1 Uplift of Layby Areas Under Progress RD 274 South Brickwork parapet wall – 100% Brickwork of bdry wall– 100% Plaster work – 100% Grill instl – 100% Aluminum Cladding – 100% Masjid fiber shed – 45% Horticulture – 100% Parking Area bdry wall – 100% RD 256 North Brickwork parapet wall – 100% Brickwork of bdry wall– 100% Plaster work – 100% Grill instl – 100% Aluminum Cladding – 30% Masjid fiber shed – 50% Horticulture – 100% RD 256 South Brickwork parapet wall – 100% Brickwork of bdry wall– 100% Plaster work – 100% Grill instl – 100% Aluminum Cladding – 50% Masjid fiber shed – 30% Horticulture – 100% RD 209 South Brickwork backwall wall – 100% Brickwork of bdry wall– 100% Plaster work – 100% Grill instl – 100% Horticulture – 100% UPDATE – PRI TASKS
Ser Description Status Remarks 1 Uplift of Layby Areas Under Progress RD 109 North Brickwork Parapet wall – 30% Brickwork of bdry wall– 100% Plaster work bdry wall– 100% Plaster work parapet wall–5% Grill instl – 100% Horticulture – 70% Fiber Shed- 100% RD 109 South Brickwork backwall wall – 100% Brickwork of bdry wall– 100% Plaster work bdry wall – 100% Grill instl – 80% Horticulture – 70% Fiber Shed- 100% 2 Str design of Jnr Sec at FMHS Design Firm Finalized Site visit by rep of Firm completed Minute Sheet and MOU being fwd UPDATE – PRI TASKS
Ser Description Status Remarks 3 Magic River Proj ‘’ Fresh copies of draft MOU being fwd to HQ 498 O&M Gp • Const dwgs ,design report & BOQs of retaining wall and earth fill fwd to Gp HQ via Email Storm water drainage, water sup and sewerage sys in progress 4 Uplift of MSAs ‘’ Svy of 10 x MSA completed • Prep of 2D line plan completed, est of repair works under progress • 3D prep completed for façade uplift in progress 25 Mar given by COO MORE for brief on MSAs 5 Repair of Steel Pedestrian Brs ‘’ 1. Maj Repair ( 5 x brs ) a. RD - 5 : 100 % completed b. RD - 9: 100% Completed c. RD - 10: 100 % Completed d. RD - 134: 100 % completed e. RD - 312: 100 % completed 2. Minor Repair (6 x brs ) a. RD - 18: 20% completed b. RD - 91: 100 % completed c. RD - 122: 40% completed d. RD - 136: 85 % completed e. RD - 197: 100 % completed f. RD - 315: Contr being mob 6 Instl of sign bds & electronic Chevrons at Salt Rg ‘’ 8 x Sign bds Instl at RD 229, 231 & 232 3 x New Sign bd Instl at RD 232 (S) & 223 +500 (S) Prep of elec chevrons on 8 th bend completed 7 Sign bd repair Under Progress 25 x Sign bds Instl 19 x Bds under prep by ZKS 2 x Sign Bds out of 41 del by BRICS (FA of 41 x bds approved) UPDATE – PRI TASKS
Ser Description Status Remarks 8 Repair of damaged gd rail ‘’ Received after repair : 1335 m Instl at site 1. Sec – 1: 294 m 2. Sec – 2: 629 m 3. Sec – 3: 170 m 9 Extn at MTP KSK “ Lean for Rigid pavement : 0+160 to 0+240 (NB) – Completed • Lean for Rigid Pavement : 0+040 to 0+120 (NB) – Completed • Sub grade : 0 + 065 to 0+ 120 (SB) – 2 nd Layer Completed Sub base: 0+040 to 0+080 (NB) – 2 nd layer completed Sub base: 0+040 to 0+120 (SB) – 2 nd layer completed Sub base (Shoulder): 0+40 to 0+120 (NB) – 3 nd layer in progress Sub base (shoulder): 0+160 to 0+280 (NB) – 4 nd layer completed Bed concrete for cattle creep completed, walls 50% completed Pipe Culvert – Pipe Laying and concrete completed, bk filling and wing wall complete Rigid payment at RD 0+160 to 0+200 in progress 58 x tons steel del at site 10 Emergency exit staircase at FMHS ‘’ • Prep of fdn for Staircase bed completed Welding / fixing of columns/ frame work 90% completed 11 Renovation of GRs ‘’ • Brick Masonry wall completed Instl of precast roof completed Conduiting for elec work and plaster work completed Instl of elec cables and plumbing completed Instl of ceiling in progress 12 Renovation of BOQs ‘’ • Renov of 4 x BOQs completed 13 Uplift of Emergency Climbs ‘’ • Excavation and Sand filling completed Const concrete str for confinement completed Instl of perforated GI Pipe Completed Instl of used tires completed 14 Repair of Toll Booth Chairs ‘’ 35 out of 120 x chairs repaired, 24 x chairs under repair UPDATE – PRI TASKS
EXTN / WIDENING AT MTP KSK 18-10-2023 MTP KSK (Sec-I)
EXTN / WIDENING AT MTP KSK 18-10-2023 MTP KSK (Sec-I)
PEDESTRIAN BRIDGE - PAINT RD - 122+000 (Sec-II)
MASONRY WORK 18-10-2023 RD - 274+000 (N) (Sec-III ) After Before
REMOVAL OF TUFF TILES 18-10-2023 RD - 349+000 (N) (Sec-III ) After Before