District schedule rates (DSR), specification of items of work as per PWD, Specification of PCC work, Measurement of work as per IS 1200
Size: 186.11 KB
Language: en
Added: Jul 04, 2020
Slides: 14 pages
Slide Content
ESTIMATING & COSTING Topic: District Schedule Rates (DSR), Specification of items of work as per PWD Presented by: Ms. Ashwini A. Chaudhari Lecturer, Department of Civil Engineering, R. C. Patel Polytechnic, Shirpur
District Schedule Rates (DSR): Printed Booklet having rates of different works. List of different items of work. Serves as a guide in deciding rates of various items of work. If rates of contractor differs much from DSR rates, his tender may be rejected.
Measurement of work as per IS:1200 Lengths shall be measured to the nearest 0.01m. Areas shall be measured to the nearest 0.01m 2 . Volumes shall be measured to the nearest 0.01m 3 .
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 1. Cement: OPC Fresh Stock If stored for more than 60 days, test before using
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 2. Coarse Aggregate: Of hard broken stones (about 40mm) Free from dust, organic materials Well graded Lesser voids
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 3. Fine Aggregate: Of coarse sand (about 4.75 mm) Free from dust, organic materials Hard, sharp, angular In dry condition
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 4. Water: Clean & Potable Free from acidic and alkaline matters Free from other impurities
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 5. Proportion: Must be measured using a Box Volume of Box must be equal to volume of 1 bag of cement Take 1 bag cement; 4 boxes Fine Aggregate and 8 boxes of Coarse Aggregate
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 6. a. Machine Mixing: First put Coarse agg . fine agg cement in hopper. Let this dry mixture be mixed for at least 4 turns of hopper Then add water slowly Mix this mixture for at least 2 minutes Get a uniform colored and consistent mixture
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 6. b. Hand Mixing: First dry mix Coarse agg ., fine agg ., and cement on a smooth platform. Slowly add water and mix again. Mix shall be turned 3 times in dry condition and 3 times in wet condition. It gives you a consistent and workable mixture.
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 7. Laying and Compacting: Before laying concrete in trench, sprinkle some water Concrete is laid slowly in layers not more than 20 cm and compacted before putting another layer Before 2 nd layer is laid, make top surface of 1 st layer rough All this process should be free from dust, leaves, earth etc.
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 8. Curing: Concrete must be kept wet for at least 7 days Curing using Gunny Bags or sprinkling water at regular intervals
Specification of items of work as per PWD: (A) PCC 1:4:8 for Foundation Concrete: 9. Measurements: Measurement shall be taken in cu.m for finished concrete Measurements (Length, Breadth and Depth) shall be accurate up to 0.01m.