DOUBLE WALL COFFER DAM civil engineering

nandanh1416 1 views 12 slides May 11, 2025
Slide 1
Slide 1 of 12
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12

About This Presentation

DOUBLE WALL COFFER DAM civil engineering


Slide Content

DOUBLE WALL COFFER DAM By, NITHIN KUMAR

INTRODUCTION The design and construction of a double wall coffer dam is a specialized process used in civil engineering projects , particularly when working on projects such as bridge foundations, tunnels, or piers in bodies of water. A double wall coffer dam is often employed to create a dry working area in water by enclosing an area with two concentric walls of barriers, allowing for the dewatering of the area between the walls.

KEY ELEMENTS IN THE DESIGN OF A DOUBLE WALL COFFER DAM Outer wall (Primary wall) 1. The outer wall is typically the first barrier construction, designed to withstand the hydrostatic pressure of the surrounding water. 2. it is often made of sheet piles or other impermeable materials such as steel or reinforced concrete 3. The outer wall should be sufficiently robust to resist forces such as water pressure, wave action, and potential impacts from debris or vessels.

Inner Wall (Secondary Wall) 1. The inner wall is built inside the outer wall and serves as a secondary containment barrier 2. It provides added security by limiting water leakage and ensuring stability in the event of damage to the outer wall. 3. This wall may be constructed with similar materials to the outer wall, but can also include methods such as slurry walls or reinforced concrete if the outer wall is sheet piling Foundation and bottom Seal 1. The cofferdam must have an adequate foundation that anchors the outer wall and provides stability against water pressure and soil movement. 2. A botto m seal is essential to prevent water from seeping underneath the cofferdam. This is typically done by driving sheet piles into the riverbed, applying bentonite slurry or using impermeable membranes. Water removal systems. 1. once the cofferdam is in place, continuous pumping or dewatering systems are needed to maintain a dry environment within the cofferdam. Sump pumps or well points are commonly used to lower the water level inside. 2. Monitoring systems to detect leakage are also important.

Access for construction workers and Equipment 1. Temporary bridges or causeways may be built to provide safe access into the cofferdam area for construction workers and heavy equipment. 2. For very large cofferdams, cranes or barges may be used for construction and material handling.

CONSTRUCTION PROCESS OF A DOUBLE WALL COFFER DAM Site preparation and surveying 1. The first step is to conduct a detailed survey of the site to understand the water depth, soil conditions, and expected water pressures. 2. Temporary access roads or barges are often needed to bring equipment and materials to the construction site. Outer wall installation 1. Sheet Piling Method- Sheet piles ( steel, concrete, or composite ) are driven into the ground using vibratory or impact driving methods. These piles from the outer barrier. 2. The outer wall must be installed to a depth that ensures adequate stability and resistance against water forces. The outer edge of the cofferdam may also be anchored to the bedrock or deep into the soil to prevent movement.

Formation of the inner wall 1. Once the outer wall is completed, the inner wall is constructed. The method of construction depends on the specifics site conditions and design. It involves additional sheet piles or a concrete barrier, or in some cases, a slurry wall can be used. 2. The inner wall is typically placed to a similar depth or slightly shallower than the outer wall to provide redundancy. Dewatering and waterproofing 1. After the walls are erected, dewatering equipment is set up inside the coffer dam to lower the water level and maintain a dry working environment. 2. A bottom seal or membrane may be added to ensure the water does not seep beneath the cofferdam. This could include installing a bentonite slurry or impermeable membrane. Additional structural Elements 1. Anchoring- Additional anchor piles or tiebacks are installed to stabilize both the outer and inner walls 2. Dewatering wells and pumps- sump pumps or wellpoint systems are used to manage the water inside the cofferdam during construction activities. Access construction 1. Temporary platforms, bridges, or ramps may be constructed to allow workers and machinery to safely enter the dry area within the cofferdam. 2. This also includes ensuring that utilities such as lighting and power are available to support construction operations.

Monitoring and Maintenance 1. During the construction phase, continuous monitoring is critical. This includes checking for water seepage or wall movement, as well as ensuring that dewatering systems are functioning properly. 2. Maintenance of the cofferdam may involves repairing leaks or reinforcing sections that show signs of movement or wear. DESIGN CONSIDERATIONS 1. Hydrostatic pressure :- The design must account for the water pressure acting on the cofferdam, especially the outer wall, as it must be designed to withstand both static and dynamic loads ( e.g. waves or boat traffic ) 2 . Soil and bedrock conditions :- The soil and bedrock conditions impact the design, particularly in terms of foundation depth and the installation of anchors. For ex. Soft soils might require additional stabilization techniques. 3. Safety:- Structural safety is paramount. The cofferdam design should be robust enough to prevent collapse or failure, ensuring that workers are safe from sudden water intrusion. 4. Environment Impact:- The cofferdam should be designed to minimize environmental disruption, particularly to aquatic habitats, during construction.

ADVANTAGES OF DOUBLE- WALL COFFERDAM Enhanced Stability:- The two-layer structure provides increased resistance to external water pressure, reducing the risk of failure. Redundancy :- in the event of a breach in the outer wall, the inner wall provides a backup Flexibility:- Double wall cofferdam can be customized for a variety of site conditions, form shallow waters to deep, turbulent environments. Lower water leakage:- The two walls reduce the potential for water seepage, ensuring a more controlled and dry construction environment.

DISADVANTAGE OF COFFERDAM Cost- Double wall cofferdam tend to be more expensive to design and construct than single wall alternatives due to the complexity of construction and the materials involved. Construction Time- The additional wall and structural elements increase the overall time required for construction Materials Requirements – The amount of materials required for both walls and dewatering systems can be substantial, making it less efficient in some cases.

CONCLUSION The construction of a double- wall cofferdam is an effective method for providing a stable and dry work environment in water bodies, particularly when the external conditions are challenging. It involves careful design, including the choice of materials for both walls, as well as careful planning of dewatering systems, access, and structural monitoring to ensure safety and functionality.

THANK YOU
Tags