Flowchart Steel Structure


Slide Content

INSPECTION OF WORKING AREA & TOOL PREPARATION OF WORKING AREA & TOOL START PIC CHECK AND B RIEFING BEFORE ERECTION FINISH INSPECTION OF PLATFORM INSTALL PLATFORM (SCAFFOLDING + STAIR + ASIBA) CHECK RESULT OF UNINSTALL ROOF CANOPY CHECK NO YES CHECK YES CHECK NO CHECK NO YES YES NO START WORKING UNISTALL PLATFORM CHECK NO YES

START U NLOADING MATERIAL FINISH WORK ROAD ERECTION COLUMN INSTALL BONDECK INSTALL STAIR PREPARATION ERECTION AND INSTALL STEEL MEMBER INSTALL RAFTER TOUCH UP PAINT GROUTING BASE PLATE INSTALL FLOOR MEMBER INSTALL WIREMESH INSTALL STEEL GRATING INSTALL ROOF & WALL MEMBER FINISHING INSTALL ROOF INSTALL WALL INSTALL FLASHING AND RWDP

START U NLOADING MATERIAL FINISH WORK ROAD ERECTION COLUMN INSTALL BONDECK INSTALL STAIR PREPARATION ERECTION AND INSTALL STEEL MEMBER INSTALL RAFTER TOUCH UP PAINT GROUTING BASE PLATE INSTALL FLOOR MEMBER INSTALL WIREMESH INSTALL STEEL GRATING INSTALL ROOF & WALL MEMBER FINISHING INSTALL ROOF INSTALL WALL INSTALL FLASHING AND RWDP

H EAVIEST CRANE MOVE TO WORKING ROAD START CHECK MOVE TEST, JACKING TEST, LOAD TEST NO FINISH STACKING STEEL PLATES AT WORKING ROAD LEVELING AND COMPACTION WORKING ROAD CHECK YES NO READY TO STEEL ERECTION YES

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE LIFTING NO FINISH POSITIONING CRANE AND SUPPLY TRUCK PREPARATION LANDING, JACKING, AND LAYDOWN AREA CHECK YES NO READY TO UNLOADING PROCESS YES

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE ERECTION NO FINISH PREPARATION OF WORKING TOOLS POSITIONING CRANE AND STEEL MEMBERS CHECK YES NO INSTALL COLUMN AND TEMPORARY ANCHORAGE ROPE YES INSTALL RAFTER AND STRUT BEAM CHECK VERTICALITY NO INSTALL BRACING AND SETTING YES CHECK BOLT TIGHTENING NO YES CHECK NO YES GROUT BASE PLATE INSTALL STAIR

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE ERECTION NO FINISH PREPARATION OF WORKING TOOLS POSITIONING CRANE AND STEEL MEMBERS CHECK YES NO INSTALL SCAFFOLDING AND TEMPORARY ANCHORAGE ROPE YES INSTALL RAFTER AND STRUT BEAM CHECK VERTICALITY NO INSTALL BRACING AND SETTING YES CHECK BOLT TIGHTENING NO YES CHECK NO YES GROUT BASE PLATE INSTALL STAIR INSTALL COLUMN UNINSTALL SCAFFOLDING CHECK

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE ERECTION NO FINISH PREPARATION OF WORKING TOOLS POSITIONING CRANE AND STEEL MEMBERS CHECK YES NO INSTALL COLUMN AND TEMPORARY ANCHORAGE ROPE YES INSTALL RAFTER AND STRUT BEAM CHECK VERTICALITY NO INSTALL BRACING AND SETTING YES CHECK BOLT TIGHTENING NO YES CHECK NO GROUT BASE PLATE INSTALL STAIR BOLT TIGHTENING CHECK NO YES YES INSTALL RAILING AND OTHER MEMBERS

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE ERECTION NO FINISH PREPARATION OF WORKING TOOLS POSITIONING CRANE AND BONDECK MATERIAL CHECK YES NO LIFTING BONDECK YES INSTALL BONDECK AND SHEAR CONNECTOR CHECK TOUCH UP PAINT NO L IFTING AND INSTALL WIREMESH YES CHECK INSTALL END STOP FORMWORK NO YES CHECK NO YES NEXT STEP (MS POURING)

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE ERECTION NO FINISH PREPARATION OF WORKING TOOLS POSITIONING CRANE AND BONDECK MATERIAL CHECK YES NO LIFTING BONDECK YES INSTALL BONDECK AND SHEAR CONNECTOR CHECK TOUCH UP PAINT NO L IFTING AND INSTALL WIREMESH YES CHECK INSTALL END STOP FORMWORK NO YES CHECK NO YES NEXT STEP (MS POURING)

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE LIFTING NO FINISH INSTALL PURLIN AND GIRT ROOF AND WALL POSITIONING CRANE AND MATERIAL ROOF AND WALL CHECK YES NO YES CHECK INSTALL GUTTER NO INSTALL ROOFING AND WALLING YES CHECK INSTALL FLASING AND RWDP NO YES CHECK NO YES

INSTALL BARRICADE AND PROTECT LIFTING AREA (LINE OF FIRE) START CHECK PIC CHECK AND B RIEFING BEFORE LIFTING NO FINISH INSTALL PURLIN AND GIRT ROOF AND WALL POSITIONING CRANE AND MATERIAL ROOF AND WALL CHECK YES NO YES CHECK INSTALL GUTTER NO INSTALL ROOFING AND WALLING YES CHECK INSTALL FLASING AND RWDP NO YES CHECK NO YES GROUTING BASE PLATE

H EAVIEST CRANE MOVE TO WORKING ROAD START CHECK MOVE TEST, JACKING TEST, LOAD TEST NO FINISH TECHNICAL QUERY FIND VARIATION CHECK YES NO READY TO STEEL ERECTION YES TENDER DOC. IFT VS IFC NEW ITEM C OSTED