10
Action Items To Be Completed: Each member has now been
assigned these tasks:
Darlene Interview software users February
23
Pulchra Get product specifications from
vendors
February
25
Apple Add info from Darlene & Pulchra, then
take paper to writing center
February
25
Dianne Fine-tune the rough draft for final
printing
February
27
Anticipated Problems : Our progress is still on
schedule. However, we anticipate difficulty in cohesively
bringing together the two pages each team member has
written for the rough draft. We will overcome this problem
through careful proofreading, revising and editing along with
help from the writing center.
By February 24, you will have another updated progress
report from our team. If you would like further information,
please contact us via e-mail at
[email protected].