Installation of Metering System at Distribution Transformer Centers
Application of DTC Metering Analysis of DTC meter is not merely used for the energy gap but also give healthiness of transformer . Application : Load unbalancing in system. Voltage unbalancing . Utilization of Transformer Power off duration . Improvement of transformer loading
DTC Meter Specification & Feature Specification Make : Secure Type : 3 Phase 4 Wire Accuracy Class :0.5s Ref Voltage : 3 x 240 V AC, 50 Hz Serial No : T4000XXXX Current Rating :100/5 A Meter constant : 400 Imp/ Unit Feature 35 days midnight data . Phase wise voltage . Phase wise active power. Phase wise apparent power. Power of duration . Absolute Active energy
DTC Meter Installation Process Site Selection UG Fencing Feeder Metering System Installation. A. Meter Installation Fence Mounted Pole Mounted Wall Mounted B. CT Installation FSP Bushing C. PT Supply Directly being fed from FSP/Transformer LT side D. Control cabling With proper demarcation of the Control cable connection to CT & PT Unit of the meter installed is provided.
DTC Metering Installation Process 3. Scope of Work : DTC location & material will be issued by Torrent representative. Transportation of materials from company’s stores to site and vice versa will be done by contractor . The installation of Meter box , Meter & CT’s , laying & termination of control cable ,furling , lugging etc will be done by contactor . Installation completion report filled by contactor supervisor in prescribed format . Sealing ,Testing & CMRI of installation done by TPL site engineer . Material used in DTC metering installation is conformed by TPL site engineer in prescribed format . Removal of existing metering system including meter box, meters, cables etc wherever exists will be done by contractor .
DTC Metering Installation Process 4. Testing & Verification: A. Testing & Data Collection Installation details of DTC Metering system done by TPL site Engineer. Testing & validation of MF Metering system done by TPL site Engineer. CMRI data collection done by TPL site Engineer Sealing of Energy Metering system done by TPL site Engineer. B. Data Dumping & Analysis Onsite data collected is dumped into system server . Analysis of Data Collected at site to verify installation system .
Installation Model-One CT’s are installed in FSP
Installation Model-two CT’s are installed at Transformer Bushing
Energy Audit – EHV to DTC 33 kV Line Loss 11 kV Line Loss Power Tr Loss DTC Loss
Energy Audit – EHV to DTC Database Sr . No . EHV SubStation Power Transformer 33 kV Feeder 33 kV SubStation 11 kV Feeder DTC Feeder Wise DTC EHV S/s wise 1 220/132/33 kV Sikandra Tr-I ( 40 MVA ) 33 kV Riggs Division (40 MVA TR) 33 kV Riggs S/s 3 95 1047 33 kV Dayalbag 33/11 kV Dayalbagh S/s 6 239 33 kV Shanti Nagar S/S 3 104 Tr-II ( 63 MVA ) 33 kV Guru Ka Tal 33/11 kV Guru Ka Taal S/s 4 127 33/11 kV Tota Ka Taal S/s 3 64 33/11 kV T.P. Nagar S/s 2 21 Tr -III ( 60 MVA ) 33 kV Medical (60 MVA TR) 33/11 Raja Mandi 5 70 33/11 New Agra 3 42 33 kV Sanjay Place (60 MVA TR) 33/11 kV Shah Talkies S/s 6 151 33 kV Hariparvat (60 MVA TR) 33/11 kV Sanjay Place S/s 8 134 2 132/33 KV Foundry Nagar Tr-I ( 40 MVA ) 33 kV Trans Yamuna 33/11 kV Trans Yamuna Bank S/s 4 33 651 33 kV TR-10 MVA 33/11 kV Mandi Samiti S/s 3 76 33 kV Jack Bus ( Kamla Nagar) 33/11 kV Kamla Nagar S/s 7 149 33/11 kV Balkeshwar S/s 4 46 Tr-II ( 63 MVA ) 33 kV Kalindi Vihar 33/11 kV Nandlalpur S/s 3 57 33/11 kV Foundry Nagar S/s 4 79 33 kV TR-8 MVA 33/11 kV Mandi Samiti S/s 3 23 33 kV Water works 33/11 kV Free Gunj S/s 3 51 33/11 kV water Works S/s 3 21 33/11 kV Dhuliya Gunj S/s 3 31 33 kV Yamuna Bank 33/11 kV Yamuna Bank S/s 5 85 3 220kV/132/33 KV Shamshabad Tr-I ( 40 MVA ) 33 kV ADA Feeder 33/11 kV Taj Nagri Phase-II S/s 3 66 66 4 132/33 kV Agra Cantt Tr-I ( 40 MVA ) 33 kV Air Force Feeder 33/11 kV Aziz Pur S/s 4 54 117 Tr-II ( 40 MVA ) 33 kV Sadar Feeder 33/11 kV Gwalior Road S/s 3 63 33 kV S J Ice & Cold Storage
Energy Audit – EHV to DTC Energy Input at EHV Substation @ 08:00 Hrs Energy Input at 33kV Substation @ 08:00 Hrs 3. Energy Input at DTC Consumer Mapped DTC wise Consumer Billing date/Lot are fixed Consumption of Consumer from IT DTC Meter data collection date will be next day of consumer reading date Monthly DTC energy input from Mid night data of load survey %Energy Gap = (DTC Consumed Energy –Consumer Energy) x100 DTC Consumer Energy
Alteration , Maintenance & Breakdown of DTC 1. Addition of New DTC In case of New installation of DTC , the respective department will intimate to EA cell. EA cell will installed the DTC metering system. 2. Removal of DTC In case of Removal of DTC , the respective department will intimate to EA cell EA cell will removed the installed DTC metering system. 3. Preventive Maintenance of DTC Metering Requirement of maintenance of DTC metering will be identified by EA cell. Maintenance & Reworking of External CT’s will be done by MMR along with EA department . Replacement of Meter will be done by EA cell .
Alteration , Maintenance & Breakdown of DTC 4. Breakdown Maintenance of DTC The CT’s of metering system are marks with Red , Yellow , Blue ( For respected Phase ). In case of Breakdown of DTC , Breakdown team remove & put in same manner. The direction of arrow ( Upward direction -P1 to P2 ) marks are mention each on CT’s . Breakdown team put CT’s in respective phase with Arrow in upward direction .