About This Presentation

Field training for construction activities at a school as a public building provides practical experience and firsthand insight into the various aspects of the construction process. This training is essential for understanding the complexities and requirements involved in building a safe, functional...


Slide Content

Presentation on Civil Engineering- construction site training

CONSTRUCTION SITE DETAILS Name of building: Ashram School, Ashta. Location: Anand colony, Ashta. Floors: G + 3 Columns: 36 Purpose: School. Area: 6000 sq.ft Project duration: 4 years. Client: Sant Dnyaneshwar Shikshan Sanstha. Engineer: Mr. Sanjay Patil. Site engineer: Mr. Akshay Patil. Architect: Mr. Prakash Jadhav. Structural consultant: Dr. A.B.Kulkarni.

WORKING DRAWING- BRICKWORK

DAY 1 TO DAY 7- BRICKWORK Materials required: Bricks, Cement, sand, water. Type of brick : Burnt clay brick. Sizes: 9”x6”x4” & 9”x4”x4” Proportion used: 1:6 (Cement: sand) Morter thickness: 1” to 1.5” Water : required per (50kg) bag of cement...20-30 litres. Bond type: Flemish bond. Work done: Secondary capacity (2 rooms), bathrooms(6x2) Manpower: Site engineer: 1 Male labour: 5 Female labour: 2 Equipments used: Trowel, spade, float, pan, plumb bob, bucket, wheel borrow.

Preparation of morter Brickwork of secondary capacity(R1) Brickwork of secondary capacity(R2) Brickwork of toilet & bathrooms BRICKWORK

DAY 8 TO DAY 14 - PLASTERING Materials required: Cement, sand, sea sand, water Equipments required: Trowel, spade, bucket, float. Safety equipments used: Helmet, hand gloves, shoes. Mix proportion used as: a) For external wall- 1:4 b) For internal wall- 1:6 c) For sealing- 1:4 Thickness of plastering: 1’’ to 1.5’’ Manpower: Site engineer: 1 Male labour: 6

Plastering of secondary capacity(R2) Internal wall plastering Mixing Internal wall plastering PLASTERING

DAY 15 TO DAY 21- DADOWORK Material details: Tile: 600x600x7 mm. Vitrified-Ceramic type (Rs.56 per ft 2 ) Cement: Chettinad, PPC, 43 grade. (Rs.320 per 50 kg bag) Chemical(Mapie) : RS.1305 per 20 kg bag Vetra glue: 20 g bottle ,Rs.50 , Spacers: 4 mm,100 pcs, Rs.125 Equipment details: Spade, bucket, pan, trowel, hammer, tile cutting machine, marker, clamps. Manpower: Site engineer-1 Contractor-1 Male labour-4

Spacers- 50 nos/pack Mapei hemical-20 kg bag Vetra- fevibond Dadowork for bathroom Use of clamp DADOWORK

DAY 22 TO DAY 28-BEAM AND SLAB REINFORCEMENT Slab reinforcement details: Steel: Rajuri 550 25 mm cover (tile cut). These are to be put after 4 bars interval. Main and distribution bars: 10 mm and 8 mm bars. Material and equipments: Steel bars, binding wire, hook, die( for steel bar bending) Slab type used: One way: L/S>=2 Two way: L/S<2 (In place of toilet and bathrooms) Beam r einforcement details: Steel: Rajuri 550 Beam size: 650×230 (Cover 100 mm) Stirrup dimension : 10 mm. Anchor: 16 mm Bottom Bars: 25 mm. Distance between two stirrups: At end: 100 mm. At centre: 175 mm. Cover: 25 mm Material and equipments: Steel bars, binding wire, hook, die(bar bending rod).

Spacing between bars: 100 mm Slab reinforcement Arrangement of beam Construction of two way slab Construction of one way slab REINFORCEMENT

Slab work details: Slab thickness: 150 mm.(total). Equipment details: Vibrator: 2 Hammer for reinforcement fitting: 4. Wheel borrow: 3 Pole: 1 Wheel borrow lifting machine RMC plant. Concrete used: M25 Grade(Mix proportion - 1:1:2). Total labours: 20 Working hours given for slab: 9 hours. DAY 29 & 30- MATERIAL IMPORTATION AND SLAB WORK Importing Materials: Cement: Chettinad Grade: 43, PPC 1520 bags(Rs.320 per bag) Sand: 3- 4 brass Aggregate: 4 brass Binding wire: 12 kg Formwork: As per requirement (At rent) Wooden board: 10 ft, 4 nos.

Material importing: Slab work: