Lecture - 1-2_-_Project_Managementgfi.ppt

destiny0001 5 views 15 slides Jul 25, 2024
Slide 1
Slide 1 of 15
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15

About This Presentation

PM


Slide Content

Project Management

What is a Project?
“Unique process consisting of a set of coordinated
and controlled activitieswith start and finish
dates, undertaken to achieve an objective
conforming to specific requirements, including
constraints of time, cost, quality and resources.”
A Project has;
a planned set of activities
a scope
time, cost, quality and resource constraints
2

What is Project Management?
The art of organising, leading, reportingand
completinga project through people
3

Project Management
Project Management Covers;
Scope Management
Time Management
Cost Management
Human Resource Management
Risk Management
Quality Management
Contract and Procurement Management
Communications Management
4

Project Manager’s Roles
A Good Project Manager;
Takes ownership of the whole project
Is proactive not reactive
Adequately plans the project
Is Authoritative (NOT Authoritarian)
Is Decisive
Is a Good Communicator
Manages by data and facts not uniformed optimism
Leads by example
Has sound Judgement
Is a Motivator
Is Diplomatic
Can Delegate
5

Stakeholder
“A person or group of people who have a vested
interest in the success of an organization and the
environment in which the organization operates”
6

Stakeholder
Sponsor
Funding Body
Customer
Suppliers
End User
Health, Safety and Environment
Maintenance Team
Neighbours/Community/Shareholders
7

Key Points in Project Set-up
Clarity of Scope and Objectives
WBS -clear statement of What is to be done
Resource Requirement
Identification of Risks to be Managed
Establish Costs and Durations
Creation of Project Management Plan (PMP)
8

Project Management Plan –PMP
(Master Document for Project)
PMP defines the following;
Project Objectives, Scope, Deliverables
Stakeholders (Internal & External)
Work to be done (WBS)
Project Organisation and Resources
Project Costing
Project Schedule
Procurement/Contract Strategy
Risk Management
Quality Management
Change Management 9

Project Risk
“Project risk is an uncertain event or
condition that, if it occurs, has a positive or
negative effect on a project objective”.
“A combination of the probability of a
defined threat or opportunity (Likelihood)
and the magnitude of the consequences of
the occurrence (Impact) defines a Risk
Index”.
10

Risk Impact
Threat→Scope → Poor Quality Product
Threat→ Schedule → Late Delivery
Threat→ Cost → Overspending
In addition there are health, safety and
environmental threats that mustbe
managed
11

Risk Management Process
Identify Risks
Assess likelihood and Impact
Rank Risks and Prioritise
Define Risk Management Approach &
Actions
Implement Actions
Monitor & Review
12

Project Monitoring
Typical Monitoring Activities;
Regular reviews of progress against schedule using WBS
Regular review of actual costs against budgeted costs
Regular review of resource loading
Regular progress meetings with project team
Regular meetings with contractors
Production of periodic progress reports
Risk reviews
Inspections/ audits
13

Project Control
Typical Control Activities;
Assign responsibilities at Work Package level
Staged authorisation of work to be done
Staged release of budgets
Ensure PM has a ‘Management Reserve’ under his
control
Seek corrective action reports when work go ‘off
track’ (overrunning or overspending)
Release Management Reserves carefully
Apply change control (if required)
14

Thank You
Tags